Frustration Flashcards
Structure for Answering Frustration Question? (4)
1) Is it Frustration?
o After contract is formed
o Beyond control of both parties
o Impossible, illegal or radically altered
2) Type of Frustration o Destruction of the subject matter o Personal services contracts o Subject matter no longer available o Gov’t intervention/subsequent illegality o Method of performance o Failure of source o Non-occurrence of event
3) Limitations: o Imprudent bargains o Foreseeable when contract was made o Actually foreseen but not in contract o Express provision in contract o Self-induced frustration
4) Effect
o Common Law
o Law Reform (Frustrated Contracts) Act 1943
o Ss. 1(2), 1(3)
Different from mistake how?
•Mistake happens before the contract is entered into
•Frustration is after the contract
o Something happens during the performance of the contract that ends the contract
•Mistake voids contract
o Rescind contract
o Place back in position before contract
•Frustration terminates contract
o End on day of frustration
What is Frustration?
Unforeseen/unforeseeable events which take place after contract made and which make contract impossible/illegal/something very different from what parties had in mind in making the contract may have effect of bringing the contract to an end by operation of law
What happens when things go wrong in the middle of the contract
• Something that the parties did not or could not foresee
Taylor v Caldwell (1863) Facts
• P entered into contract
• D allowed P to use music hall to give 4 concerts
• After contract, before first concert, music hall was destroyed by fire
• Fire was no one’s fault
• P brought a claim for breach of contract
• Question:
o If contract is still good, there is an obligation to pay
o If contract is frustrated, no obligations on either side
• Argued that if music hall no longer exist, should no longer have to provide it
• Held:
o Contract was frustrated
o Implied term theory of frustration
o Subject matter of the contract had been destroyed,
o When performance depends on existence of particular thing, if the thing no longer exists, contract is frustrated (no longer need be performed)
o Contract was terminated, not rescinded
Taylor v Caldwell (1863) Principle
- Beginning of modern doctrine of frustration
- Implied term theory of frustration
Contract became impossible to perform
Imprudent Bargains are not enough to frustrate
Davis Contractors Ltd v Fareham UDC Facts
• D contracted with F to build houses
• Unexpected circumstances, no one’s fault
• Could not get the labor necessary to build houses
• Cost around £115k rather than £95k projected
• Argued that the contract was frustrated
• Entitled to reasonable sum for work to be done
• Held:
• Not frustrated
• More difficult, but not impossible to perform
• Simply a bad deal
• Just because it is disadvantageous doesn’t mean it was frustrated
• Rejected implied term theory
o Neither party foresaw the difficulties
o No way to create a clause to cover this
• New theory
o Construction of the contract itself
Davis Contractors Ltd v Fareham UDC Principle
•This case nullifies the Implied term theory concept
•New theory
Construction of the contract itself
•“true meaning of the contract”
•X should happen, if it doesn’t, frustrated
- – Circumstances in which performance is called for would render it a thing radically different from that which was undertaken by the contract
- Impracticality is not sufficient enough to frustrate a contract
National Carriers v Panalpina (Northern) Ltd Principle
- Favoured Construction theory
- Unjust to hold parties to literal sense of stipulation in the new circumstances
- If circumstances change
- Should be frustrated
Leases
Krell v. Henry (CA 1903) Facts
• H hired flat from K for 2 days
• K advertised that the flat had a window that overlooked the coronation processions on those days
• There was no express term in the contract regarding the coronation processions
• H entered into the contract after reading the advertisement
• The coronation processions were postponed and only one-third of the rent had been paid
• Held:
o K could not recover the rest
o The processions and position of the flat were at the foundation of the agreement
Krell v. Henry (CA 1903) Principle
Non-Occurrence of a Particular Event
- Common purpose of contract can no longer be performed
- Purpose in Krell was wholly frustrated
Rare
Contrasts Herne Bay Steamboat v Hutton case
• Impracticality is not sufficient to frustrate a contract
Herne Bay Steamboat Co. v. Hutton (1903) Facts
?
Herne Bay Steamboat Co. v. Hutton (1903) Principle
Frustrating event at common law
Non-Occurrence of a Particular Event
purpose only partially frustrated
Contrasts Krell Case
• Impracticality is not sufficient to frustrate a contract
Fibrosa v. Fairbairn (HL1943) Facts
•Held:
o £1,000 deposit should be returned
o If you get nothing from the expected result, you can get your money back
Fibrosa v. Fairbairn (HL1943) Principle
Frustrating event at common law
• It subsequently becomes illegal to perform contract
moneys paid recoverable on a restitutionary basis; total failure of consideration, if party who paid has had nothing of what he bargained for in return
Recipient could not set-off against money to be repaid to paying party on total fixed costs expenses he had incurred in performing contract:
Denny Mott & Dickson v James B. Fraser & Co [1944] Facts
?
Denny Mott & Dickson v James B. Fraser & Co [1944] Principle
?
Tatem v. Gamboa (1939) Facts
?
Tatem v. Gamboa (1939) Principle
• Event, though not foreseen by parties, would have been foreseeable (i.e. seen by ordinarily intelligent people as likely to occur) at time contract made
-Not enough to frustrate a contract
The Eugenia Facts
?
The Eugenia Principle
Frustrating event at common law
• Method of performance
• Event, though not foreseen by parties, would have been foreseeable (i.e. seen by ordinarily intelligent people as likely to occur) at time contract made
- Not enough to frustrate a contract
Constantine Steamship Co. v. Imperial Smelting (CA1942) Facts
?