If sabotage occurs on Transmission system, who should be notified

A

FBI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Per COM-001, telecommunication shall be

A

redundant and diversely routed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

NERC requires what language to be universally used when communicating among operators/RC’s of the BES

A

English

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is NERCnet

A

a wide area network using frame relay as its communications medium

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Per COM-002, requires each TO, BA and GO to have communications with appropriate RC’s, BA’s and TO’s. These communications include?

A

both voice and data links

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Who is notified when a condition threatens the reliability of its area or when firm load shedding is anticipated?

A

The RC and all other potentially affected BA’s and TO’s

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When testing telecommunications channels, special attention should be given to emergency telecommunications facilities and….

A

equipment not used for routine communications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which entities are expected by NERC to issue directives in a clear, concise and definitive manner?

A

RC’s, TO’s and BA’s

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

PER-005 specifies the requirement for emergency operations training is…

A

32 hours annually

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

PER-001 requires TO’s and BA’s must have the ________ and _______ to implement real-time actions to ensure the stable and reliable operation of the BES

A

responsibility and authority

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

PER-003 NERC requires that TO’s, BA’s and RC’s who fill a real-time operating position be…..

A

certified

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is Generator Shift Factor

A

A factor to be applied to a generator’s expected change in
output to determine the amount of flow contribution that
change in output will impose on an identified transmission
facility or Flowgate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Power Transfer Distribution Factor

A

In the pre-contingency configuration of a system under
study, a measure of the responsiveness or change in
electrical loadings on transmission system Facilities due to
a change in electric power transfer from one area to
another, expressed in percent (up to 100%) of the change
in power transfer. Can be expressed -100 to +100

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

To determine the power transfer distribution factor you take the….

A

amount of MW reduction needed and divide it by the percentage of the lines PTDF…. example 100mw reduction on a line with 70% PTSD 100.7 = 143MW

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

how to figure out generation shift factors (GSF)

A

GSF=[(change in path flow) \ (change in generation)] x 100

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

If a generation shift factor is a negative it…

A

an increase in generation would result in a decrease in transmission line flow, thus relieves line loading, this is because typically the generation increase is close to load

17
Q

The amount of relief determined by generation shift factor is..

A

Take the amount of overload and divide it by the GSF

18
Q

If a generations shift factor is positive it…

A

with decreased generation it will relieve loading on the transmission line

19
Q

How to determine MW impact using GSF’s

A

MW Impact = Genration MW x GSF

20
Q

How does a generation shift factor of .2 affect the transmission line

A

20% of any generation change will be reflected on the transmission line’s flow

21
Q

When there are two generators to adjust using GSF what is the equation

A

Amount of relief (overload) / shift factor A - shift factor B this will be the change in generation for generator B

22
Q

Outage Transfer Distribution Factors help system operators…

A

estimate the effect of an outages transmission elements

23
Q

When power flow is expected to reach or exceed a SOL, what is one of the first things an operator can do.

A

Redistribute power flow to relieve the overload… i.e. generation re-dispatch

24
Q

Vital telecommunications facilities shall be..

A

managed, alarmed , tested and/or actively monitored

25
Q

How to determine difference between vandalism and sabotage

A

intent

26
Q

SOL’s are determined by

A
  • Setting appropriate voltage levels to withstand various contingencies - Identifying equipment loading capability before excessive heat degrades their function - Recognizing stability limitations
27
Q

Certification of operating personnel is necessary to ensure ________ competencies for operation a reliable BES

A

Minimum