JCT contracts Flashcards

1
Q

What does a relevant event mean?

A

If a delay is due to an event specified in contract (cl 2.29) then contractor is entitled to additional time - as decided by the CA/architect.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What generally counts as a relevant event under cl 2.29?

A

Type 1 - employer is liable for these events:

  • variations
  • architect’s instructions
  • antiquities
  • deferment of possession
  • approx. quantities that are not an accurate forecast
  • suspension of contractor’s obligations
  • impediment, prevention or default of employer

Type 2 - neutral - no liability

  • delay by statutory undertaker
  • exceptionally adverse weather conditions
  • loss or damage occasioned by a specified peril or perils
  • civil commotion or terrorism
  • strikes
  • act of Government
  • force majeure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

what does cl 2.6 allow?

A

allows employer to occupy site if contractor agrees and if insurers have been notified.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what does cl 2.7 refer to?

A

work outside the contract which employer intends to carry out: CHECK -DOESNT SOUND RIGHT

1 - if contract allows/provides for the work then contractor should permit work to happen
2 - if contract doesn’t discuss the work then if the contractor agrees and insurers are notified the employer can arrange the work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly