*Design Phase Criteria Flashcards

1
Q

Deliverables of programming

A
  • Programming document
  • Project schedule
  • The project team identified roles and responsibilities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Deliverables of Schematic Design

A
  • SD estimate of the cost of work
  • Update project schedule
  • Conceptual diagrams
  • Preliminary plans and layouts
  • Floor plans
  • Hand-drawn sketches to convey design and material intent
  • preliminary code analysis
  • Outline specifications
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Deliverables of design development

A
  • DD estimate of the cost of work
  • Final recommendations for complete project
  • Coordination with consultants
  • Refined conceptual drawings to gain client approval
  • Enlarged plans
  • Reflected ceiling plans
  • Unique design elements more refined
  • MEP design intent
  • More detailed specifications
  • Refined code checklist
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Deliverables of Contract Documents

A
  • Fully documented construction drawings
  • Bid package
  • Issue for a permit set
  • Fleshed out specifications
  • Schedules
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The overall code compliance process for the project begins when?

A

Code compliance reviews should begin near the end of the initial floor plan development stages to prevent costly rework later.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

During which project phase would the interior designer first review and approve consultant’s billing?

A

schematic design

Consultants may work with designers throughout the project in all phases of design.

The consultant’s involvement is planned out during programming, and billing is first reviewed and approved in schematic design.