EOPS Flashcards

1
Q

Interruptible Load or Interruptible Demand

A

Demand that the end-use customer makes available to its Load-Serving Entity via contract or agreement for curtailment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

BA’s shall have operating agreements with who?

A

adjacents BA’s, these contain provisions for emergency assistance including support from remote BA’s (BA’s that do not touch your BA boundary)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the primary objective of each BA during a capacity or energy emergency?

A

return ACE to an acceptable value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The development of emergency load reduction plan for all IROL violation is the responsibility of who?

A

TO

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the 4 types of plans each TO and BA are required to develop, maintain and implement

A

Generation shortage capacity, transmission systems emergency, load shedding and system restoration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are required to be in the plans

A

communication protocols, control actions (things that will resolve emergency), coordination with other BA’s and TO’s and staffing levels

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

each emergency plan is updated how often

A

annually, and plans are provided to RC and neighboring TO’s and BA’s

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

______ is the rated continuous load carrying ability of generation, transmission or other electrical equipment expressed in MW

A

capcity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the four things a BA must do prior to having an EEA declared

A

Bring on all available generation, postpone equipment maint., scheduling interchange purchases in advance, being prepared to shed firm load load.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When using voltage reduction for energy emergencies, what is the rule of thumb.

A

a 5% reduction in voltage results in a 3% reduction in load

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When an EEA is issued what does the RC do?

A

Start actions to mitigate the emergency (request emergency assistance if needed) and notify all BA’s and TSP in its area also notify all other RC’s

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

There are two reasons an LSE would require an EEA

A

They cannot locate available resources to purchase and they cannot schedule due to available transmission limitations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Describe EEA1

A

all available resources are committed to meet firm load, firm transactions and reserve commitments and non firm wholesale sales have been curtailed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Describe EEA2

A

no longer able to provides the customers expected energy requirements and has started procedures to make up the insufficient energy, like public appeals, voltage reduction, interruptible loads

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Describe EEA3

A

firm customer load is being shed, during EEA3 the deficient BA must give hourly updates to the RC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the two types of automatic load shedding

A

undervolatge and underfrequency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

describe undervolatge load shed

A

load shed that is designed to prevent local area voltage collapse from lack of reactive resources

18
Q

describe underfrequency load shed

A

load that is shed to re-balance load and generation within an electrical island caused by a system disturbance

19
Q

low frequency causes damage to what kind of turbine

A

low pressure blades in steam turbine

20
Q

UVLS is designed to drop loads in

A

pre-selected blocks

21
Q

Each Transmission Operator and Balancing Authority shall establish plans for automatic load shedding for __________ or ___________ conditions

A

underfrequency or undervoltage

22
Q

Which entities has the responsibility to establish plans for load shedding

A

TO and BA

23
Q

why are reports sent to NERC

A

to note lessons learned and implement corrective actions

24
Q

timeframe an entity has to report to NERC

A

initial report is due 24hrs, except if it’s an IROL violation then its 72 hours. final report due in 60 days

25
Q

NERC reporting guildlines are

A

system sepration, firm load shed of 100mw or more, IROL violation, operator error, loss of generation, loss of BES component affecting system integrity, equip. failures or system operational actions resulting in loss of firm system demands for more than 15 mins.

26
Q

define disturbance

A

An unplanned event that produces an abnormal system condition or any perturbation to the electric system or the unexpected change in ACE that is caused by the sudden failure of generation or interruption of load

27
Q

entity experiencing a reportable incident shall provide a preliminary written report to

A

NERC & RRO

28
Q

TO’s shall have restoration plans in the event of partial or total system shutdown, plans must be….

A

updated to reflect changes, reviewed at least annually, developed for restoring interconnection and coordinated with neighboring systems

29
Q

if load must be shed in an island and good rule of thumb is

A

shed 6-10% of connected load will increase frequency by 1hz

30
Q

when restoring load in an island. how much load to be restored at one time.

A

5% of online generations capacity

31
Q

if you are in a island trying to pick up load and there is one 1000 MW generator online generating 500MW, how much load could you pick up?

A

50MW, 5% of 1000

32
Q

When re-synchronizing what are the 3 things that are measured

A

Phase angle. voltage and frequency…if possible phase angle should be 10 derees or less

33
Q

what are some things an operator can do when syncing two islands together when there is a large phase angle

A

re-dispatch generation, change system configuration, shed load

34
Q

True or False: the RC is required to have an RC area restoration plan

A

True

35
Q

What document must RCs sign because of market transaction

A

NERC Reliability Coordinator Standards of Conduct

36
Q

Re-synchronizing with the interconnection should only be attempted where

A

breaker with sync check or generating plant

37
Q

are reliability entities required to have a backup control center

A

no, but they are required to have plan to continue reliable operations, including procedures to address the loss of voice and data…… primary control center is also not required to have redundant power supply

38
Q

What must be included in a plan for the loss of a primary control center

A

basic-tie line control, hourly accounting of all schedules, time and frequency control

39
Q

Implementation of the Capacity and Emergency plan is required and appropriate to

A

reduce risk to the interconnected system

40
Q

Verification of the restoration procedure shall be confirmed by

A

actual testing or by simulation

41
Q

If a Transmission Operator operates a system at a voltage of less than 100 kV, and experiences a restoration event, does this change the Reliability Coordinator’s role in the restoration process

A

no, Standard EOP-006 does not address specific voltage requirements when discussing the role of the Reliability Coordinator in the restoration process

42
Q

most critical issue in implementing a backup control center is its access to

A

voice and data communications