Role of the Contract Administrator (CA) Flashcards

1
Q

What is the Contract Administrator (CA)?

A

A person appointed by the Employer to administer the contract. They issue instructions, monitor progress, assess claims, and ensure both parties follow the contract (JCT SBC/Q)

JCT stands for Joint Contracts Tribunal, a body that produces standard forms of contracts for the construction industry.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the main responsibilities of the CA?

A

Issuing instructions and variations, certifying interim payments, granting extensions of time, issuing certificates (PC, NCC, etc.), monitoring progress and compliance, keeping records and communications, valuing loss & expense (with QS), facilitating dispute resolution

PC stands for Practical Completion, NCC stands for Non-Completion Certificate, and QS stands for Quantity Surveyor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Under JCT, which clause governs the contractor’s obligation to comply with CA instructions?

A

Clause 3.10 — Contractor must comply with CA/Architect instructions unless exempted (see 5.1.2, 2.23.2, CDM etc.)

CDM refers to the Construction (Design and Management) Regulations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the three hats worn by a Contract Administrator?

A

Agent for the Employer (issuing instructions), Certifier (interim payments, completion), Quasi-arbitrator (impartial decision-making on extensions/time/loss claims)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What certificates does the CA issue under JCT?

A

Interim Certificate (Clause 4.14/4.15), Non-Completion Certificate (Clause 2.31), Practical Completion Certificate, Certificate of Making Good Defects, Final Certificate (Clause 4.23)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How does the CA handle delay or non-completion?

A

Reviews contractor’s EoT application, issues Non-Completion Certificate if no EoT is justified, can recommend LADs be deducted (Clause 2.31 & 2.32)

EoT stands for Extension of Time, and LADs stands for Liquidated and Ascertained Damages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the CA’s duties in relation to time?

A

Give access to site (Date of Possession – Clause 2.4), monitor progress against Completion Date, grant Extension of Time for Relevant Events (Clause 2.28/2.29), issue revised Completion Dates if delay is valid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How does the CA interact with the Quantity Surveyor (QS)?

A

QS supports the CA in valuing variations, interim payments, and loss/expense; QS does the numbers; CA does the admin, instructions, and certification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What makes the CA role potentially difficult or controversial?

A

Balancing loyalty to the Employer with impartiality in certifying, pressure from both parties, high workload during variations, delay, and disputes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Can the CA delegate their powers?

A

Only if the contract allows it — the appointment letter or contract may allow specific tasks to be delegated (e.g. to Architect or Clerk of Works), but overall accountability remains

How well did you know this?
1
Not at all
2
3
4
5
Perfectly