SAFe Master Deck Flashcards

1
Q

During PI Planning, which two tasks are part of the Scrum Master’s role in the first team breakout? (Choose two.)

Identify as many risks and dependencies as possible for the Management Review
Facilitate the coordination with other teams for dependencies
Be involved in the Program Backlog refinement and preparation
Provide clarifications necessary to assist the team with their story estimating and sequencing
Review and reprioritize the Team Backlog as part of the preparatory work for the second team breakout

A

Facilitate the coordination with other teams for dependencies

Identify as many risks and dependencies as possible for the Management Review

page 79

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why do teams have an Iteration Retrospective?

To evaluate metrics
To identify acceptance criteria
To iterate on stories
To adjust and identify ways to improve

A

To adjust and identify ways to improve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which meeting should the Scrum Master attend (not facilitate)?

Daily Stand-up
Iteration Review
PO Sync
Scrum of Scrums

A

Scrum of Scrums?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The program board highlights feature delivery dates, milestones, and what else for Agile Release Train teams?

Requirements
Timeboxes
Dependencies
Objectives

A

Dependencies

The program board is often used during the Scrum of Scrums meetings to track dependencies, or it may not be maintained (manually) after that time. This depends upon the Agile project management tooling in place and the needs of the ART.

© Scaled Agile, Inc.
Include this copyright notice with the copied content.

Read the FAQs on how to use SAFe content and trademarks here:
https://www.scaledagile.com/about/about-us/permissions-faq/
Explore Training at:
https://www.scaledagile.com/training/calendar/

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is an anti-pattern for the IP Iteration? (Choose two.)

To plan work for the IP Iteration during PI Planning
To ensure all stories and teams’ PI plans are completed prior to the IP Iteration
To allow for sufficient capacity in the program roadmap
To wait for the IP Iteration to fix defects
To minimize lost capacity when people are on vacation or holidays

A

To plan work for the IP Iteration during PI Planning

To wait for the IP Iteration to fix defects

https://www.scaledagileframework.com/innovation-and-planning-iteration/

or page 125

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The business must depend on the team for what in order for the business to do any meaningful planning?

Measurements
Team capabilities
Commitment to the plan
A cross-functional skill set

A

Commitment to the plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Good coaches do not give people the answer, but instead they do what?

They hold them to their commitments
They guide people to the solution
They make the decisions
They limit the number of questions

A

They guide people to the solution

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

In SAFe, who owns the decision for releasing changes into production?

Release Train Engineer
Solution Owner
System Architect
Product Management

A

Product Management

https://www.scaledagileframework.com/product-and-solution-management/

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When does the Plan-Do-Check-Adjust cycle occur in Scrum?

As part of the Iteration Retrospective
At all formal Scrum events
At the Iteration Review
In the daily Scrum

A

At all formal Scrum events

https://www.scaledagileframework.com/iterations/

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which three attributes summarize DevOps? (Choose three.)

A set of technical practices
Combined deployment and release
Strong organizational structure
A mindset
A high performing DevOps Team
A shared culture
A

A set of technical practices
A mindset
A shared culture

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is this statement describing?
‘Agile Teams continuously adapt to new circumstances and enhance the methods of value delivery.’

Continuous Delivery
Continuous Improvement
Continuous Integration
Continuous Deployment

A

Continuous Delivery??

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A servant leader knows that his or her own growth comes from what?

Facilitating the growth of others
Management support
Effective training
Implementing a CALMR approach to SAFe

A

Facilitating the growth of others

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is one truth about teams?

Products are more robust when individuals on teams have specific skill sets
Teams are more productive than the same number of individuals
Development Teams can manage daily interruptions
Changes in team composition do not impact productivity

A

Teams are more productive than the same number of individuals

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are two good Scrum Master facilitation practices? (Choose two.)

Do not enforce accountability as it creates an environment of distrust
Allow for unproductive conflict to encourage open communication
Ensure all voices are heard
Create an environment of safety so that everyone feels comfortable contributing to the discussion
Allow for deep, meaningful conversations even if it is outside the scope of the agenda

A

Ensure all voices are heard

Create an environment of safety so that everyone feels comfortable contributing to the discussion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the purpose of the Plan-Do-Check-Adjust cycle?

To provide a regular, predictable development cadence to produce an increment of value
To give the Agile Release Train team members a process tool to keep the train on the tracks
To create a continuous flow of work to support the delivery pipeline
To allow the team to perform some final backlog refinement for upcoming Iteration Planning

A

To provide a regular, predictable development cadence to produce an increment of value

https://www.scaledagileframework.com/iterations/

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Becoming a coach requires a shift from old behaviors to new ones. What are three examples of old behaviors? (Choose three.)

Facilitating team problem solving
Asking the team for the answers
Focusing on deadlines
Driving toward specific outcomes
Fixing problems for the team
Focusing on business value delivery
A

Focusing on deadlines
Driving toward specific outcomes
Fixing problems for the team

page 140

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is one time when a Scrum Master participates but does not necessarily facilitate?

If the entire team is present during the Daily Stand-up
When using ad-hoc teams for Inspect and Adapt
During team breakout sessions at PI Planning
When the Agile Release Train does not require any team coordination

A

???

When the Agile Release Train does not require any team coordination

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is the recommended frequency range for PI Planning in SAFe?

Every 12 to 16 weeks
Every 8 to 12 weeks
Every 4 to 6 weeks
Every 6 to 8 weeks

A

Every 8 to 12 weeks

page 40

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is the main reason why some teams never reach stage 4 (Performing) in the stages of high performing teams?

Because leadership is spontaneous
Because there is too much conflict
Because the team is not structured correctly
Because no one guides them

A

Because no one guides them

page 136

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are two common PI Planning anti-patterns? (Choose two.)

The team decides which changes need to happen and when
Stories are created for the PI Planning Iterations
Part-time Scrum Masters do not have time to plan as part of the team
Too much time is spent analyzing each story
Too much time is spent prioritizing features

A

Part-time Scrum Masters do not have time to plan as part of the team
Too much time is spent analyzing each story

page 79

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Scrum Masters are effective by using Scrum methods, supporting SAFe principles and practices, and what else?

Delivering through Agile practices
Writing stories and enablers
Managing Architectural Runway
Serving as a customer proxy

A

Delivering through Agile practices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What are the three pillars of Scrum?

Adaptation, Transparency, Acceptance
Collaboration, Acceptance, Progress
Retrospection, Inspection, Adaptation
Transparency, Inspection, Adaptation

A

Transparency, Inspection, Adaptation

page 17

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is one example of a servant leader behavior pattern?

Understands and empathizes with others
Focuses on individual task metrics
Thinks about the day-to-day activities
Uses authority rather than persuasion when necessary

A

Understands and empathizes with others

Section 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Which statement is true about Scrum?

It is an ideal method for static design requirements
It is a software technical practice
It is based on empirical process control theory
It is a Lean System Engineering technique

