Session 5 Flashcards

1
Q

What is the purpose of the Earned Value Analysis

A

It measures project performance using scope, cost, and schedule.
It compares amount of work planned vs actually accomplished to determine if cost and schedule is going as planned.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is BCWS

A

It’s the planned cost of work scheduled.
What is the cost we should have incurred so far?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is BCWP

A

It’s the planned cost of work completed so far.
= Earned Value
= budgeted cost to date x % work completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is ACWP

A

The actual cost of work completed so far.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How do you calculate Cost Variance and what does the number mean?

A

= BCWP - ACWP
= EV - AC
If negative, you are over budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How do you calculate Schedule Variance and what does the number mean?

A

= BCWP - BCWS
= EV - PV
If negative (EV<PV), you have finished less than planned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How do you calculate the Cost Performance Index and what does the number mean?

A

= BCWP/ACWP
If negative, you are overspending

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How do you calculate the Schedule Performance Index and what does the number mean?

A

= BCWP/BCWS
If negative, you are behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How do you calculate the Estimate at Completion?

A

= BAC / CPI
= Budget at Completion / Cost Performance Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How do you calculate the Estimated Time at Completion?

A

= Original Estimate / Schedule Performance Index (SPI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly