Describe the content of ISO19650.
ISO19650 is an international standard. Sets out the organisation and digitization of information about buildings in project over the whole life cycle.
What is PAS1192?
The BIM standard ssuperseeded by ISO19650.
What are the 4 status for information container in a CDE?
Work in progress, shared, published and archive.
What is an information model?
A set of structured or unstructured information containers.
What is PIM (project information model)
Information model relating to the delivery phase.
What is AIM (Assest information model)
Information model relating to the delivery phase.
What are organizational information requirements (OIR)?
The information requirements in relation to organizational objectives e.g. requirements for a airport if we need a new one.
What are asset information requirements (AIR)?
Information requirements in relation to the operation of the asset.
What are project information requirements (PIR)?
The information required to deliver the project/asset.
What are exchange information requirements (EIR)?
The information the client requires that bidders much declare if they can provide.
What is the information delivery cycle?
When an asset is being managed and something needs to be changed, relevant data is transfered from AIM to PIM then developed and turned back into AIM when delivered.
What is a BIM execution plan?
Explains how the information management aspects of the appointment will be carried out by the delivery team.