SPECIFICATIONS Flashcards

1
Q

A type of contract with which the design firm invoices on a cost basis up to a stipulated maximum dollar amount that cannot be exceeded.

A

Guaranteed Maximum Price (GMP)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A unit price bid that accurately reflects the actual anticipated price of each item of work to be performed.

A

Balanced bid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A surety instrument that guarantees to the owner that the bearer, if awarded the contract, will enter into a binding contract and provide all required bonds.

A

Bid Bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A specification that is expressly restrictive in stating that only one or two products will satisfy the quality requirements, or is implied when performance is so narrowly prescribed that only one or two products will satisfy the requirement.

A

Closed Specification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A bid that is not prepared in earnest, but is presented to appear to be a serious bid. Such bids are usually generated through collaborative efforts with another bidder who does submit a serious bid.

A

Complimentary Bid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

AKA Boilerplate: outlines the roles of the parties to a construction agreement and provide guidance concerning procedures to follow under varying circumstances.

A

General Conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A common procedure in which the owner of a project contracts with a single firm, often called a prime contractor, for its construction. This firm may contract with speciality contractors for portions of the work

A

General Contract Method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Guidelines or rules enumerated for bidders on a project concerning proper procedures for bid submittal and relevant project information

A

Instructions to Bidders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A means of notifying the contractor about the decision to award the contract and of specifying when the contract time will start.

A

Notice to proceed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

An open or nonrestrictive specification in which a wide variety (three or more) of products are considered suitable.

A

Open specification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A surety instrument in which the faithful performance of a contractor is guaranteed up to the face value of the bond.

A

Performance bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A descriptive requirement that states the results or the performance of the finished product rather than the specific methods and means used to construct the product.

A

Performance specification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A meeting between the owner, the general contractor, and the major subcontractors that takes place after the contract is awarded but before construction begins. This conference addresses various matters deemed to be of importance to the project.

A

Preconstruction conference

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A closed specification that names a project made by a particular manufacturer.

A

Proprietary specification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A performance specification that defines the acceptable product in terms of its ability to satisfy a standard developed by one of several standards organizations.

A

Reference specification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A bid that conforms to the standards outlined in the instruction to bidders. Only such bids can be considered on public works projects to assure all bidders of fair and equal treatment.

A

Regular bid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

A compilation of general conditions, technical specifications, and other requirements that an agency uses on numerous construction projects. Such documents are prepared by state departments of transportation and many major municipalities.

A

Standard Specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

A document that provides the qualitative requirements for a project in terms of materials, equipment, work performed, and so forth.

A

Technical Specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

A unit price bind in which the pricing of the various items of work does not reflect the actual anticipated costs, but redistributes those costs to serve a specific objective of the bidder.

A

Unbalanced Bid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

A contract in which payment is based on a contractor’s quoted price per unit of work performed and the owner’s measurement of the total number of such units installed.

A

Unit Price Contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

A contract in which the contractor is reimbursed for specified incurred costs, with an additional allowance provided for overhead and profit

A

Cost-Plus Contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

A contract in which the contractor agrees to construct a project for a specified sum of money.

A

Fixed-Price Contract / Lump Sum Contract

23
Q
  1. Agreement
  2. Conditions
  3. Drawings
  4. Specifications
  5. Adenda
  6. Misc. documents associated w/ the contract bw the owner and contractor
A

Elements of the Contract Documents (according to AIA 201-207)
(6)

24
Q

In the event of conflicting information between specifications and drawings…

A

Specifications supersede drawings

CLARB / LARE answer

25
Q

Components of a three-part specification

A

Part 1: General
Part 2: Product / Materials
Part 3: Execution

26
Q

Tech Spec Section

PART 1: General

A

Defines the scope and the ground rules for work to be performed

Lists reference specs (ASTM, etc)

May list related work, required submittal requirements, quality control or quality assurance requirements, warranty, manuals, product handling requirements

27
Q

Tech Spec Section

PART 2: Product / Materials

A

The specific materials and products to be used

May outline the performance requirements of each product or manufacturing / fabrication processes to be used in production

Any products specified should be accompanied with an “approved equal” or similar language to keep the spec “open”

28
Q

Tech Spec Section

PART 3: Execution

A

Describes the actual means of preparing, installing, or constructing the item in question, as well as any quality or performance requirements (testing) expected

29
Q

3 Primary Specification Types

A

Performance
Prescriptive
Proprietary

30
Q

Specifies the operational requirements of a component or installation; contractor is not instructed on how to accomplish the task, only how the component must function / perform

A

Performance Specification

31
Q

Details materials to be used and means of installation

Shifts more design control to the LA / designer and away from the contractor by establishing a set of rules that is to be followed for each project component

Provides more certainly regarding the final product composition than a performance specification

Typically follows the CSI 3-part specification format

A

Prescriptive Specification

32
Q

A type of “closed” specification; requires the use of a single approved product or system type for installation without alternates. Typically would list the approved manufacturer and model number

Typically not used / or prohibited in public work

Can increase project costs / prohibits competitive bidding

A

Proprietary Specification

33
Q

Often developed by industry professionals and associations. Considered well vetted. Refer to pre-existing standards.

