Experiencing PI Planning Flashcards

1
Q

When looking at the Program Board, what does it mean when a feature is placed in a team’s swim lane with no strings?

A

That the feature can be completed independent from other teams.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is one thing the Scrum Master does during the IP Iteration?

A

Updates capacity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are common anti-patterns during PI planning?

A
  • Pressure is put on the team to over commit
  • The team under commits due to fear of failure
  • Over planning ahead of time to make it more efficient loses the essence of PI Planning
  • The plan, rather than the alignment, becomes the goal
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which two actions are part of the Scrum Master’s role in PI Planning?

A
  • Maintain the time box
  • Ensure the team builds a plan they can commit to
  • Make sure the team is honest in their confidence vote
  • Facilitate coordination with other teams without doing it for them
  • Act as a request buffer for a team that has a lot of dependencies
  • Manage the Program Board
  • Facilitate the retrospective
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When is a feature hypothesis fully evaluated?

A

When the customer uses the feature in production.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is accomplished in the first part of the PI Planning meeting?

A

Items are selected from the Program backlog.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

During PI Planning, who owns feature priorities?

A

Product Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What Agile Manifesto principles describe the importance of PI Planning in SAFe?

A

The most efficient and effective methods of conveying information to and within a development team is face-to-face conversation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Why is a confidence vote held at the end of PI Planning?

A

To build shared commitment to the program plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When working with an Agile Team, what is expected from Product Management?

A

To clarify the scope of feature work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

PI Objectives summarize data into meaningful information that enhances alignment and provides what outcome?

A

Visibility for all.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are PI Planning inputs?

A
  • Vision/Product Vision

- Top 10 Features

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are PI Planning outputs?

A
  • PI Objectives (Team and Program)

- Program Board

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are some of the benefits provided by PI Objectives?

A
  • Common language for communicating with business and technology stakeholders is created
  • Near term focus and vision is created
  • AV (Achieved business Value) can be assessed by the Agile Release Train
  • Contribution by Team to business value is communicated/highlighted
  • Dependencies that require coordination are exposed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly