Damages Flashcards

1
Q

What are contractual damages in construction?

A

Compensation payable when a party breaches contract. The goal is to put the innocent party in the position they would’ve been in if the contract had been performed (Robinson v Harman, 1848).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the two main types of contractual damages?

A
  • Liquidated and Ascertained Damages (LADs)
  • Unliquidated Damages
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are Liquidated and Ascertained Damages (LADs)?

A
  • A pre-agreed fixed sum set out in the contract
  • Must be a genuine pre-estimate of loss (not a penalty)
  • Example clause: JCT Clause 2.32
  • Example case: Dunlop v New Garage [1915]
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are unliquidated damages?

A
  • Damages that are assessed by the court after a breach
  • No fixed sum agreed in advance
  • Typically harder to enforce and calculate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When can LADs be applied under JCT?

A
  • Non-Completion Certificate issued by the Architect/CA (Clause 2.31)
  • Employer notifies intention to deduct LADs (Clause 2.32)
  • LADs must be set out in the Contract Particulars to be enforceable
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What happens if an Extension of Time (EoT) is granted after LADs are applied?

A

The Employer must repay any LADs deducted for the extended period (JCT Clause 2.32).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What clause in NEC4 deals with delay damages?

A

Secondary Option X7 – sets out the delay damages (LADs) rate and conditions for deduction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the purpose of LADs?

A
  • Avoid disputes
  • Give certainty
  • Save time/litigation
  • Reflect genuine potential losses (not penalties)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the “conditions precedent” to apply LADs under JCT?

A
  • Clause 2.31: Issue Non-Completion Certificate
  • Clause 2.32: Employer gives notice before Final Certificate
  • LAD clause must be in Contract Particulars
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What case shows failure to re-issue an NCC invalidates LADs?

A

Octoesse LLP v Trak Special Projects Ltd (2016) - If a new Completion Date is set after an NCC, a new NCC must be issued, or LADs become unenforceable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the test for damages to be valid in law?

A
  • Damages must arise naturally from the breach
  • Must be foreseeable by both parties
  • Must not be too remote
How well did you know this?
1
Not at all
2
3
4
5
Perfectly