Blackbooks Flashcards
What is acceleration?
When the Employer wishes to bring Practical Completion forward, the Contractor may implement measures to do this such as increasing labour/ resources, introducing shifts etc
What are capital allowances?
They permit tax relief on capital expenditure. The main capital allowances are plant and machinery allowances, business premises renovation allowances, flat conversion allowances and research and development allowances
What are the two main types of cash flow forecast?
- Company cash flow
- Project cash flow
What is the purpose of a cash flow?
To ensure the employer has an accurate assessment of what needs to be paid to the Contractor and when and therefore their bank or funder is aware of monthly draw-downs
How did the Construction Act improve payment?
- Statutory right to refer disputes to adjudication
- Introduced right to periodic, interim or stage payments
- Requiring contracts should provide a mechanism to determine what payments become due and when and a final date for payment
What is an S curve?
It represents the lower level of expenditure at the beginning of a project, increase in the middle and decrease again at the end of the project
What does change control mean?
Process that can lead to the alteration of the timescale, cost or scope of the project
What are the two principal categories of change?
- Contractor change
- Employer change
What are some reasons for change?
- Employer
- Ground conditions
- Statutory requirement
- Tender assumptions incorrect
- Specified items unavailable
- Discrepancies in Contract Docs
What is change defined as?
Alteration or modification of design, quality or quantity of the works
What is the difference between SBC and D&B in regards to changes?
In SBC, they’re known as variations whereas in D&B they’re known as changes
What does a commercial manager do?
Maximise the potential of a business in terms of profitability, manage and control internal processes and also external relationships. They monitor financial performance and manage risks.
What are the most common forms of procurement / payment mechanisms?
- Lump sum contracts
- Remeasurement contracts
- Target sum contracts
- Guaranteed maximum price
- Cost reimbursable
- Management contracts
What is a CVR?
Comparison of cost to date vs value to date
Name some forms of ADR
- Adjudication
- Mediation
- Negotiation
What is the process of adjudication?
Any party can refer a dispute to adjudication at any time, by serving notice. An adjudicator should then be appointed in 7 days of the notice, and have 28 days to reach a decision.
What are collateral warranties?
They create a contractual link between a third party and a main party of the contract, so the third party can make a claim if they suffer loss, usually funders or purchasers/ tenants
What are third party rights?
A third party may enforce a term of a contract if the contract expressly provides if may do so, without a collateral warranty being in place.
What is the difference between an on demand and conditional bond?
On demand - do not need to prove there has been a breach
Conditional - Employer has to establish breach by the Contractor
What is a parent company guarantee?
Contract between a parent company and a third party beneficiary where the parent guarantees performance of one of its subsidiaries.
What is the difference between a performance bond and parent company guarantee?
Performance bond provides financial compensation in event of Contractor breach of obligations, whereas PCG is intended to guarantee obligations are performed.
What is cost analysis?
Full appraisal of costs involved in previously constructed buildings aimed at providing reliable information which will assist in accurately estimating costs of future buildings
What important factors need considering when completing cost analysis?
Location and time
What information is required for a cost analysis?
- GIA / NIA
- Number of storeys
- Was there a basement
- Number / type of functional units
- Start on site and completion date
- Type of procurement / contract used
- Location
- Base date
- Contract sum
What is benchmarking?
Overall process of improvement aimed at providing better value for money for employers
What is the base date?
For lump sum contracts, it is usually 10 days before tender return whereas for projects where the price isn’t fixed, it is usually mid point of construction.
Where are the GIA, NIA, GEA defined?
RICS Code of Measuring Practice
What is a prime cost sum?
Financial adjustment of work where the extent is known but the specification has yet to be determined.
What does Practical Completion trigger?
- Client can no longer levy LDs
- Client must insure works
- Commencement of Rectification Period
- Release of retention