Review of All Chapters Flashcards

1
Q

This is a matrix chart that only uses the activities of responsible, accountable, consult, and inform.

A

RACI chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A moderator-led requirements collection method to elicit requirements from stakeholders.

A

Focus groups

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A schedule compression approach that adds more resources to activities on the critical path to complete the project earlier. When doing this in a project, costs are added because the associated labor and sometimes resources (such as faster equipment) cause costs to increase.

A

Crashing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A project management subsidiary plan that documents the decisions made in the procurement planning processes.

A

Procurement management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

This plan details the project procedures for entertaining change requests: how change requests are managed, documented, approved, or declined.

A

Change management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

This is a statistical approach to predicting what future values may be, based on historical values. This creates quantitative predictions based on variables within one value to predict variables in another. This form of estimating relies solely on pure statistical math to reveal relationships between variables and to predict future values.

A

Regression analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The level of ownership an individual or entity has over a project risk.

A

Risk responsibilities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Part of stakeholder analysis classification. A ______ stakeholder is aware of your project and is not concerned if the project succeeds or fails.

A

Neutral stakeholder status

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

This type of communication pulls information from a central repository. This allow stakeholders to retrieve information from a central source as needed.

A

Pull communications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Theory is based on the participative management style of the Japanese. This theory states that workers are motivated by a sense of commitment, opportunity, and advancement.

A

Ouchi’s Theory Z

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The cost management plan dictates how cost variances will be managed.

A

Cost management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

4.2 Develop Project Management Plan - Outputs

A

Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

This is the cost associated with the monies spent to attain the expected level of quality. It is also known as the cost of quality.

A

Cost of conformance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

As with value engineering, this approach examines the functions of the project’s product in relation to the cost of the features and functions. This is where, to some extent, the grade of the product is in relationship to the cost of the product.

A

Value analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A market condition where the market is so tight that the actions of one vendor affect the actions of all the others.

A

Oligopoly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

An “act of God” that may have a negative impact on the project. Examples include fire, hurricanes, tornadoes, and earthquakes.

A

Force majeure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

A mathematical model to examine the relationship among project variables, like cost, time, labor, and other project metrics.

A

Regression analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Also known as firm fixed-price and lump-sum contracts, these are agreements that define a total price for the product the seller is to provide.

A

Fixed-price contracts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

An estimating technique for each activity that requires optimistic, most likely, and pessimistic estimates to be created. Based on these three estimates, an average can be created to predict how long the activity should take.

A

Three-point estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Earned after the PMP to maintain the PMP certification. PMPs are required to earn 60 per three-year certification cycle. Of the 60, a minimum of 35 hours must come from educational opportunities.

A

Professional Development Units (PDUs)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Comparing any two similar entities to measure their performance.

A

Benchmarking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

The hidden goals, personal agendas, and alliances among the project team members and the stakeholders.

A

Political interfaces

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Many vendors can provide what your project needs to purchase, but you prefer to work with a specific vendor.

A

Single source

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

These are useful in providing information to customers, management, the project team, and other stakeholders.

A

Project presentations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

This approach requires that both parties give up something.

A

Compromising

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

The work that a role performs.

A

Responsibility

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Logic that describes activities that must happen in a particular order. For example, the dirt must be excavated before the foundation can be built. The foundation must be in place before the framing can begin. Also known as a mandatory dependency.

A

Hard logic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

These estimates are often referred to as “should cost” estimates. They are created by the performing organization or outside experts to predict what the cost of the procured product should be.

A

Independent estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Theory which states our needs are acquired and developed by our experiences over time. All people are, according to this theory, driven by one of three needs: achievement, affiliation, or power.

A

McClelland’s Theory of Needs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

A chart showing the relationship between superior and subordinate employees, groups, disciplines, and even departments.

A

Hierarchical organizational chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

This subsidiary plan defines how changes to the features and functions of the project deliverables will be monitored and controlled within the project.

A

Configuration management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

A scope definition approach that studies and analyzes a system, its components, and the relationship of the components within the system.

A

Systems analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

These are the demands set by the customer, regulations, or the performing organization that must exist for the project deliverables to be acceptable. These are often prioritized in a number of ways, from “must have” to “should have” to “would like to have.”

A

Project requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

A method to rate potential project team members based on criteria such as education, experience, skills, knowledge, and more.

A

Multicriteria Decision Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

This is a table that maps the requirements throughout the project all the way to their completion.

A

Requirements traceability matrix (RTM)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

An organization where organizational resources are pooled into one project team, but the functional managers have more project power than the project manager.

A

Weak matrix structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

A process to identify which parts of the project warrant procurement from a vendor by the buyer.

A

Procurement planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Stakeholders are mapped on a grid based on their influence over the project in relation to their influence over the project execution.

A

Influence/impact grid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

This is a centralized database consisting of the outcome of all the other risk management processes, such as the outcome of risk identification, qualitative analysis, and quantitative analysis.

A

Risk register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

This is an analysis meeting to examine and document the roles in the project. The role’s interests, concerns, influence, project knowledge, and attitude are documented.

A

Profile analysis meeting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Defines how the project schedule will be created and managed

A

Schedule management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

The project manager has a warm personality that others like.

A

personal or charismatic power

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

An organization that creates a blend of the functional, matrix, and project-oriented structures.

A

Hybrid structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

A WBS companion document that defines all of the characteristics of each element within the WBS.

A

WBS dictionary

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

A ranking approach that identifies and ranks the risks from very high to very unlikely or to some other value

A

Ordinal scales

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

Part of stakeholder analysis classification. An ______ status means the stakeholder doesn’t know about the project and the effect the project may create on the stakeholder.

A

Unaware stakeholder status

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

4.2 Develop Project Management Plan - Tools & Technitques

A

Expert JudgementData GatheringInterpersonal and Team SkillsMeetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

A matrix that ranks the probability of a risk event occurring and its impact on the project if the event does happen; used in qualitative and quantitative risk analyses.

A

Probability and impact matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

Notices to the stakeholders about resolved issues, approved changes, and the overall health of the project.

A

Stakeholder notifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

The leader is motivating, has high-energy, and inspires the team through strong convictions about what’s possible and what the team can achieve. Positive thinking and a can-do mentality are characteristics of this.

A

charismatic leadership

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

The location and culture of the environment where the project work will reside. Includes the social, economic, and environmental variables the project must work with or around.

A

Project environment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

An anonymous method of querying experts about foreseeable risks within a project, phase, or component of a project. The results of the survey are analyzed by a third party, organized, and then circulated to the experts. There can be several rounds of anonymous discussion with the this, without fear of backlash or offending other participants in the process. The goal is to gain consensus on project risks within the project

A

Delphi Technique

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

This is a project plan component that contains all of the information related to the risk management activities. It’s updated as risk management activities are conducted to reflect the status, progress, and nature of the project risks.

A

Risk register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

A business unit that centralizes the operations and procedures of all projects within the organization. The PMO can be supportive, controlling, or directive.

A

Organizational System

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

The primary output of breaking down the WBS work packages.

A

Activity list

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

The device that encodes the message being sent.

A

Encoder

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

A histogram that illustrates and ranks categories of failure within a project

A

Pareto diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

This is the process of examining the project from the perspective of each characteristic: strengths, weaknesses, opportunities, and threats.

A

SWOT analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

The management and selection of projects that support an organization’s vision and mission. It is the balance of project priority, risk, reward, and return on investment. This is a senior management process.

A

Project portfolio management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

A method to flatten the schedule when resources are overallocated. This can be applied using different methods to accomplish different goals. One of the most common methods is to ensure that workers are not overextended on activities

A

Resource-leveling heuristic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

This project scope statement creation process studies how a system should work, designs and creates a system model, and then enacts the working system based on the project’s goals and the customer’s expectations. This aims to balance the time and cost of the project in relation to the scope of the project.

A

Systems engineering

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

A contingency allowance to account for overruns in costs. Contingency allowances are used at the project manager’s discretion and with management’s approval to counteract cost overruns for scheduled activities and risk events.

A

Contingency reserve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

The project manager is respected or admired because of the team’s past experiences with the project manager. This is about the project manager’s credibility in the organization.

A

referent power

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

Documents the quality objectives for the project, including the metrics for stakeholder acceptance of the project deliverable.

A

Quality baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

These diagrams show the relationship between elements of an environment. For example, this would illustrate the networks, servers, workstations, and people that interact with the elements of the environment.

A

Context diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

A fixed-price contract with a special allowance for price increases based on economic reasons such as inflation or the cost of raw materials.

A

Fixed-price with economic price adjustments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

Created and maintained by the project sponsor and shows the financial validity of why a project is chartered and launched within the organization. Typically, this is created before the launch of the project and may be used as a go/no-go decision point.

A

Project business case

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

Documented in the scope management plan, this system defines how changes to the project scope are managed and controlled.

A

Change control system (CCS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

A meeting of all the project’s potential vendors to clarify the contract statement of work and the details of the contracted work.

A

Bidder conference

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

An organization that is divided into functions, and each employee has one clear functional manager. Each department acts independently of the other departments. A project manager in this structure has little to no power and may be called a project coordinator.

A

Functional structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

This document authorizes the project. It defines the initial requirements of the project stakeholders. It is endorsed by an entity outside of the project boundaries.

A

Project charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

The monetary value of a risk exposure based on the risk’s probability and impact in the risk matrix. This approach is typically used in quantitative risk analysis because it quantifies the risk exposure

A

Expected monetary value (EMV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

In formal presentations, the presenter’s oral and body language, visual aids, and handouts all influence the message being delivered.

