SWYD Flashcards

1
Q

How do the 500kv breakers operate?

A

Air to open/Spring to close

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

at what pressure will the 500kv breaker open?

A

182 psig

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

when does the compressor cycle on and off?

A

200-220 psig

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what PPE is required while operating items in the switchyard?

A
  • hardhat
  • safety glasses
  • rubber gloves
  • leather outer gloves
  • flame retardant suit
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what is the voltage and frequencies range for the switchyard?

A
  • 491 - 525 kv
  • 112.125 - 120.25 kv
  • 58.5 - 61.8 hz
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

In order, what are the preferred methods of operation for breakers in the switchyard?

A
  1. TOC or Control room
  2. relay house
  3. local at control
  4. Local manual (old style)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How are the 34.5 kv breakers operated?

A

Air to close/Spring to open

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Whose permission is required to operate breakers in the switchyard?

A

Shift manager and CRS/TOC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are some safety items to be aware of when operating disconnects in the switchyard?

A

Falling debris

steady deliberate motion

don’t look up

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

explain opening breaker ad disconnect including using kirk key

A
  1. open breaker
  2. open disconnect
  3. remove kirk key from disconnect
  4. install key in ground disconnect, close ground
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How do you place ESF 12 onto 15AA with ESF 11 currently lined up to it?

A

turn on synchroscope to verify “IN SYNC” then close ESF 12 breaker and verify ESF 11 breaker opens

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Why is 13R a dead bus transfer?

A

to prevent OVERLOADING the TRANSFORMER

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

If an ESF transformer locks out, what breakers open?

A

closest to the transformer (19 series) upstream and downstream

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

what breaker will LSS shed?

A

Local breaker at bus

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What can be done if ST21 locks out and the generator starts, but output breaker doesn’t close?

do you need a synchroscope? why?

A

Close diesel output breaker of ESF 12 breaker

No, because the bus is de-energized

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

If transformer is used, what sequence is done?

A

BUV

17
Q

If diesel is used, what sequence is done?

A

LOP