Help to reduce the length of project specifications.

A

Reference Specifications

examples: ANSI, ASTM, AASHTO, etc

34
Q

Implies less than 100% complete but considered open for use by owner / public. Typically there are minor corrections that remain from punch list which the contractor must address.

Final payments are made during this phase to contractor excluding a 5-10% retainage

A

Substantial completion

part of project closeout

35
Q

3 Primary Documents used in solicitation of bids

A
  1. Invitation to Bid
  2. Instructions to Bidders
  3. Bid Form
36
Q

Construction Contract Method Type

Owner will enter into 2 contracts: w/ design firm & w/ contractor.

GC hires subcontractors

Design, bid, and building phases do not overlap

A

General Contract Method

37
Q

A guarantee provided by a firm that states that the contractor will fulfill the terms of the contract; if the contractor defaults, the surety will be obligated to satisfy the terms of the contract

More typically used in General Contract types

A

Surety Bonds

38
Q

Protects the owner if subcontractors and suppliers are not paid by the prime contractor; surety will pay the sub / suppliers if the prime fails to pay

Typically required on public projects

A

Payment Bonds

39
Q

Advertises or otherwise notifies bidders of the proposed project

A

Invitation to Bid

Typically includes: 
Nature of project and location 
Type of contract 
Bonding requirements 
Dates in which to perform work 
Terms of payment 
Estimated construction costs (sometimes) 
Time, manner, and place to submit bids 
Location to obtain bid documents 
Deposit required on bid documents 
Owners right to reject bids 
Requirements regarding prevailing wage rates
40
Q

Outlines the requirements to prepare and submit a bid properly

Includes detailed guidance to bidders, including the process of award and rejection of bids

A

Instructions to Bidders

Typically includes:
Procedures / instructions for writing and submitting the bid
Qualifications
A list of all the bid documents
Construction timeframe
Identify responsible parties for testing and site visits
Requirements of a bid guarantee
Insurance to be provided by the contractor
Bonding requirements
Conditions for handling bid irregularities
Bid delivery instructions
Indicates if the bid opening will be closed or public
Describes pre-bid conference (if any)

41
Q

Provides the template for how the required information is to be conveyed to the owner; standardizes all bids submitted so that they can be compared accurately to one another

A

Bid Form

Typically includes:
GCs bid price(s) (lump-sum or unit price)
Time of completion
Bid surety
Agreement to provide contract surety
Acknowledgement of having reviewed addenda
List of subcontractors
Experience record, financial statement, plant and equipment inventory
Statement regarding site examination
Signature

42
Q

Corrections to the bid documents made to correct errors caught by owner or designer OR to provide additional clarification for the contractor. Must be communicated formally to all bidders

Issued by owner (or owner’s rep)

A

Addenda

43
Q

Responsible Bidder

A

Contractor that is qualified to perform the work / execute project

44
Q

Regular Bid

A

A bid that complies with bid instructions

e.g. fails to acknowledge addenda, excludes bid security, late, missing info, etc

45
Q

Contains schedule of prices that will be incorporated into the Agreement

Used in unit price bids in particular

A

Bid Schedule

46
Q

A single book or set of documents that contain all of the relevant project documents in one place.

Includes:
Bidding and Contract Requirements
Contract Forms (agreement, bonds, certificates)
Conditions of the Contract (General and Supplementary conditions)
Technical specifications

A

Project Manual

47
Q
Agreement 
Conditions 
Drawings 
Specifications 
Addenda 
Misc. documents associated w/ the contract bw owner and contractor 

Effectively the Project Manual plus the Contract Drawings and minus the Bidding Requirements

A

The Contract Documents

48
Q

Bid Solicitation
Instructions to Bidders
Information Available to Bidders
Bid Forms & Supplements

A

Bidding Requirements

49
Q

Boilerplate language that outlines the rules under which the project will be built; establishes the rights of the contracting parties

A

General Conditions

50
Q

Language that amends or augments the general conditions and is more specific to the project being constructed

A

Supplementary Conditions

51
Q

A construction contract is fully executed when

A

Work is completed and the owner has made final payment

52
Q

If the contractor defaults on a public project the responsbility is assumed by

A

The surety company

53
Q

Bidding of a public project generally requires (4)

A
  1. Public advertisement
  2. Bid bond
  3. Payment of prevailing wage rates
  4. Insurance covering liability and property