A

presentation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
74
Q

New risks that are created as a result of a risk response.

A

Secondary risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
75
Q

A quality control chart that maps the performance of project work over time.

A

Control chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
76
Q

The difference of the earned value amount and the cumulative actual costs of the project. The formula is EV – AC.

A

Cost variance (CV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
77
Q

The path in the project network diagram that cannot be delayed, otherwise the project completion date will be late. There can be more than one. Activities in the this have no float.

A

Critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
78
Q

This type of communication means that information is happening among stakeholders, like in a forum. Examples of this are meetings, videoconferences, phone calls, and ad-hoc conversations. Interactive communications means that the participants are actively communicating with one another.

A

Interactive communications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
79
Q

The results of the project work as needed. This includes technical performance measures, project status, information on what the project has created to date, corrective actions, and performance reports

A

Work performance information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
80
Q

Theory that states management views workers in the Y category as competent and self-led and workers in the X category as incompetent and needing to be micromanaged.

A

McGregor’s Theory of X and Y

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
81
Q

As with brainstorming, participants are encouraged to generate as many ideas as possible, but the suggested ideas are ranked by a voting process.

A

Nominal group technique

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
82
Q

The person who receives the message.

A

Receiver

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
83
Q

This diagram breaks down ideas, solutions, causes, and project components and groups them together with other similar ideas and components.

A

Affinity diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
84
Q

This project scope statement component works with the project requirements, but focuses specifically on the product and what the conditions and processes are for formal acceptance of the product.

A

Product acceptance criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
85
Q

The difference between the earned value and the planned value. The formulas is EV – PV.

A

Schedule variance (SV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
86
Q

This theory states that people will behave based on what they expect as a result of their behavior. In other words, people will work in relation to the expected reward.

A

Vroom’s Expectancy Theory

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
87
Q

A somewhat unreliable estimating approach that relies on historical information to predict what current activity durations should be. This estimating is more reliable, however, than team member recollections. This estimating is also known as top-down estimating and is a form of expert judgment.

A

Analogous estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
88
Q

The actual amount of monies the project has spent to date.

A

Actual cost (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
89
Q

The areas of expertise, industry, or function where a project is centered. Examples include architecture, IT, health care, and manufacturing.

A

Application areas

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
90
Q

This is a narrative description of what the project is creating as a deliverable for the project customer.

A

Product scope description

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
91
Q

This is part of stakeholder analysis classification. A _____ stakeholder is aware of your project and is supportive and hopeful that the project will be successful.

A

Supportive stakeholder status

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
92
Q

The leader puts others first and focuses on the needs of the people he serves. These leaders provide opportunity for growth, education, autonomy within the project, and the well-being of others. The primary focus is service to others.

A

servant leadership

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
93
Q

The formal inspection of the project deliverables, which leads to project acceptance.

A

Scope validation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
94
Q

A risk response appropriate for both positive and negative risks, but often used for smaller risks within a project.

A

Acceptance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
95
Q

The earliest a project activity can begin. Used in the forward pass procedure to discover the critical path and the project float.

A

Early start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
96
Q

An approach that relies on historical information to predict the cost of the current project. It is also known as top-down estimating and is the least reliable of all the cost-estimating approaches

A

Analogous estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
97
Q

From buyer to seller. Requests the seller to provide a proposal to complete the procured work or to provide the procured product.

A

Request for Proposal (RFP)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
98
Q

Calendars that identify when project resources are available for the project work.

A

Resource calendars

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
99
Q

This documentation of what the stakeholders expected in the project defines all of the requirements that must be present for the work to be accepted by the stakeholders.

A

Requirements documentation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
100
Q

Conditions that affect how the project manager may manage the project. Come from within the project, such as policy, or they be external to the organization, such as law or regulation.

A

Enterprise environmental factors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
101
Q

Low-priority risks are identified and assigned to a watch list for periodic monitoring.

A

Low-priority risk watch list

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
102
Q

Status of the deliverables: the work that’s been started, finished, or has yet to begin.

A

Work performance information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
103
Q

This is anything that limits the project manager’s options. Consider a predetermined budget, deadline, resources, or materials the project manager must use within the project—these are all examples of these

A

Project constraints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
104
Q

This document requires that the seller fully describe the work to be completed and/or the product to be supplied. This becomes part of the contract between the buyer and the seller.

A

Contract statement of work (SOW also CSOW)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
105
Q

The contractual relationship between the buyer and the seller is often considered confidential and secret

A

Privity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
106
Q

Raw data, observations, and measurements about project components. Gathered and stored in the project management information system.

A

Work performance data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
107
Q

A report that depicts how well a project is performing. Often, the this is based on earned value management and may include cost or schedule variance reports.

