Facilitating Iteration Execution Flashcards
1
Q
At the end of the first iteration, the team finishes user stories A, B, and 50% of C.
Story A = 8 points
Story B = 1 points
Story C = 5 points
Story D = 3 points
What is the team’s velocity?
A
9
2
Q
What are two outputs of Iteration Planning?
A
- Iteration Goals
- Iteration Backlog
3
Q
When is Iteration Planning completed?
A
When the team commits.
4
Q
What are two SAFe primary opportunites for driving relentless improvement?
A
- Inspect and Adapt Events (workshop)
- Iteration Retrospective
5
Q
What does SAFe CALMR apply to?
A
- DevOps
- Culture