Standard of Performance Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

Hochster v de la Tour (1853) Facts

A

o T spoke to H on April 12 to enter into his services
o Employment was to start on June 1
o On May 11, T told H that his services were no longer required
o H brought an action, although the time of performance had not yet arrived (June 1)
o Held:
• H was entitled to do so
• It was a anticipatory breach
• Only has to wait until contract is made, not until performance is due
• Entitles H to be discharged and to sue for damages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Hochster v de la Tour (1853) Principle

A

Anticipatory breach
• created the doctrine

o Contract says performance has to happen on certain day
o If clear that it wont happen on that date, allows us to terminate when it is clear that it wont happen if they know beforehand
o Terminating is a risky business
• Court may not agree with you
• Must be very obvious

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Schuler v Wickman Machine Tool Sales [1974] Facts

A

o S manufactured tools
o W was a sales company granted the sole right to sell certain tools made by S
o Term of contract, listed as a condition, stated that W would send a sales person to each named company once a week to solicit sales
o Imposed obligation to make 1,400 visits total.
o W failed to make some of the visits
o S terminated the contract for breach of condition
o Held:
• It was only a warranty
• Even though it expressly stated that the term was a condition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Schuler v Wickman Machine Tool Sales [1974] Principle

A

• Construction of the contract

It was only a warranty
• Even though it expressly stated that the term was a condition

• Identifying terms as conditions
Standard was unreasonably high
not a condition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Arcos v Ronaasen [1933] Facts

A
  • Wooden staves
  • Should be1/2 inch thick
  • Some were not thick enough
  • Didn’t meet specific term
  • Held:
  • Not good
  • Said ½ inch , should be that thick
  • Strict liability
  • Sale of goods
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Arcos v Ronaasen [1933] Principle

A

Strict Liability

Supply of Goods

• Didn’t meet specific term
Not good

Breach and termination
The term broken is a major term: a ‘condition’ or ‘of the essence’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

s.13 of the Supply of Goods and Services Act 1982?

A

Standard of reasonable care and skill

  • Adds additional requirements for services
  • Implied term for services that they must be carried out with reasonable care
  • S.14, must be in reasonable time
  • S. 15, if no price, must pay reasonable price
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

4 Ways to Bring a contract to an end?

A

• 1. by the parties performing according to the terms of the contract (the most common outcome)

• 2. by the parties agreeing to abandon/discharge the contract (needs consideration or deed)
o New agreement in and of itself
o Need to abandon needs consideration

• 3. by operation of law (e.g., frustration)
o Misrep, Duress, Mistake, etc…

• 4. By breach
o Usually just one party breaches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Re Moore and Landauer [1921] Facts

A
o	Fruit to be sold in tins
o	Supposed to be packed in cases of 30
o	In the case, packed cases of 24
o	Description said 30
o	Held:
•	Could reject the shipment 
•	S. 15 SOGA 1979
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Re Moore and Landauer [1921] Principle

A

Performance

Parties must perform precisely all the terms of the contract in order to discharge their obligations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Cutter v Powell (1795) Facts

A
  • Seaman
  • C was supposed to do his duty as a sailor
  • Died 2 weeks before end
  • Compensation?
  • Did not perform ALL of his obligations
  • Held:
  • His wife got nothing
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Cutter v Powell (1795) Principle

A

Performance

Parties must perform precisely all the terms of the contract in order to discharge their obligations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Sumpter v Hedges [1898] Facts

A
•	Build stable of C’s land
•	Did part of the work, than abandon the rest of the contract
•	D actually completed the building
•	Can D claim amount of work done
•	Held:
o	No 
o	Cannot recover for partial performance 
o	Entire contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Sumpter v Hedges [1898] Principle

A

Performance
Divisible contracts

Cannot recover for partial performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Roberts v Havelock (1832) Facts

A
•	Repair of a ship
•	Contract did nt say when payment occurred
•	Ship right stopped
•	Can he claim money?
•	Held:
o	Yes
o	Divisible 
o	Can claim part of the money 
•	Difference:
•	Construction of the contract
•	If implied that partial performance can amount to partial payment, then it will be construed as such
•	Courts are reluctant to allow someone to claim payment before completion
•	If in doubt, it is divisible
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Roberts v Havelock (1832) Principle

A

Performance
Divisible contracts

  • If implied that partial performance can amount to partial payment, then it will be construed as such
  • Courts are reluctant to allow someone to claim payment before completion
  • If in doubt, it is divisible
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Christy v Row (1808) Facts

A

• Ship going to Hamburg
• Did not arrive because it was seized by people
• Cargo dropped at other point, still accepted
• Were they liable for cost?
• Held:
o They implied a new contract for the new port
o Could get the expenses incurred
o Cargo was still accepted
o This makes it acceptable to the court

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Christy v Row (1808) Principle

A

Performance
Acceptance for partial performance

• Court can infer new agreement
o This makes it acceptable to the court

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Planche v Colburn (1831) Facts

A
•	P was supposed to write a book
•	Receive £100 for it
•	Publisher abandoned before he started
•	P made 2 claims
•	Held:
o	P could recover money for research completed
o	Not his fault that contract was stopped
o	Not his fault
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Planche v Colburn (1831) Principel

A

Performance
COmpletion of performance prevented by the promise

o P could recover money for research completed
o Not his fault that contract was stopped

  • Quasi contract claim
  • Recover in on quantum merit (something of value)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Dakin v Lee [1916] Facts

A
•	Building a house
•	Had specific specification
•	Did not match of these specifications 
•	Purchasers refused to pay
•	Held:
o	Substantial performance occurred
o	Can receive payment,
o	Minus defective costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Dakin v Lee [1916] Principle

A

Performance
Substantial performance

• if you do pretty much everything under the contract, can be said to have substantially performed obligations under the contract

23
Q

Startup v M’Donald (1843) Facts

A
•	P agreed to sell 10 tons of oil to D at end of March
•	Delivery took place of 31st of march 
•	Said it was too late
•	Held:
o	Still 31st of march
o	Their offer to deliver is ok
o	Could recover for damages
o	S. 29 SOGA
•	Delivery is ok, as long as it is at reasonable hour
•	Reasonable= depends of circumstance
24
Q

Startup v M’Donald (1843) Principle

A

Performance
Tender of performance

o Could recover for damages
o S. 29 SOGA
• Delivery is ok, as long as it is at reasonable hour
• Reasonable= depends of circumstance

25
Q

Stipulations as to time of performance: 2 modifications

A
  1. Section 41 Law of Property Act 1925

    • if no stipulation, than late payment is acceptable
    • might be remedy for damages, but cannot terminate contract
2. Equity
Time is not regarded of the essence
3 exceptions
o	1) Expressly says it is of the essence
o	2) It is clear by notice
o	3) If it is clear from the circumstances that time is of the essence
26
Q

2 Types of Agreements to End a contract?

A

1) Bilateral Discharge

2) Unilateral Discharge

27
Q

4 types of Bilateral Discharge?

A

1) – Accord and satisfaction
o Parties want to terminate present contract

2)– Rescission and substitution
o Terminate existing contract and substitute a new one in its place
o Not rescission!

3) – Variation

o Agreeing the change some of the terms

4)– Waiver
o Agreement to accept less the complete performance under the contract
o Agree to accept tless than promised

28
Q

Diab v Regent Insurance Co Ltd [2006] Facts

A
  • Deals with insurance
  • Insurer said that if he made a claim under the policy, it will be rejected
  • Contract is still alive, still must follow all obligation
  • Important
  • Even if breach of one clause, does not permit you to breach the contract as a whole
29
Q

Diab v Regent Insurance Co Ltd [2006] Principle

A

Breach and Termination

• Even if breach of one clause, does not permit you to breach the contract as a whole

30
Q

Universal Cargo Carriers Corporation v Citati [1957] Facts

A

o Shipping case
o Ship was being chartered
o Wanted to load cargo in July
o Couldn’t find a cargo upon arrival
o Hirer of ship grew impatient
o Cancelled charter party
o Owner wanted to rehire the ship as fast fo possible
o Still had lay-days remaining
o Can the ship be loaded with remaining lay-days?
o Held:
• No, it could not be done
• Ok for them to breach the contract
• Was the breach a condition or warranty?
• If condition, entitled to terminate with damages
• If warranty, only damages
• Held:
• If delay was long enough to frustrate the contract, they can terminate

31
Q

Universal Cargo Carriers Corporation v Citati [1957] Principle

A

Breach and Termination
The other party refuses to perform or is clearly unwilling to do so

  • If condition, entitled to terminate with damages
  • If warranty, only damages
  • Held:
  • If delay was long enough to frustrate the contract, they can terminate

