Q

A permit for asbestos abatement is good for ____ days from the date of issue and only for the specific project for which it is issued.

A

180

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Asbestos multi story building:

  1. A standard ____ inch by ____ inch black on yellow (Per updated fire code: RED, BLACK, and WHITE) warning sign placed in the Fire Control Room adjacent to the fire alarm annunciator panel
  2. A ____ by ____ inch sign with minimum 3” X 1/2” lettering on a contrasting background, indicating which floors are involved in the abatement process
  3. An additional set of signs shall be placed on each landing in each stairwell which leads to all floors undergoing abatement beginning ____ floors below the affected floor(s) and ___ floor(s) above the affected floor
A
  1. 20”x14”
  2. 12x12”
  3. 2 and 1
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Division 5 Permits are obtained from the Bureau of Fire Prevention’s _____ Unit.

A

Engineering

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

All asbestos projects in L.A. City over ____ square feet require an on-site inspection and a _____ permit.

A

100 sq ft

Division 5

How well did you know this?