Standard Costing and Variance Analysis Flashcards
Which of the following would not be used to estimate standard material prices?
A - The availability of bulk purchase discounts
B - Purchase contracts already agreed
C - The forecast movement of prices in the market
D - Performance standards in operation
D - Performance standards in operation
Performance standards would be taken into account when estimating material usage, they would not have a direct effect on material price.
All of the other factors would be used to estimate standard material prices for a forthcoming period
Which of the following statements about budgets and standards is/are correct?
1) Budgets can be used in situations where output cannot be measured but standards cannot be used in such situations.
2) Budgets can include allowances for inefficiencies in operations but standards use performance targets which are attainable under the most favourable conditions
3) Budgets are used for planning purposes, standards are used only for control purposes
A - 1, 2 and 3
B - 1 and 2 only
C - 1 only
D - 2 and 3 only
C - 1 only
1) Budgets can be used in situations where output cannot be measured but standards cannot be used in such situations.
Statement 1 is correct. The use of standards is limited to situations where output can be measured.
Statement 2 is not correct. Standards can include allowances for inefficiencies in operations, through the use of attainable standards.
Statement 3 is not correct. Standards and budgets are both used for planning and control purposes.
Which of the following is not a cause of variances?
A - Actual prices are different from budgeted prices
B - Actual resource usage is different from planned resource usage
C - Actual production volume is different from budgeted production volume
D - Actual prices are different from forecast prices
D - Actual prices are different from forecast prices
All of the other options given will give rise to a variance
Telgar plc uses a standard costing system, with its material inventory account being maintained at standard cost. The following details have been extracted from the standard cost card in respect of materials.
8 kg @ £0.80/kg = £6.40 per unit
Budgeted production in April was 850 units
.
The following details relate to actual materials purchased and issued to production during April when actual production was 870 units
Materials purchased 8,200 kg costing = £6,888
Materials issued to production = 7,150 kg
The material price variance for April was:
A - £286 adverse
B - £286 favourable
C - £328 adverse
D - £328 favourable
The material usage variance for April was
A - £152.00 favourable
B - £152.00 adverse
C - £159.60 adverse
D - £280.00 adverse
C - £328 adverse
8,200 kg did cost 6,888
But should have cost (×£0.80) 6,560
——
328 (A)
However, the material inventory account is maintained at standard cost, therefore the material price variance is calculated when the materials are purchased. Adverse as they cost more than they should have.
B - £152.00 adverse
870 units did use 7,150 kg
But should have used (×8 kg) 6,960 kg
—-
Usage variance in kg 190 (A)
Usage variance in £ = (190 kg ×standard price per kg £0.80) £152 A
Extracts from Verona Ltd’s records for June are as follows
Budget vs actual:
Production = 520 units vs 560 units
Variable production overhead cost = £3,120 vs £4,032
Labour hours worked = 1,560 vs 2,240
The variable production overhead total variance for June is
A - £240 adverse
B - £672 adverse
C - £672 favourable
D - £912 adverse
B - £672 adverse
Standard variable overhead cost per unit = £3,120/520 units = £6 per unit
Standard variable overhead cost for 560 units (×£6) = 3,360
Actual variable overhead cost = 4,032
——
672 adverse
Extracts from Verona Ltd’s records for June are as follows
Budget vs actual:
Production = 520 units vs 560 units
Variable production overhead cost = £3,120 vs £4,032
Labour hours worked = 1,560 vs 2,240
The variable production overhead expenditure variance for June is
A - £448 favourable
B - £448 adverse
C - £672 adverse
D - £912 adverse
A - £448 favourable
Standard variable production overhead cost per hour = £3,120/1,560 = £2 per hour
2,240 hours of variable production overhead should cost (×£2) = 4,480
But did cost = 4,032
——
448 (F)
Extracts from Verona Ltd’s records for June are as follows
Budget vs actual:
Production = 520 units vs 560 units
Variable production overhead cost = £3,120 vs £4,032
Labour hours worked = 1,560 vs 2,240
What is the efficiency variance?
A - £1,008 adverse
B - £1,120 adverse
C - £1,120 favourable
D - £1,360 adverse
B - £1,120 adverse
Standard time allowed for one unit = 1,560 hours/520 units
= 3 hours/unit
Standard variable production overhead cost per
hour = £3,120/1,560
= £2/hour
560 units should take (×3 hours) = 1,680 hrs
But did take = 2,240 hrs
—–
Efficiency variance in hours 560 hrs (A)
Efficiency variance in £ = (Efficiency variance in hours × standard variable
production overhead per hour £2) = £1,120 (A)
The following information is available for Mentamint Ltd, which makes one product
Budgeted fixed overhead per unit = £10
Budgeted output = 1,000 units
Actual output = 1,200 units
Actual fixed overheads = £11,200
What is the fixed overhead expenditure variance?
