Technical Competencies Flashcards
What is NRM?
- New Rules of Measurement
- 2021 latest publications of all three suites
- Set of standard measurement rules and essential guidance for cost management of construction projects and maintenance work
- Superseded SMM7
What is NRM 1?
Order of cost estimating and cost planning for capital building works
What is NRM 2?
Detailed measurement for building works
What is NRM 3?
- Order of cost estimating and cost planning for building maintenance works.
- Provides tools to provide transfer of cost information from construction team to asset management team.
- Links cost analysis of capital cost with consideration of whole life costing
What is ICMS?
- International Cost Management Standard
- Followed on from IPMS
- Construction cost and carbon emissions
What is the hierarchy of cost management standards?
- ICMS
- Cost prediction professional statement
- NRM
What is the RIBA Plan of Work?
- Organises process of briefing, designing, delivering, maintaining, operating and using a building into 8 stages
- Framework for all disciplines
- Used solely as guidance
- Procurement neutral
What stage should planning be submitted?
Usually at the end of Stage 3 and only earlier if threshold of info required is met
What is Stage 0?
Strategic definition
What is the outcome/ core tasks of Stage 0?
Outcome: Means of achieving Clients requirements confirmed
Tasks:
- Define Clients requirements
- Develop Business Case considering Risks and Budget
- Ratify option that best delivers Clients Requirements
- Review feedback from previous projects
- Undertake site appraisals
What is Stage 1?
Preparation and Briefing
What is the outcome/ core tasks of Stage 1?
Outcome - Project Brief approved by Client and confirmed it can be accommodated on the site
Tasks
- Prepare Project Brief
- Undertake feasibility studies
- Agree project budget
- Source site info including surveys
- Prepare project programme
- Prepare project execution plan
- Source pre-app planning advice
- Start to collate PCI
What is Stage 2 of the RIBA Plan of Work?
Concept design
What is the outcome/ core tasks of Stage 2?
Outcome: Approved Architectural Concept
Core Tasks
- Prepare concept design
- Undertake design reviews
- Prepare stage design programme
- Obtain pre-app planning advice
- Can submit outline Planning
- Agree route to Building Regs compliance
What is Stage 3 of RIBA Plan of Work?
Spatial coordination
What is the outcome/ core tasks at Stage 3?
Outcome - Architectural and engineering information spatially coordination
Core tasks
- Coordination between Architect and Engineer
- Cost exercises
- Test Architectural Concept
- Review design against Building Regs
- Submit Planning Application
What are the two types of planning application
Outline and reserved matters
What is Stage 4 of the RIBA Plan of Work?
Technical design
What are the outcomes/ core tasks involved at Stage 4?
Outcome - All design info required to manufacture and construct the building
Core Tasks
- Develop design
- Prepare and coordinate Building Systems information
- Prepare stage Design Programme
- Submit Building Regs application
- Discharge pre commencement planning conditions
- Prepare construction phase plan
What is Stage 5 of RIBA Plan of Work?
Manufacture and construction
What is the outcome/ tasks involved at Stage 5?
Outcome - Manufacturing, construction and commissioning completed
Tasks
- Finalise Site Logistics
- Manufacture Building Systems and construct building
- Monitor progress against Programme
- Inspect Quality
- Resolve Site Queries
- Commissioning
- Prepare Building Manual
- Comply with Planning Conditions
What is Stage 6 of RIBA Plan of Work?
Handover
What is the outcome/ core tasks of Stage 6?
Outcome - Building handed over, Building Contract concluded
Core tasks
- Hand over building
- Review of project performance
- Seasonal commissioning
- Rectify defects
- Complete initial aftercare tasks
What is Stage 7 of RIBA Plan of Work?
Use
What is the outcome/ core tasks at Stage 7?
Outcome - building used, operated and maintained efficiently
Tasks
- Implement facilities management and asset management
- Undertake post occupancy evaluation
What stage of the RIBA Plan of Work does NRM 1 apply to?
Stage 1-2
What stage of the RIBA Plan of Work does NRM 2 apply to?
Stage 2-4
What stage of the RIBA Plan of Work does NRM 3 apply to?
Stage 6&7
Why is cost planning important through design development?
- Ensures design still aligns with Project Budget
- Managing Clients expectations
- Highlights any cost increases
What is cost checking?
- Ensuring the actual design can be constructed for the various elements within the cost plan
What are the cost planning stages?
- Feasibility estimate
- Cost plan
- Cost checking
- Tender comparison
- Post contract cost control
What is value engineering
- Process designed to maximise value through improving design, enhanced function, reduced cost, reduced risk or reduced whole life cost of the asset being constructed
- Term value means what would be the most economically advantageous price for the optimum product
What does BCIS stand for?
Building cost information service
What is the difference between building cost indices and tender price indices?
- Building cost indices are the cost to the Contractor in construction the building
- Tender price indices are the price the client pays to have a building constructed, they are used to calculate inflation from the base date to the proposed construction start date
What are BCIS average prices?
Split buildings into functions such as industrial, health and welfare, residential etc
What is Spons pricing book?
- Updated every year to account for inflation etc
- Split into 4 editions: Architects/ Builders Pricing Book, M&E, Landscaping and Civil Engineering
- Split into labour, materials and plant
- Split into approximate estimating and measured works sections which is more detailed
What did you include/ how do you produce a Reinstatement Valuation?
- Work out Schedule of Accommodation
- Calculate Demo and Site Clearance - Spons has rates for this
- Use BCIS for building category to calculate building construction cost, incl. Prelims, OH&P and Contingency i.e., serviced offices
- Identify any abnormals i.e., city centre locatio
- Professional fees added
- If adjusting from previous, adjust using BCIS rate or general TPI increase if no specific category
How do D&B and Traditional procurement effect cost
- D&B - risk is priced within the Contractors price, usually higher but more cost certainty
- Traditional - risk is owned by the Employer so they will usually include risk/ contingency below the line
What are the programme differences between D&B and Traditional?
- D&B - quicker start on site as design and construction can overlap
- Traditional - longer programme as design has to be developed prior to start on site
What are the different JCT suites of contract?
- D&B
- Standard Building Contract - with or without quants
- Intermediate
- Minor Works
What are the different types of contract?
- JCT
- NEC
- FIDIC
- Bespoke
Which is the most suitable contract for price certainty
D&B - lump sum contract, Contractor takes on the risk
Which is the most suitable contract for programme benefits
Management contracting or construction management
What is the most suitable contract for quality?
Traditional - Employer more in control of design
What is the most suitable contract for risk?
Design and build - Contractor owns the risk
What are the key payment mechanisms in the contract?
- Contract Particulars defined the IVD date, due date, certificate date, Final Date for Payment, can have amendments which changes the payment timescales
What are Liquidated Damages?
- Genuine pre-estimate of loss the Client would incur if the Contractor failed to complete by the Contract Completion Date
- Rate is specified in the Contract
What needs to be in place to levy LADs?
- Non-Completion Notice
- Withholding notice
What are the change control categories?
- Contractor changes (design changes)
- Employer changes (variations)
What are changes called in NEC?
Compensation events
What is the process of change control for an Employer change?
- Employer agrees scope of change
- Writes and issues instruction in accordance with the contract
- Contractor records change, instigates change and forwards cost/ programme
- Employer accepts or rejects
- Proceed or start again
What does PCR stand for?
Proposed change request
What is a CCR?
Contractor change request
What is a TVR?
Tenant variation request
Why was the construction act amended in 2011?
- Clearer and fairer payment terms
- Improve rights for Contractors to suspended works for non-payment
- Make adjudication more accessible for resolution of disputes
Why are Letters of Intent used?
- To allow Contractors to begin procuring materials, labour, setting up site etc before negotiations for the detailed construction contract have been completed
- Often provide a cap on value or a drop dead date where it will no longer be valid
- Can form a Contract if the terms are clear