A

Performance report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
108
Q

This is the planned start and finish of the project. The comparison of what was planned and what was experienced is the schedule variance.

A

Schedule baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
109
Q

The monies spent to recover from not adhering to the expected level of quality. Examples may include rework, defect repair, loss of life or limb because safety precautions were not taken, loss of sales, and loss of customers. This is also known as the cost of nonconformance to quality.

A

Cost of poor quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
110
Q

A management process that defines the quality system or quality policy that a project must adhere to. This aims to plan quality into the project rather than to inspect quality into a deliverable.

A

Quality assurance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
111
Q

The consideration of the risk ranking scores that takes into account any bias, the accuracy of the data submitted, and the reliability of the nature of the data submitted.

A

Data precision

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
112
Q

When there is an issue or claim that must be settled before the contract can be closed, the parties involved in the issue or claim will try to reach a settlement through mediation or arbitration.

A

Alternative dispute resolution

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
113
Q

A contract type in which the buyer pays for the time and materials for the procured work. This is a simple contract, usually for smaller procurement conditions. These contract types require a not-to-exceed clause, or the buyer assumes the risk for cost overruns.

A

Time and materials contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
114
Q

A temporary endeavor to create a unique product, service, or result. The end result of a project is also called a deliverable.

A

Project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
115
Q

This subsidiary plan defines the risk responses that are to be used in the project for both positive and negative risks

A

Risk response plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
116
Q

The organization of the product materials, details, and prior product documentation.

A

Configuration status accounting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
117
Q

A tool that filters or screens out vendors that don’t qualify for the contract.

A

Screening system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
118
Q

An organization’s approach to managing cash flow against the project deliverables based on a schedule, milestone accomplishment, or data constraints

A

Funding limit reconciliation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
119
Q

Defines how the project scope will be planned, managed, and controlled.

A

Project scope management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
120
Q

Anything that prohibits communication from occurring.

A

Communication barrier

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
121
Q

A situation where a project manager may have two competing duties of loyalty. For example, purchasing software from a relative may benefit the relative, but it may do harm to the performing organization.

A

Conflict of interest

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
122
Q

These are significant points or events in the project’s progress that represent accomplishment in the project. Projects usually create these as the result of completing phases within the project.

A

Milestone

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
123
Q

A method to determine which of two or more decisions is the best one. The model examines the costs and benefits of each decision’s outcome and weighs the probability of success for each of the decisions.

A

Decision tree

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
124
Q

A benefit comparison model to determine a future value of money. The formula to calculate future value is FV = PV(1 + I)n, where PV is present value, I is the given interest rate, and n is the number of periods.

A

Future value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
125
Q

Part of stakeholder analysis classification. _____ is aware of your project, they want your project to be successful, and the stakeholder is working to make certain the project is a success.

A

Leading stakeholder status

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
126
Q

These risks deal with faults in the management of the project: the unsuccessful allocation of time, resources, and scheduling; unacceptable work results; and poor project management.

A

Project management risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
127
Q

This hierarchical chart can decompose the project by the type of resources used throughout it.

A

Resource breakdown structure (RBS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
128
Q

The individual has power and control of the data gathering and distribution of information.

A

informational power

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
129
Q

A person who has proven project management experience and has qualified for and then passed the Exam.

A

Project Management Professional (PMP)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
130
Q

A numbering system for each item in the WBS. The PMBOK is a good example of a this, as each chapter and its subheadings follow a logical numbering scheme. For example, PMBOK 5.3.3.2 identifies an exact paragraph in the PMBOK.

A

Code of accounts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
131
Q

The leader is a hybrid of transactional, transformational, and charismatic leaders. The _____ wants the team to act, is excited and inspired about the project work, yet still holds the team accountable for their results.

A

interactional leadership

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
132
Q

The leader inspires and motivates the project team to achieve the project goals. These leaders aim to empower the project team to act, be innovative in the project work, and accomplish through ambition.

A

transformational leadership

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
133
Q

If a project team can reach the this stage of team development, they trust one another, work well together, and issues and problems get resolved quickly and effectively.

A

Performing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
134
Q

A WBS entry that considers the time, cost, and scope measurements for that deliverable within the WBS. The estimated performance is compared against the actual performance to measure overall performance for the deliverables within this. The specifics of this are documented in this plan.

A

Control account

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
135
Q

This approach _____ out the conflict by minimizing the perceived size of the problem. It is a temporary solution, but can calm team relations and boisterous discussions.

A

Smoothing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
136
Q

A ranking approach to identify the probability and impact by using a numerical value, from .01 (very low) to 1.0 (certain).

A

Cardinal scales

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
137
Q

The sender confirms that the receiver understands the message by directly asking for a response, questions for clarification, or other confirmation.

A

Feedback

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
138
Q

This is not a contract, but a letter stating that the buyer is intending to create a contractual relationship with the seller.

A

Letter of intent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
139
Q

This plan is an input to the control scope process. It defines how changes to the features and functions of the project deliverable, the product scope, may enter the project.

A

Configuration management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
140
Q

Risks that are expected to remain after a risk response.

A

Residual risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
141
Q

A process of choosing a percentage of results at random. For example, a project creating a medical device may have 20 percent of all units randomly selected to check for quality.

A

Statistical sampling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
142
Q

A risk response that shares the advantages of a positive risk within a project.

A

Sharing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
143
Q

The documented approach of how a project will be planned, executed, monitored and controlled, and then closed. This document is a collection of subsidiary management plans and related documents.

A

Project management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
144
Q

Costs are parallel to each WBS work package. The costs of each work package are aggregated to their corresponding control accounts. Each control account then is aggregated to the sum of the project costs.

A

Cost aggregation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
145
Q

Assurance provided to the external customers of the project.

A

External QA

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
146
Q

The monies spent to attain the expected level of quality within a project. Examples include training, testing, and safety precautions.

A

Cost of quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
147
Q

This explains the overall project risks and provides summaries about the individual project risks.

A

Risk report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
148
Q

The processed and analyzed data that will help the project manager make project decisions.

A

Work performance information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
149
Q

An organization of project management professionals from around the world, supporting and promoting the careers, values, and concerns of project managers.

A

Project Management Institute (PMI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
150
Q

An assumption is something that is believed to be true or false, but it has not yet been proven to be true or false. Assumptions that prove wrong can become risks for the project. All identified project assumptions are recorded in this for testing and analysis, and the outcomes are recorded.

A

Assumption log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
151
Q

The project manager has deep skills and experience in a discipline (for example, years of working in IT helps an IT project manager better manage IT projects).

A

expert power

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
152
Q

4.2 Develop Project Management Plan - Inputs

A

Project CharterOutputs from other processesEnterprise Environmental FactorsOrganizational process assets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
153
Q

Flowcharts that illustrate the flow of a process through a system, such as a project change request through the change control system, or work authorization through a quality control process.

A

System or process flowcharts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
154
Q

A data gathering technique that’s similar to brainstorming, but provides brainstorming meeting participants with the questions and topics for brainstorming before the stakeholder identification meeting.

A

Brain writing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
155
Q

Meetings are forms of communication. How the meeting is led, managed, and controlled all influence the message being delivered. Agendas, minutes, and order are mandatory for effective communications within a meeting.

A

meeting management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
156
Q

The performing organization can contribute to the project’s risks through unreasonable cost, time, and scope expectations; poor project prioritization; inadequate funding or the disruption of funding; and competition with other projects for internal resources.

A

Organizational risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
157
Q

A person who has slightly less project management experience than a PMP

A

Certified Associate in Project Management (CAPM)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
158
Q

Risk is an uncertain event or condition that may affect the project outcome. This defines how the project will manage risk.

A

Risk management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
159
Q

This approach maps ideas to show the relationship among requirements and the differences between requirements. The map can be reviewed to identify new solutions or to rank the identified requirements.

A

Mind mapping

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
160
Q

The latest a project activity can finish. Used in the backward pass procedure to discover the critical path and the project float.

A

Late Finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
161
Q

The science of using past results to predict future performance.

A

Trend analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
162
Q

The project team identifies the disciplines and specialties that the project will require to complete the project scope statement. These are the resources that will be doing the project work.

A

Technical interfaces

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
163
Q

The person with the power makes the decision.

A

Forcing power

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
164
Q

Internal relationships to the project or the organization. For example, the project team must create the software as part of the project’s deliverable before the software can be tested for quality control.

A

Internal dependencies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
165
Q

A fixed-price contract with opportunities for bonuses for meeting goals on costs, schedule, and other objectives. These contracts usually have a price ceiling for costs and associated bonuses.

A

Fixed-price incentive fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
166
Q

Describe organizations that have duplication of efforts within the organization, but not within each department or division of the organization. Project manager has little authority in this structure and the functional manager controls the project budget.

A

Multidivisional structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
167
Q

The receiver confirms that the message is being received through feedback, questions, prompts for clarity, and other signs of confirmation.

A

Active listening

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
168
Q

This conflict resolution method sees one side of the argument walking away from the problem, usually in disgust.

A

Withdrawal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
169
Q

These show the hierarchies and decomposition of a solution, an organization, or a project team. The WBS and an org chart are examples of this

A

Tree diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
170
Q

Measures the project based on its financial performance. The formula is EV/AC

A

Cost performance index (CPI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
171
Q

This is the most common and most effective approach to communication. It’s where two or more people exchange information. Consider status meetings, ad-hoc meetings, phone calls, and videoconferences.

A

Interactive communication

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
172
Q

An inspection-driven process that measures work results to confirm that the project is meeting the relevant quality standards.

A

Control quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
173
Q

A risk response that is appropriate for both positive and negative risk events that may outside of the project manager’s authority to act upon.

A

Escalating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
174
Q

A risk response to avoid the risk.

A

Avoidance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
175
Q

The device or technology that transports a message.

A

Medium

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
176
Q

These cause-and-effect diagrams are also called fishbone diagrams and are used to find the root cause of factors that are causing risks within the project.

A

Ishikawa diagrams

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
177
Q

Include organizational processes, policies, procedures, and items from a corporate knowledge Grouped into two categories to consider: processes, policies and procedures, and organizational knowledge bases.

A

Organizational process assets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
178
Q

According to ASQ, the degree to which a set of inherent characteristics fulfills requirements.

A

Quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
179
Q

The project manager can make the team and stakeholders feel guilty to gain compliance in the project.

A

guilt-based power

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
180
Q

Most projects have a determined budget in relation to the project scope. There may be a qualifier on this budget, such as plus or minus 10 percent based on the type of cost estimate created.

A

Funding limit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
181
Q

A diagram that visualizes the flow of the project activities and their relationships to other project activities.

A

Project network diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
182
Q

Reports are formal communications on project activities, their status, and conditions.

A

Project reports

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
183
Q

Costs are attributed directly to the project work and cannot be shared among projects (for example, airfare, hotels, long-distance phone charges, and so on).

A

Direct costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
184
Q

This approach to project scope statement creation attempts to find the correct level of quality in relation to a reasonable budget for the project deliverable while still achieving an acceptable level of performance of the product.

A

Value engineering

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
185
Q

Cost reserves are for unknown unknowns within a project. The management reserve is not part of the project cost baseline, but is included as part of the project budget.

A

Reserve analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
186
Q

The project manager refuses to act, get involved, or make decisions.

A

avoiding power

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
187
Q

This approach confronts the problem head-on and is the preferred method of conflict resolution. Multiple viewpoints and perspectives contribute to the solution.

A

Collaborate/Problem solving

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
188
Q

An approach using a parametric model to extrapolate what costs will be needed for a project (for example, cost per hour and cost per unit). It can include variables and points based on conditions.

A

Parametric estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
189
Q

This plan defines what quality means for the project, how the project will achieve quality, and how the project will map to organizational procedures pertaining to quality.

A

Quality management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
190
Q

A document created and maintained by the project sponsor and the project manager. Defines what benefits the project will create, when the benefits will be realized, and how the benefits will be measured.

A

Project benefits management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
191
Q

This defines all of the work, and only the required work, to complete the project objectives.

A

Project scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
192
Q

The ability to interact, lead, motivate, and manage people.

A

Interpersonal skills

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
193
Q

A business unit that centralizes the operations and procedures of all projects within the organization. The PMO can be supportive, controlling, or directive.

A

Project management office (PMO)

194
Q

An event that will likely happen within the project, but when it will happen and to what degree is unknown. These events, such as delays, are usually risk-related.

A

Known unknown

195
Q

A previous project that can be adapted for the current project and forms that are pre-populated with organizational-specific information

A

Template

196
Q

This charts out a decision problem. It identifies all of the elements, variables, decisions, and objectives and also how each factor may influence another.

A

Influence diagrams

197
Q

A decision method where only one individual makes the decision for the group.

A

Autocratic

198
Q

Costs that are representative of more than one project (for example, utilities for the performing organization, access to a training room, project management software license, and so on).

A

Indirect costs

199
Q

A product, service, or result created by a project. Projects can have multiple.

A

Deliverable

200
Q

Evaluates the monies returned on a project for each period the project lasts.

A

Net present value

201
Q

This is the work scheduled and the budget authorized to accomplish that work. It is the percentage of the BAC that reflects where the project should be at this point in time.

A

Planned value (PV)

202
Q

A risk response that attempts to enhance the conditions to ensure that a positive risk event will likely happen.

A

Enhancing

203
Q

This documents a strategy for managing the engagement of project stakeholders. THis establishes stakeholder engagement and defines how the project manager can increase and improve stakeholder engagement

A

Stakeholder engagement plan

204
Q

A schedule compression method that changes the relationship of activities. With this, activities that would normally be done in sequence are allowed to be done in parallel or with some overlap. This can be accomplished by changing the relation of activities from FS to SS or even FF or by adding lead time to downstream activities. However, this does add risk to the project.

A

Fast tracking

205
Q

This subsidiary plan defines how changes will be allowed and managed within the project.

A

Change management plan

206
Q

N(N – 1)/2, where N represents the number of identified stakeholders. This formula reveals the total number of communication channels within a project.

A

Communication channels formula

207
Q

This final process group of the project management life cycle is responsible for closing the project phase or project. This is where project documentation is archived and project contracts are also closed.

A

Closure processes

208
Q

This includes the labeling of the components, how changes are made to the product, and the accountability of the changes.

A

Configuration identification

209
Q

A project initiation activity to identify, document, and classify the project stakeholders as early as possible in the project.

A

Stakeholder identification

210
Q

The project manager has been assigned the role of project manager by senior management and is in charge of the project.

A

Formal power

211
Q

These are costs attributed to the cost of doing business. Examples include utilities, office space, and other overhead costs.

A

Indirect costs

212
Q

These are used by organizations to rate prior experience with each vendor that they have worked with in the past. This can track performance, quality ratings, delivery, and even contract compliance.

A

Seller rating systems

213
Q

A risk response that takes advantage of the positive risks within a project.

A

Exploit

214
Q

The latest a project activity can begin. Used in the backward pass procedure to discover the critical path and the project float.

A

Late Start

215
Q

4.1 Develop Project Charter - Outputs

A

Project CharterAssumption Log

216
Q

This is the total time an activity can be delayed without delaying project completion.

A

Total float

217
Q

A quality control tool that tracks the relationship between two variables over time. The two variables are considered related the closer they track against a diagonal line.

A

Scatter diagram

218
Q

The leader takes a “hands-off” approach to the project. This means the project team makes decisions, takes initiative in the actions, and creates goals. While this approach can provide autonomy, it can make the leader appear absent when it comes to project decisions.

A

laissez-faire leadership

219
Q

The process of first determining which quality standards are relevant to your project and then finding out the best methods of adhering to those quality standards.

A

Quality planning

220
Q

This approach attempts to numerically assess the probability and impact of the identified risks. It also creates an overall risk score for the project. This method is more in-depth than qualitative risk analysis and relies on several different tools to accomplish its goal.

A

Quantitative risk analysis

221
Q

A regularly scheduled meeting to discuss the status of the project and its progress toward completing the project scope statement.

A

Status review meeting

222
Q

This is the total time a single activity can be delayed without affecting the early start of its immediately following successor activities.

A

Free float

223
Q

Controls how the project will acquire goods and services.

A

Procurement management plan

224
Q

These are associated with new, unproven, or complex technologies being used on the project. Changes to the technology during the project implementation can also be a risk. These are the levels set for expectations of impractical quality and performance.

A

Technical, quality, or performance risks

225
Q

Communication requires a sender and a receiver. Within this model may be multiple avenues to complete the flow of communication, but barriers to effective communication may be present as well.

A

sender-receiver models

226
Q

The role of leading the project team and managing the project resources to effectively achieve the objectives of the project.

A

project manager

227
Q

This is the aggregated costs of all of the work packages within the work breakdown structure (WBS).

A

Cost baseline

228
Q

This chart shows the correlation between project team members and the work they’ve been assigned to complete.

A

Responsibility assignment matrix (RAM)

229
Q

A component of a control chart that illustrates the results of seven measurements on one side of the mean, which is considered “out of control” in the project.

A

Rule of Seven

230
Q

A simple approach to ensure that work is completed according to the quality policy.

A

Checklist

231
Q

A scope definition process of finding alternative solutions for the project customer while considering the customer’s satisfaction, the cost of the solution, and how the customer may use the product in operations.

A

Alternatives generation

232
Q

These dependencies are the preferred order of activities. Project managers should use these relationships at their discretion and should document the logic behind the decision. These allow activities to happen in a preferred order because of best practices, conditions unique to the project work, or external events. Also known as preferential or soft logic.

A

Discretionary dependencies

233
Q

A stakeholder who does not want the project to exist and is opposed to the project.

A

Negative stakeholder

234
Q

The project manager can reward the project team.

A

reward power

235
Q

Risks that have an uncertain, unclear nature, such as new laws or regulations, the marketplace conditions, and other risks that are nearly impossible to predict.

A

Ambiguity risks

236
Q

This is a form of unilateral contract that the buyer provides to the vendor showing that the purchase has been approved by the buyer’s organization.

A

Purchase order (PO)

237
Q

A cost-estimating approach that uses a database, typically software-driven, to create the cost estimate for a project.

A

Commercial database

238
Q

A person who is serving in the capacity of a project manager or contributing to the management of a project, portfolio of projects, or program. For example, a program manager is considered to be a project practitioner under this definition.

A

Practitioner

239
Q

The formal verification of the contract completeness by the vendor and the performing organization.

A

Contract closure

240
Q

A process to study the trade-offs between costs and the benefits realized from those costs.

A

Cost-benefit analysis

241
Q

The pitch, tone, and inflections in the sender’s voice affecting the message being sent.

A

Paralingual

242
Q

The project manager can punish the project team.

A

punitive or coercive power

243
Q

A contract that requires the buyer to pay for the costs of the goods and services procured plus a percentage of the costs. The buyer assumes all of the risks for cost overruns.