A - £1,200 adverse
B - £800 favourable
C - £1,200 favourable
D - £800 adverse
A - £1,200 adverse
Budgeted fixed overhead cost £10 ×1,000 = 10,000
Actual fixed overhead cost = 11,200
Fixed overhead expenditure variance = 1,200 (A)
To reconcile the budgeted contribution to the actual contribution, which of the following must be accounted for?
A - All sales variances and all marginal cost variances
B - All sales variances
C - All marginal cost variances
D - Neither sales nor marginal cost variances
A - All sales variances and all marginal cost variances
Budgeted contribution is different from actual contribution because of all of the sales and marginal
cost variances which have arisen.
A company budgets to make and sell 83,000 units of its product each period. The standard contribution per unit is £8.
The following variances (A = adverse; F = favourable) were reported for the latest period
Variances:
Sales volume contribution 42,400 (A)
Sales price 7,310 (F)
Material total 7,720 (F)
Material price 10,840 (F)
Labour total 6,450 (A)
Variable overhead total 4,250 (A)
Fixed overhead expenditure 8,880 (F)
The budgeted fixed overhead expenditure for the period was £210,000
The actual profit for the period was:
A - £424,810
B - £435,650
C - £482,190
D - £634,810
A - £424,810
Budgeted contribution 83,000 ×£8 = 664,000
Variances:
Sales volume = 42,400 (A)
Sales price = 7,310 (F)
Material total = 7,720 (F)
Labour total = 6,450 (A)
Variable overhead total = 4,250 (A)
Favourable = 7,310 + 7,720 = 15,030
Adverse = 42,400 + 6,450 + 4,250 = 53,100
—-
Total = 38,070 adverse
664,000 - 38,070 = 625,390 actual contribution
Budgeted fixed overhead = 210,000
Fixed overhead expenditure variance = 8,880 (F)
—
201,120
Actual profit = actual contribution - fixed overhead expenditure
625,930 - 201,120 = 424,810
During a period, 17,500 labour hours were worked at a standard cost of £6.50 per hour. The labour efficiency variance was £7,800 favourable.
Requirement
How many standard hours should have been worked?
A - 1,200
B - 16,200
C - 17,500
D - 18,700
D - 18,700
Production should have taken = X hours
But did take = 17,500 hours
Variance in hours = X – 17,500 hours (F)
× standard rate per hour = × £6.50
Variance in £ = £7,800 (F)
∴ 6.5 (X – 17,500) = 7,800
X – 17,500 = 1,200
X = 18,700
1,200 hours is the efficiency variance in terms of hours, and 17,500 is the actual number of hours worked
The following information relates to material costs for the latest period.
Actual material purchased and used 210,000 kg
Standard material for actual output 175,000 kg
Total actual materials cost £336,000
Materials price variance £21,000 adverse
What was the standard materials price per kg?
A - £1.50
B - £1.70
C - £1.80
D - £2.04
A - £1.50
Materials price variance per kg purchased and used = (£21,000/210,000)
= £0.10 (A) per kg
Actual price per kg = £336,000/210,000 = £1.60
Standard price per kg = £1.50
Consider the following statements:
1) Favourable variances are always good for an organisation
2) Variance reporting is the comparison of the actual results with the original budget
Which of the following is correct with regards to the statements above?
A - Both statements are correct
B - Both statements are incorrect
C - Statement 1 is correct but statement 2 is incorrect
D - Statement 1 is incorrect but statement 2 is correct
B - Both statements are incorrect
Favourable variances may not always be good. For example, a favourable materials variance might be achieved by buying poorer quality material which means that the labour force have to spend much longer working on the material leading to an adverse labour variance.
Variance reporting is the reporting of differences between the actual results and the flexed budget not the original budget.
Variances which are simply random deviations can be described as which of the following?
A - Controllable
B - Uncontrollable
C - Either controllable or uncontrollable
D - Marginal costs
B - Uncontrollable
Uncontrollable variances are variances which have arisen by chance. They are random deviations.
Controllable variances result from a manager’s actions and decisions
Consider the following factors for investigating a variance
1) Controllability of variance
2) Cost of investigation
3) Personnel involved
4) Trend of variance
Which of these would be a factor that would affect a decision as to whether to investigate the variance?
A - 2 and 4 only
B - 2, 3 and 4 only
C - 1, 2 and 3 only
D - 1, 2, and 4 only
D - 1, 2, and 4 only
All of these apart from personnel would influence the decision to investigate a variance as they include cost/benefit considerations, whether the variance can be controlled and what the movement of the variance suggests is a trend