Quantification and Costing (of construction works) Flashcards

1
Q

What is the purpose of a BOQ?

A

It is a pricing document which provides a detailed breakdown of works by quantities to allow contractors to price by rates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the typical interim valuation process?

A
  • Contractor submits their valuation at agreed time
  • I visit site and review works done and make my assessment
  • I certify the amount I believe due or make my recommendation to the Contract Administrator
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the different volumes of NRM?

A

NRM 1 - Order of Cost Estimating and Cost Planning for Capital Building Works
NRM 2 - Detailed Measurement for Building Works
NRM 3 - Order of Cost Estimating and Cost Planning for Building Maintenance Works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the structure of NRM 1?

A
  • Introduction
  • Measurement rules for order of cost estimating
  • Measurement rules for cost planning
  • Tabulated rules of measurement for elemental cost planning
  • Appendices
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How do you ensure the quantities you take off are accurate?

A
  • Ensure I am measuring from scaled drawings and apply the correct scale.
  • Use NRM rules on how to quantify.
  • Measure GIFA and ask architect to confirm.
  • Follow key to ensure I am measuring the correct items.
  • Undertake CostX training to ensure - I am using software correctly.
  • Spot check against items such as door widths and known quantities.
  • Have quantities peer reviewed.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Are there any alternatives to a Contract Sum Analysis?

A
  • Bill of Quantities.
  • Activitiy schedule - a list of activities contractor must undertake to complete works.
  • Schedule of rates - pre agreed schedule that the contractor applies quants against as work is carried out.
  • schedule of works
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Can you name some sources available for costing?

A
  • BCIS
  • Market Rates App
  • SPONS pricing book
  • Specialist sub-contractor engagement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What factors must you consider of using SPONS?

A

Adjust for time and location.

Consider current market conditions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a Provisional Sum?

A

An allowance included within a contract for an element of work that is not yet defined enough for contractors to price.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly