Schedule Management Flashcards
project schedule management
includes processed to plan the project schedule and monitor and control the timeliness of work performance
project schedule management
- processes
- plan schedule management (planning)
- define activities (planning)
- sequence activities (planning)
- estimate activity durations (planning)
- develop scheudule (planning)
- control schedule (monitoring and controlling)
plan schedule management
the process of documenting how the project schedule will be planned and controlled. this helps to ensure all individuals of the project management team are using the same approach and tools for time management
plan schedule management
- key inputs
- project charter
- project management plan
- scope management plan
- development approach
plan schedule management
- key outputs
- schedule management plan
schedule management plan
defines how the project schedule will be planned, approved, and controlled through a series of project management processes. this may describe the tools to be used, the participating stakeholders, and the frequency of iteration. further, it may establish thresholds for planning accuracy, variance limits (thresholds for escalation), and rules for performance measurement and reporting
define activities
the process to take work packages, the lowest level of work defined in WBS, and decompose them further into schedule activities to facilitate better schedule planning and schedule control
the purpose of this process is to elevate the level of detail found in the WBS and determine areas where more detail is required for effective scheduling. for example, it may be determined that a work package can be further divided into smaller activities that will provide more accurate sequencing, duration estimates, or resource assignments
define activities
- key inputs
- project management plan
- schedule management plan
- scope baseline
define activities
- key tools and techniques
- decomposition
- rolling wave planning
define activities
- key outputs
- activity log
- activity attributes
- milestone list
rolling wave planning
a planning technique where planning for upcoming activities is more detailed than for activities that will occur later in time. detail will be added closer to the start date of each activity. this is a form of progressive elaboration
decomoposition
the breakdown of work packages into more detailed schedule activities
progressive elaboration
means that the project team does not know all variables and details about a project from the start, so updates and revisions must be made to plans throughout the project lifecycle. as a team learns more about the project, a greater level of detail can be incorporated into the project management plan
activity list
a comprehensive list of schedule activities, in more detail than the WBS. it should contain a unique identifier as well as the scope of work for that activity
provides the level of detail required to sequence the schedule activities of the project
provides the level of detail required to estimate durations for the schedule activities of the project
activity attributes
provides additional details for each activity in the activity list such as activity codes, notes about the activities, assumptions, and constraints
milestone list
identifies all milestones for the project and describes their need. milestones are significant events on the project schedule with a duration of zero.
sequence activities
the process of identifying and documenting logical relationships such as dependencies and leads and lags between project activities
sequence activities
- key inputs
- project documents
- activity attributes
- activity list
- assumptions log
- milestone list
sequence activities
- key tools and techniques
- precedence diagramming method (PDM)
sequence activities
- key outputs
- project schedule network diagrams
precedence diagramming method (PDM)
a technique of designing a network diagram using nodes to represent activities, and using arrows to represent dependencies, connecting the nodes. alos know as activity-on-node (AON)
finish-to-start (logical relationship)
the beginning of the dependent activity (successor) cannot occur until the predecessor activity has been completed
finish-to-finish (logical relationship)
the successor activity cannot finish until the predecessor activity has completed
start-to-start (logical relationship)
the successor activity cannot start until the predecessor activity has begun
dependency determination and integration
used to classify dependency relationships
mandatory dependencies
aka hard logic. represent dependencies without alternatives. the work must be performed in the specified order due to a legal or contractual obligation or because of the nature of the work
discretionary dependencies
aka soft logic. represent a dependency that is preferred, but not required. these dependencies must be documented since they may contribute to unnecessary schedule delays
external dependencies
represent when project activities depend on activities that are beyond the scope of the project
internal dependencies
relationships between activities that are fully within the scope of the project
leads and lags
the documentation of required space (lag) or overlap (lead) built into the dependencies of project activities. it is also important to document any assumptions that are made in this process.