SSGB Chapter 4 Flashcards

1
Q

Which of the following is not an input to Six Sigma Methodology - Define

A

Problem Statement

Inputs include need for project, core team identified, executive management sponsorship

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which of the following is not a tool for Six Sigma Methodology - Define

A

Project Charter

Tools include- high level process maps, high level pareto charts, organizational hierarchy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which of the following is not an output for Six Sigma Methodology - Define

A

Organization hierarchy

Project chart, metrics, problem statement, roles and responsibilities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which of the following statements best describes a six sigma project. Six sigma projects satisfy:

A

One or more needs

A six sigma project may satisfy one or more needs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Motivation and support to initiate and sustain the six sigma project is provided by:

A

Executive sponsor

Motivation and Support to initiate and sustain the six sigma project is provided by Executive or Senior Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Who among the following resources should always be a part of six sigma project core team?

A

Green Belt or Black Belt

Six Sigma Green Belt or Black Belt should be a part of six sigma project core team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which of the following are benefits of process map (select the best answer)

A

All of the above

Benefits of process maps: - Helps clarify several process steps and process flow which may not be understood clearly before. - Helps all members of the team gain appreciation for the work being done by others in the team. - Visually shows the various alternatives possible and helps in selecting an appropriate solution.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

a graphic representation of processes in a company showing the sequence of tasks performed and their relationships is also called:

A

Process map

Process maps give a view of how work flows through the company. It is a graphic representation of processes in a company showing the sequence of tasks performed and their relationships

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A high level process map is defined early on in the project which shows major processes and this will be made more explicit and detailed as project team develops a better and more complete understanding of all the processes. This is an example of:

A

Progressive elaboration

Process maps are progressively elaborated: i.e. a high level process map is defined early on in the project which shows major processes and this will be made more explicit and detailed as project team develops a better and more complete understanding of all the processes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

In a process map, a decision step is represented by which symbol?

A

Diamond

In a process map, we use a Diamond to represent a decision step i.e. different alternatives possible depending on the input to this step

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

In process map, a process step or action taken is represented by :

A

Rectangle

In a process map we use a Rectangle to represent a process step or action taken. Each process step has one or more inputs, does some activity, and creates one or more outputs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A principle which states that a small number of causes (20%) is responsible for a large percentage (80%) of the effect is also referred to as:

A

Pareto principle

Pareto principle (also referred to as 80-20 rule), states that a small number of causes (20%) is responsible for a large percentage (80%) of the effect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Identifying and ranking which of the opportunities would yield maximum benefits and hence should be pursued first is done through:

A

Pareto chart

Pareto chart helps in identifying and ranking which of the opportunities would yield maximum benefits and hence should be pursued first.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

All the following are tools for idea generation EXCEPT:

A

Affinity Diagram

Affinity diagrams are used for Idea categorization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Which of the following is a tool for Idea Categorization?

A

Multivoting

Multivoting is used for Idea categorization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly