Risk Management Flashcards

1
Q

What information would you expect to see on a Risk Register?

A
  • Risk ID
  • Date risk raised
  • Risk Status
  • Description of risk
  • Risk Response
  • Risk owner
  • Probability and Impact
  • Expected Monetary Value
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which risk would you normally price on a Risk Register?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Risk management process?

A
  • Identification
  • Analysis
  • Response to risk
  • Management of risk
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the purpose of a risk workshop?

A

Bring together all stakeholders on a project to identify risks from all backgrounds.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How do you evaluate a risks probability and impact?

A

Review time and cost implications of each risk and score the risk, typically 1-5 which is determined by the clients attitude to risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Is there any other way to assess a risk other than Probability and Impact?

A

Monte Carlo simulation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How does a Monte Carlo simulation work?

A

Data is inputted into programme and a simulation is ran to give a percentage likelihood of the risk occurring.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How does Monte Carlo differ to Probability and Impact?

A

Monte Carlo runs the simulation over a wide range of parameters and scenarios whereas Probability and Impact is done just the once.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Are you aware of EMV as a risk management method?

A

EMV utilises decision trees via a computer simulation to provide an overall EMV value based on multiple options. e.g. two sites

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the various risk responses?

A

SADEM:
- Shrink
- Accept
- Distribute
- Eliminate
- Monitor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When distributing or transferring a risk to another party, what do you have to consider?

A

The ability of the other party to manage that risk, the effect of them baring that risk and cost of transferring the risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Under traditional procurement, who bares the risk?

A
  • Client bares design risk
  • Contractor bares construction risk
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Under design and build procurement, who bares the risk?

A
  • Contractor bares construction risk
  • Design risk is transferred from Client to Contractor however client maintains some of the risk in terms of discrepancy in documents during pre-contract. e.g. missing something from Employers Requirements.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How do single stage and two stage tendering differ in terms of risk?

A

Design risk transfer remains the same however exposure to risks may reduce due to early contractor involvement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How would you calculate contingency on a project?

A
  • Utilising priced risk register
  • Or apply a percentage based on risks associates with the project based on the four risk parameters within NRM.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly