Risk Management Flashcards

1
Q

What is a risk in the context of a construction project?

A

A potential event that, should it occur, will affect the project outcome

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is risk management?

A

A structured process for identifying and controlling risks throughout a construction project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the basic principles of risk management?

A

Risks should be:
- IDENTIFIED
- ASSESSED (qualitatively and/or quantitatively)
- RESPONDED TO (avoid, reduce, transfer, share or retain –> risk allowance)
- MONITORED

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the benefits of risk management in construction?

A
  • All construction projects involve risk
  • Managing risks can help achieve client’s time, cost and quality targets
    • TIME: reduce programme risks
    • COST: cost plan risk allowances
    • QUALITY: reduce design risks
  • Ensure risks are allocated to satisfy client’s risk appetite
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How can the client’s project team reduce design risk?

A
  • Effective management of the risk register through risk workshops
  • Transfer the risk in procurement (CDP in traditional or D&B)
  • Buildability input from early contractor involvement
  • Use a trusted and experienced design team
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Are you aware of any RICS guidance on risk management?

A

[Guidance Note] Management of risk, 1st edition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the risk response/mitigation strategies in Management of risk 1st edition?

A
  1. AVOID: eliminate the risk e.g. alternative design or project cancellation
  2. REDUCE the probability of the risk occurring or its impact e.g. alternative design or different construction method
  3. TRANSFER the risk to another party able to better control it, usually involves a premium to be paid e.g. to the contractor
  4. SHARE: some of the risk is transferred to another party, while other elements of the risk are retained by the client
  5. RETAIN: client retains the risk, appropriate risk allowance made in the cost plan (residual risk exposure)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a risk management strategy?

A

A strategy outlining how risks will be handled on a project. This could include:
- how risks will be identified e.g. risk workshops, and their frequency
- how risks will be recorded and assessed (risk register)
- who’s responsible for recording identified risks
- who’s responsible for managing each risk (each risk has an owner who is best suited to manage it)
- the client’s risk appetite
- how risks are to be reported to the client e.g. via regular meetings or monthly reports

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Who should own a risk?

A

The person/organisation best suited to manage the risk

Depends on the procurement route but generally:
- architectural design risk = architect
- structural design risk = structural engineer
- cost risks = QS
- programme risk = contractor / PM

On a higher project level:
- client should manage their risks
- contractor should manage their risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How do you monitor and report risks?

A
  • All risks are recorded and monitored throughout the project in the risk register
  • Risks can be reported to the client via regular meetings or monthly reports (see risk management strategy)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a risk register?

A

A schedule of all identified risks on a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What information would you find in a risk register?

A

Typically for each risk:
- ref nr
- description
- category (e.g. programme, design, planning etc)
- probability (1-5)
- impact (1-5)
- overall score (1-25) (probability * impact)
- risk status
- due date
- raised by
- risk owner
- open/closed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What types of risk assessment/analysis are there?

A

Qualitative: assesses risks using descriptive terms such as ‘high probability’ and ‘low impact’

Quantitative: assesses risks by assigning values such as ‘probability of 65%’ or ‘impact of £2m’
- Expected Monetary Value (EMV) = probability * cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How do you go about creating a risk register for a new project?

A

Bring the project team together at a risk workshop:
- Identify all possible risks
- Qualitative risk assessment: assign ‘probability’ and ‘impact’ values to each risk to give an overall risk score, then rank them accordingly
- Quantitative risk assessment: cost the risks
- Allocate an ‘owner’ to each risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a risk workshop?

A
  • A meeting between the project team to identify risks, discuss actions for already known risks
  • Risk register is usually updated following a risk workshop
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is risk allocation?

A
  • Assigning a risk a “risk owner” who is then responsible for managing that risk
  • Risks should be allocated to those best able to manage them
  • This allocation should be clearly identified in the risk register under the ‘risk owner’ column
17
Q

How do you use the risk register (post-contract)?

A
  • Monitor existing items in the register
  • Update it throughout the project as new risks are identified or when newer information about a risk already recorded becomes available. Obtain additional risk allowance if necessary
  • Any risks that haven’t materialised and are are no longer a risk are closed out. Associated risk allowance can be re-allocated or given back to client
18
Q

What is risk allowance?

A

An allowance made in a cost estimate to protect the client from any residual risk

19
Q

What are the main risk allowance categories in NRM1?

A
  1. DESIGN DEVELOPMENT risk
    - An allowance for use during the design phase for risks associated with design development, changes in estimating data, third-party risks e.g. planning requirements or delays in tendering
  2. CONSTRUCTION risk
    - An allowance for use during the construction phase for risks associated with site conditions e.g. access restrictions or existing buildings
  3. EMPLOYER CHANGE risk
    - An allowance for use during the design and construction phases for risks associated with employer-driven changes e.g. change to scope of works, or quality/time requirements
  4. EMPLOYER OTHER risk
    - An allowance for other employer risks e.g. early handover, acceleration or availability of funds
20
Q

How would you calculate risk allowance?

A

Depends on the project RIBA stage…

OoCE:
- Likely a %, e.g. based on a similar past project

Cost Plan:
- Compile risk register, cost the risks. Include costs associated with the residual risks
- Risk allowance = design development risk + construction risk + employer change risk + employer other risk

21
Q

What is Central limit theorem?

A

A mathematical technique used to provide a 90% confidence level for a project contingency fund

22
Q

What is a Monte Carlo simulation?

A

A computer-generated simulation used to model outcomes

23
Q

Why is a QS ideally suited to act as a risk manager?

A
  • Risk is present in all projects and QSs make decisions which can have a major impact on risk
  • The QS can quantify the impacts of risks in terms of cost and time
24
Q

What is the role of a QS in terms of risk management?

A
  • The QS can quantify the impacts of risks in terms of cost and time
  • Ensure risks are allocated to satisfy client’s risk appetite
  • Ensure there’s adequate risk allowance in the cost plan to cover the residual risk (the risk retained by the client)
25
Q

What are the problems to the QS regarding cost control of piling?
Whose risk is the piling?

A
  • Pile depths are never a certainty (risk)
  • Procurement route determines who takes the risk