• Other party refused and were unable to perform

• Anticipatory breach
Said Anticipatory breach can happen in 2 ways
1) breacher displays by words or conduct that he will not perform, or
2) he made it impossible for himself to perform on that day
o ex: already sold the goods
• Clear that the breach is going to happen
• Do not need to wait
• Acting on a tip is not good enough
o Must be based on real facts

32
Q

ERG Raffinerie Mediterranee SpA v Chevron USA (The Luxmar) [2007] Facts

A

o Sale of gasoline
o C was selling it to E
o E said it was entitled to terminate the contract because it said it was a traditional FOB contract
o Time of shipment is of the essence in these
o If it was, termination was possible
o Contract itself said there was a 4 day period to load the ship, could be narrowed to 2 days (lay day clause)
o Held:
• Have to read delivery clause as a whole
• Cannot read out 4 day period
• Made it a non-tradition Freight on board (FOB) contract
• Time was no longer of the essence
• Can no longer terminate the contract

33
Q

ERG Raffinerie Mediterranee SpA v Chevron USA (The Luxmar) [2007] Principle

A

Breach and Termination
The other party refuses to perform or is clearly unwilling to do so

  • Have to read delivery clause as a whole
  • Cannot read out 4 day period
  • Made it a non-tradition Freight on board (FOB) contract
  • Time was no longer of the essence
  • Can no longer terminate the contract
34
Q

Mersey Steel & Iron v Naylor, Benzon (1884) Facts

A

o Sale of steel
o R sold 5000 tons to P
o Supposed to delivery 1000 a month
o When started, got in difficulties
o When Buyers found out, they suspended payments
o R didn’t get paid and refused to continue with the contract
o Was this a repudiatory breach?
o Held:
• No
• Because they thought they had the right to not pay
• Did not give rise to the right of termination

35
Q

Mersey Steel & Iron v Naylor, Benzon (1884) Principle

A

Breach and Termination
The other party refuses to perform or is clearly unwilling to do so

  • Because they thought they had the right to not pay
  • Did not give rise to the right of termination
36
Q

Eminence Property Developments Ltd v. Heaney [2010] Facts

A

o CoA gave us a test to look a repudiatory breach
o E sold flats to H
o Contract had standard conditions for sale
o Conditions say time is of the essence only where there is notice to complete
o If purchaser did not complete, seller had right to rescind the contract and claim damages
o Seller served notice, but gave wrong date of complete (15 Dec, rather than 18 Dec)
o Buyer did not complete, but said date was wrong
o Argued that wrong date amounted to rescission of the contract
o Held:
• Sending the notice of rescission was not a repudiatory breach
• Clear that buyer actually knew the actually date and that the seller wanted to complete the contract
• Clear what was intended
• Test:
• If look at all circumstances objectively (reasonable person)
• Have they shown a clear intention to not perform obligations under the contract
• They showed intention to perform

37
Q

Eminence Property Developments Ltd v. Heaney [2010] Principle

A

Breach and Termination
The other party refuses to perform or is clearly unwilling to do so

o CoA gave us a test to look a repudiatory breach
• If look at all circumstances objectively (reasonable person)
• Have they shown a clear intention to not perform obligations under the contract

38
Q

Test for Repudiatory Breach?

A

If look at all circumstances objectively (reasonable person)
• Have they shown a clear intention to not perform obligations under the contract

Eminence Property Developments Ltd v. Heaney [2010]

39
Q

British & Benningtons v NW Cachar Tea [1923] Facts

A

• tea trade case
• question whether the buyers repudiated the contract or not
• buyers argued the seller has to show that he was ready and willing to deliver the tea to get damages
• did not argue that he repudiated
• Held:
o No
o They can still get damages even if they weren’t ready to deliver
o Buyer was the one who breached

40
Q

British & Benningtons v NW Cachar Tea [1923] Principle

A

Breach and Termination
o • The other party is clearly unable to perform

o They can still get damages even if they weren’t ready to deliver
o Buyer was the one who breached

41
Q

Union Eagle Ltd v Golden Achievement Ltd [1997] Facts

A

• sale of land
• completion was supposed to be at 5pm on certain date
• time was expressed to be of the essence
• buyer sent the money 10 mins after 5
• seller said no, rescinded the contract
• Argued that matter of equity, its unfair
• Held:
o Seller won
o Specified date/time to be of the essence is good
o Matter of equity, this is contract for sale of land, no jurisdiction of equity
o Could of made it by 5, did not

42
Q

Union Eagle Ltd v Golden Achievement Ltd [1997] Principle

A

Breach and Termination
The term broken is a major term: a ‘condition’ or ‘of the essence’

o Specified date/time to be of the essence is good
o Matter of equity, this is contract for sale of land, no jurisdiction of equity
o Could of made it by 5, did not

43
Q

15A, Sale of Goods Act 1979?

A

Breach and Termination
The term broken is a major term: a ‘condition’ or ‘of the essence’

  • Gives standard for strict liability for sale of goods is modified
  • Term would normally be a breach of condition (s. 13-15 SOGA 1979)
  • 15a says if breach is so slight that it would be unreasonable for buyer to reject the goods, it is a breach of a warranty rather than condition
  • Only remedy is damages, no termination
  • Courts determine what is reasonable
44
Q

The Mihalis Angelos [1971] Facts

A

• owners of the ship let it to charterers
• contract said it would be ready to load july 1, then go to the destination
• charterer could cancel it if it wasn’t ready by the 20th of july
• charterer could not get a cargo by the 17th and cancelled it
• ship was not ready by the 23rd
• both were in breach of the contract
• argued that the owner was in breach on the 27 (implied term that it would be ready to load on july 1)
o court said term was a condition
o allowed to end the contract on the 17th
• does not matter if it was frustration
• Denning
o Bad reason to terminate does not mean you cant later rely on a good reason to terminate

45
Q

The Mihalis Angelos [1971] Principle

A

Construction of the contract
o • Common usage of the term ‘condition’

• Denning
o Bad reason to terminate does not mean you cant later rely on a good reason to terminate

46
Q

o Bentsen v Taylor [1893] Facts

A
  • Ship sailing from a certain port
  • Contracts say ships need to start at a certain port
  • Courts tend to treat this as a condition
  • Supposed to sail from pitch pine ports to Uk, dated march 29
  • Ship didn’t actually leave until April 23
  • Was this a breach of condition
  • Held:
  • Yes
  • Didn’t leave at appropriate time
  • Didn’t matter because breach was raised in this case
47
Q

o Bentsen v Taylor [1893] Principle

A

Construction of the contract
o • Common usage of the term ‘condition’

  • Didn’t leave at appropriate time
  • Didn’t matter because breach was raised in this case
48
Q

Lombard North Central Finance v Butterworth [1987] Facts

A
  • Involves the lease of a computer from C
  • C was supposed to pay £584, 20 installments every 3 months
  • Lease said prompt payment is required
  • Breach would end up in termination
  • D was behind payments
  • C took possession and sold it for £175
  • C sued D, claiming arrears and all future payment ($7000)
  • Was this term a condition?
  • Held:
  • Yes it was
  • Construction of contract made it clear
  • They both insisted on prompt payment
  • Necessary that payment was prompt
  • Even 1 late payment would allow for termination
49
Q

Lombard North Central Finance v Butterworth [1987] Principle

A

Construction of the contract
o • Common usage of the term ‘condition’

  • Construction of contract made it clear
  • They both insisted on prompt payment
  • Necessary that payment was prompt
  • Even 1 late payment would allow for termination
50
Q

Hong Kong Fir Shipping v Kawasaki [1962] Facts

A
  • ship was out of action for 20 weeks of 24 month contract
  • justify termination?
  • Held:
  • 20 weeks was not enough
  • sets out the rules for innominate terms
51
Q

Hong Kong Fir Shipping v Kawasaki [1962] Principle

A

• Role of innominate terms

o What goes to the root of the contract?
• Depends on each case

52
Q

The Hansa Nord [1976] Facts

A

• involves the sale of citrus pulp pellets
• used for animal food
• contract said shipment must be made in good condition
• shipment was in poor condition (part of it)
• market value fell
• Buyers rejected the goods
• Later sold to original buyers for much less money
• Buyers used the goods for intended purpose, but had less than originally planned
• Was this rejection justified?
• Held:
• No
• This statement about good condition was an innominate term
• Must look at effect of breach
• Was not serious enough to justify termination
• Motivation?
o Not because of poor condition
o They saw opportunity to get them at lower price

53
Q

The Hansa Nord [1976] Principle

A

• Role of intermediate terms

  • Must look at effect of breach
  • Was not serious enough to justify termination

• Motivation?
o Not because of poor condition
o They saw opportunity to get them at lower price

54
Q

Anticipatory breach can happen in 2 ways?

A

• 1) breacher displays by words or conduct that he will not perform, or

• 2) he made it impossible for himself to perform on that day
o ex: already sold the goods
• Clear that the breach is going to happen
• Do not need to wait
• Acting on a tip is not good enough