*Shop Drawings and Submittals Flashcards
1
Q
Contractor responsibility after the contract is awarded is in regards to submittals
A
After the contract is awarded, the contractor is responsible for submittals per the contract documents. These include shop drawings, samples, and product data.
2
Q
The last person to see the mechanical shop drawings before they are returned to the mechanical subcontractor should be the
A
general contractor
After a review by the mechanical engineer and interior designer, the shop drawings are returned to the general contractor, who reviews them again to see what comments the engineer and designer have made before returning them to the subcontractor.