A

It is based on empirical process control theory

https://less.works/less/principles/empirical-process-control.html

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
How are the 5 Whys used? To coach a team through powerful questions To identify a root cause(s) of a problem To brainstorm ideas To define acceptance criteria for a story
To identify a root cause(s) of a problem https://en.wikipedia.org/wiki/5_Whys or https://www.scaledagileframework.com/inspect-and-adapt/
26
An effective SAFe Scrum Master is a team-based servant leader who helps the team do what? Develop better and more specialized skill sets Embrace relentless improvement through Iteration Retrospectives Understand and operate within Lean Budgets Manage the team's own backlog
Embrace relentless improvement through Iteration Retrospectives
27
What is one truth about teams? Development Teams can manage daily interruptions Teams are more productive than the same number of individuals Changes in team composition do not impact productivity Products are more robust when individuals on teams have specific skill sets
Teams are more productive than the same number of individuals
28
What is one example of a servant leader behavior pattern? Understands and empathizes with others Focuses on individual task metrics Thinks about the day-to-day activities Uses authority rather than persuasion when necessary
Understands and empathizes with others
29
Scrum Masters are effective by using Scrum methods, supporting SAFe principles and practices, and what else? Writing stories and enablers Managing Architectural Runway Delivering through Agile practices Serving as a customer proxy
Delivering through Agile practices
30
Features lend themselves to the Lean UX process model. They include a description, a benefit hypothesis, and what else? IP outcomes Content readiness Scope and context Acceptance criteria
Scope and Context ??
31
``` What are two critical areas that differentiate Agile from waterfall development? (Choose two.) Staggered integration Face-to-face interaction Architectural Runway Fast feedback Incremental delivery of value ```
Fast feedback Incremental delivery of value page 11
32
Who can change the backlog during an Iteration? Release Train Engineer Senior Management Agile Team Scrum Master
Agile Team
33
During PI Planning, who owns the planning of stories into Iterations? Scrum Master Product Management Agile Teams System Architect
Agile Teams ? https://www.scaledagileframework.com/pi-planning/
34
There are two primary aspects of a Lean-Agile mindset -- Lean Thinking and what else? Feature Enablement Systems Engineering Lean Systems Embracing Agility
Embracing Agility https://www.scaledagileframework.com/lean-agile-mindset/
35
What is this statement describing? 'Agile Teams continuously adapt to new circumstances and enhance the methods of value delivery.' Continuous Improvement Continuous Integration Continuous Delivery Continuous Deployment
Continuous Delivery
36
Participating in PI Planning enables teams to gain alignment and commitment around a clear set of what? User stories Team dependencies Prioritized objectives Features and benefits
Prioritized objectives
37
``` Who commits to the plan at the end of Iteration Planning? The Solution Owner The Team The Product Owner The Scrum Master ```
The Team
38
Cadence and what other action are the key constructs to delivering continuous value? Execution Synchronization Refactoring Flexibility
Synchronization https://www.scaledagileframework.com/develop-on-cadence/
39
What is the recommended duration of a SAFe Iteration? Six weeks Four weeks Two weeks Three weeks
Two weeks
40
An effective SAFe Scrum Master helps the team improve on their journey towards technical excellence through Continuous Integration, Continuous Deployment, and what else? WIP limits Continuous Release Continuous Exploration State of the art build tools
Continuous Exploration? page 166
41
The skills of a good SAFe Scrum Master include which three attributes? Communicate, coordinate, cooperate Share, pair, communicate Represent, direct, govern Self-organize, self-manage, self-direct
Communicate, coordinate, cooperate page 153
42
Who is responsible for prioritizing the Iteration Backlog? The Product Owner The Scrum Master The Product Management Team The Development Team
The Product Owner
43
Scrum Masters help remove impediments, foster an environment for high-performing team dynamics, and what else? Continuously deliver Estimate stories Form and re-form teams Relentlessly improve
Relentlessly improve page 173
44
What is one example of a servant leader behavior pattern? Understands and empathizes with others Uses authority rather than persuasion when necessary Focuses on individual task metrics Thinks about the day-to-day activities
Understands and empathizes with others
45
Why do teams have an Iteration Retrospective? To iterate on stories To evaluate metrics To adjust and identify ways to improve To identify acceptance criteria
To adjust and identify ways to improve
46
Which type of enabler does a System Architect review during a System Demo? Enabler Stories Enabler Capabilities Enabler Portfolio Epics Enabler Features
Enabler Portfolio Epics ???
47
Which demo is performed in the IP Iteration? The Integrated Demo from the Agile Release Train's final Iteration The demo from all the Agile Release Trains' Iterations The demo from the team's final Iterations The PI System Demo
The Integrated Demo from the Agile Release Train's final Iteration ?? https://www.scaledagileframework.com/iterations/
48
What is the basis for most team conflicts? Unexamined assumptions Ideological differences Lack of leadership Lack of common goals
Unexamined assumptions ?
49
``` What is the name of the event where all team members determine how much of the team's backlog they can commit to delivering during an upcoming Iteration? Solution Demo Backlog Refinement Iteration Planning Solution Planning ```
Iteration Planning ?
50
``` According to the Five Dysfunctions of a Team, what is a team's ultimate competitive advantage? Transparency Commitment Accountability Teamwork ```
Teamwork Page 144
51
Each PI Planning meeting evolves over time, and ending PI Planning with a Retrospective will help to do what? Lengthen the Architectural Runway Continuously improve Fine tune the Economic Framework Meet compliance more rapidly
Continuously improve page 76
52
``` The goal of Lean is to deliver the maximum customer value in the shortest sustainable lead time while providing what else? Significant team contributions Improved capacity allocation The highest possible quality A Continuous Delivery Pipeline ```
The highest possible quality https://www.scaledagileframework.com/lean-agile-mindset/
53
An effective SAFe Scrum Master elevates people problems with strict confidence to the appropriate levels when necessary, but only after what has happened? Team members complain A team member consistently disagrees with the Scrum Master Coaching and internal processes have failed to achieve the objective The team consistently fails to meet consecutive PI goals
Coaching and internal processes have failed to achieve the objective
54
``` What is a characteristic of an effective Scrum Master? Is a technical expert Articulates architectural solutions Supports the autonomy of the team Understands customer needs ```
Supports the autonomy of the team
55
``` What does SAFe's CALMR approach apply to? Continuous Deployment Economic Framework DevOps PI Planning ```
DevOps
56
Cadence and synchronization help reduce uncertainty and manage what? Capacity allocation Other commitments The variability in research and development Product management
The variability in research and development ??
57
What is one responsibility of a SAFe Scrum Master? Maintaining the depth of the Architectural Runway Coordinating with the Solution Architect and Solution Management Facilitating an effective team breakout session Prioritizing the work of the Systems Team
Coordinating with the Solution Architect and Solution Management ?
58
Which two actions are part of the Scrum Master's role in PI Planning? (Choose two.)You have reached the max number of allowed answers Align the Value Stream and Agile Release Trains to a common vision Prioritize features to support the Program Vision Ensure the team builds a plan they can commit to Serve as the customer proxy and work with Product Management Manage the program board
Ensure the team builds a plan they can commit to Manage the program board Page 79
59
What is the key Scrum Master responsibility when estimating stories? Provide information about customer needs Ensure the team gives estimates that do not increase the velocity Limit discussion to minimize timeboxes Ensure everyone on the team participates
Limit discussion to minimize timeboxes ?? | 52
60
What is accomplished in the first part of the PI Planning meeting? Items are selected from the Program Backlog The Product Owner defines the Iteration goal All tasks are defined The Scrum Master decides how much work can be accomplished
The Product Owner defines the Iteration goal ?