Section 8 Flashcards
section 8
Suspension of work and termination of the contract
The contractor may suspend or terminate work upon ____ written notice to the
owner and architect
15 days
Order of court or public authority caused the work to stop or suspension for
________ through no act of the contractor and employees.
90 days
If architect fails to act upon request for payment within _____ after
presented.
15 days
If owner fails to act upon request for payment within ______ after
presented.
15 days
If owner fails to pay the contractor within_____ after its award by
arbitration.
30 days
The contractor may suspend or terminate work upon 15 days written notice to the
owner and architect for the following:
- Order of court or public authority caused the work to stop or suspension for
90 days through no act of the contractor and employees. - If architect fails to act upon request for payment within 15 days after
presented. - If owner fails to act upon request for payment within 15 days after
presented. - If owner fails to pay the contractor within 30 days after its award by
arbitration.
The owner, upon certification of the architect justifying his action, may terminate
the contract with the contractor within______ written notice and surety of the
contractor if any and take possession of the premises, tools, materials, etc.
15 days
The owner shall terminate contract based on the following:
- If contractor declares bankruptcy or assign assets to creditors.
- Disregard or violate provisions of the contract documents or fail to
prosecute work according to schedule. - Fail to provide qualified superintendents, workman, sub-contractors and
materials. - Fail to make payments to sub-contractors, workmen and dealers.