Project Finance Flashcards
What is post contract cost control?
Managing the contract sum and any variations during the programme, so that the project remains affordable and funds are available when needed
Why do we need post contract cost control?
Ensures:
- project remains affordable
- risks are managed throughout the project
What is an Interim Payment Application?
- A document prepared by the contractor containing their progress against each of the work elements
- Revalues the whole work, not just the work done since the last valuation
- Precursor to the issue of an interim payment certificate
(basis of contractor’s application for payment varies depends contract type used)
What are interim valuations?
Why do we do them?
- Payment for completed works at agreed regular intervals during the project, rather than a lump sum at completion
- Used on larger projects to ease contractor’s cash flow, as project finance is cheaper for the client than the contractor (unrealistic to expect contractor to finance project)
What are the 4 valuation rules?
- Use BoQ rates
- Star rates (adjust BoQ rates)
- Day works
- Fair and reasonable price
What are the main elements of an interim valuation?
- Measured works to date
- Materials on/off-site
- Preliminaries
- Variations
- Retention
- Payments on account
- Extension of time (JCT)
- Loss and expense (JCT)
(adjustment of prime cost sums, provisional sums (JCT))
What are the key considerations of an interim valuation?
Frequency/timing - see payment schedule
What the contract says about:
- Payment timeline (notice to withhold etc)
- Materials
- Variations
- Retention
Approach: setting up the spreadsheet so it
- clearly shows movement in the month
- breaks items down so they’re easier to value (e.g. floor types)
Relationship with the contractor’s QS
(common QS mistakes: using wrong previously cert value, no certificates)
How would you assess the interim valuation?
- Review contractor’s application – identify any movement in the month
- Walk around site with contractor: check work completed, materials on-site
- Carry out my assessment - apply appropriate %s
- Agree valuation with contractor (negotiation)
- Create a recommendation letter based on my assessment, issue to the EA who issues the payment certificate
(liaise with the clerk of works (JCT), value preliminaries, agree variations, check materials off-site)
How are works valued?
Contractually:
- Interim payments: payment for completed work at agreed regular intervals during the project, rather than a lump sum at completion (can be based on a BoQ, Pricing Schedule or Activity Schedule)
- Stage payments: payment for completed work upon reaching an agreed milestone
(Calculations can be based on:
- Activity Schedule: assessed in terms of % achieved or completion of activity.
- Milestones reached on a pre-agreed programme
- Measurement against a BoQ/CSA
- Stage payments against calendar date)
What are the implications of over or under valuing the works?
- Overvaluing the works puts the employer at risk of paying sums in exchange for no benefit
- Undervaluing the works creates unreasonable cashflow issues for the contractor
(interim valuation must be a realistic assessment)
What would you do if the contractor claims for paint in their 1st interim valuation?
- Assuming the project is new build, the contractor is probably front-loading
- I would assess if they had done any painting during the site visit and adjust the valuation accordingly
What are the key things you should consider prior to valuing materials off-site?
Depends on contract:
- Request a vesting certificate
- Check materials are clearly marked for the project and are separate from other materials
- Check insurance is in place until the materials arrive on site
- Check material off-site bond has been provided
What needs to be in place to make payment for materials on-site?
Materials should:
- be adequately protected
- be covered by the works insurance
- arrive on-site within a reasonable time before they’re needed e.g. delivering doors in the first week of a new build project wouldn’t be appropriate
What is a vesting certificate?
A document evidencing that ownership of materials will transfer from one party to another on payment
What is a ‘payment on account’?
Payment against an item of work (or materials) for which no instruction has been issued but is anticipated, and both sides agree that some payment is due
Can you explain what is meant by the term ‘daywork’?
- Contractor is paid for their work based on the materials, plant, labour used plus OH&P
- Used when work cannot be priced in the normal way
What is a variation?
An alteration to the scope of work originally specified in the contract through addition, omission or substitution of the works, or changing the way in which the works are carried out
What information is typically shown on a payment certificate?
- Certificate and contract date
- Contractor, employer and EA’s details
- Site address and project number
- Contract Sum
. - Gross valuation
- Less retention
- Less works not in accordance with contract
- Net valuation
- Less cumulative value of previous payments
- Amount due (excluding VAT)
. - EA’s signature
What happens if the employer fails to pay the amount due (on the payment certificate) on or before the final date for payment?
- Employer will be liable for interest on the amount due (subject to contract conditions)
- Contractor may exercise their right to suspend part or all of the works
What is a ‘pay less notice’?
Gives the paying party the right to withhold all or part of the notified sum
What are the employer’s obligations if they wish to withhold the notified sum, but fail to issue a pay less notice?
If the paying party doesn’t serve a valid pay less notice timeously, they are obliged to pay the notified sum in full, regardless of whether they have a valid challenge to the sum
Can you explain the payment timeline for the JCT Design & Build 2016 contract?
(a) INTERIM VALUATION DATE - contractor required to make an Interim Payment Application before this date
(b=a+7) DUE DATE - date up to which the works are valued
(b+5) Payment Notice - employer issues contractor a ‘Payment Notice’, stating the sum they consider to be due to the contractor at the due date, otherwise application becomes the Interim Payment Application
(c-5) Payless Notice - if the employer will pay less than the sum in the Interim Payment Application, they must notify the contractor
(c=b+14) FINAL DATE FOR PAYMENT - employer must pay contractor on or before this date
(NB: Interim Payment Application (or Payment Notice) = contractor’s assessment of money employer owes them)
What are change control procedures?
- Ensure variations are identified, costed and approved prior to issuing instructions
- This ensures value for money and impact (e.g. disruption to current work) are considered before a variation is either approved, pending or rejected
Changes include:
- PM or architect instructions
- design development
- site instruction or RFIs
- client changes
- VE
(include contingency in variation cost build-up)
How is change captured in a cost report?/
How do you report change to the client?
Under the EAI section (change control log), each variation has a:
- description
- cost
- funding source e.g. risk allowance, budget transfer or external source to project
AI section describes variations that haven’t yet been approved through change control, e.g. mentioned at progress meetings or informal discussion with contractor and design team
What’s included in a change control form?
Depends on project, but generally:
- change request number
- date raised
- change type
- change description incl. impact on cost, time and area (GIA/NIA loss/gain)
- change justification
- authorisation section
- distribution section
Why does the QS typically fill out the change control form?
The QS can be perceived as an impartial “intermediary” between the contractor and design team