A

Cost plus percentage of costs

244
Q

The cost aggregation achieved by assigning specific dollar amounts for each of the scheduled activities or, more likely, for each of the work packages in the WBS. Cost budgeting applies the cost estimates over time.

A

Cost budgeting

245
Q

The identification of more than one solution. Consider roles, materials, tools, and approaches to the project work.

A

Alternative analysis

246
Q

As the name implies, these are dependencies outside of the project’s control. Examples include the delivery of equipment from a vendor, the deliverable of another project, or the decision of a committee, lawsuit, or expected new law.

A

External dependencies

247
Q

Undocumented, unapproved changes to the project scope.

A

Scope creep

248
Q

A subsidiary plan in the project management plan. It defines how the project schedule will be created, estimated, controlled, and managed.

A

Schedule management plan

249
Q

An audit to test the validity of the established risk responses.

A

Risk response audit

250
Q

A contract that pays the vendor all costs for the project, but also includes a buyer-determined award fee for the project work.

A

Cost plus award fee contract

251
Q

A diagram illustrating how components within a system are related. These show the relation between components, as well as help the project team determine where quality issues may be present and, once done, plan accordingly.

A

Flowchart

252
Q

When stakeholders create a large number of ideas, you can use an this to cluster similar ideas together for further analysis.

A

Affinity diagrams

253
Q

An ordinal scale that uses red, amber, and green (RAG) to capture the probability, impact, and risk score.

A

RAG rating

254
Q

A simulation technique that got its name from the casinos of Monte Carlo, Monaco. The simulation is completed using a computer software program that can simulate a project, using values for all possible variables, to predict the most likely model.

A

Monte Carlo technique

255
Q

All opinions are formed by one component. A great engineer doesn’t always make a great projectmanager.

A

Halo Effect

256
Q

An activity relationship that requires an activity to start so that its successor can finish. This is the most unusual of all the activity relationship types.

A

Start-to-finish

257
Q

A prompt list used for risk identification. Examines risks in the Political, Economic, Social, Technological, Legal, and Environmental domains.

A

PESTLE

258
Q

Facial expressions, hand gestures, and body language are ______ cues that contribute to a message. Approximately 55 percent of communication is this.

A

Nonverbal

259
Q

These include the application of accounting, procurement, sales and marketing, contracting, manufacturing, logistics, strategic planning, human resource management, standards and regulations, and information technology.

A

General management skills

260
Q

Anything that the project management team believes to be true but hasn’t proven to be true. For example, the project management team may assume that all of the project team can be reached via cell phone, but parts of the world, as of this writing, don’t have a cell signal.

A

Communication assumptions

261
Q

A time-lapse exposure of when the project monies are to be spent in relation to cumulative values of the work completed in the project.

A

Cost baseline

262
Q

This is a combination of three project documents: the project scope statement, the work breakdown structure, and the WBS dictionary. The creation of the project deliverable will be measured against the scope baseline to show any variances from what was expected and what the project team has created.

A

Scope baseline

263
Q

This rough estimate is used during the initiating processes and in top-down estimates. The range of variance for the estimate can be from –25 percent to +75 percent.

A

Rough order of magnitude

264
Q

A forecasting formula that predicts how much of a variance the project will likely have based on current conditions within the project. The formula is BAC – EAC.

A

Variance at completion (VAC)

265
Q

Based on the audience and the message being sent, the media should be in alignment with the message.

A

media selection

266
Q

A percentage of the project duration to combat Parkinson’s Law. When project activities become late, their lateness is subtracted from this

A

Management Reserve

267
Q

A document the seller provides to the buyer. This includes more than just a fee for the proposed work. It also includes information on the vendor’s skills, the vendor’s reputation, and ideas on how the vendor can complete the contracted work for the buyer.

A

Proposal

268
Q

A representation of a project network diagram that is often used for outsourced portions of a project, repetitive work within a project, or a subproject. Also called a subnet.

A

Fragnet

269
Q

A system that examines any changes associated with scope changes, the cost of materials, and the cost of any other resources, and the associated impact on the overall project cost.

A

Cost change control system

270
Q

The phases that make up the project. Unique to the type of work being performed and are not universal to all projects.

A

Project life cycle

271
Q

The tone, structure, and formality of the message being sent should be in alignment with the audience and the content of the message.

A

style

272
Q

An activity relationship type that requires the current activity to be finished before its successor can finish.

A

Finish-to-finish

273
Q

This aims to find out why a risk event may be occurring, the causal factors for the risk events, and then, eventually, how the events can be mitigated or eliminated.

A

Root cause identification

274
Q

A central office that oversees all projects within an organization or within a functional department. Supports the project manager through software, training, templates, policies, communication, dispute resolution, and other services.

A

Project management office (PMO)

275
Q

The individuals or entities that are responsible for monitoring and responding to an identified risk within the project.

A

Risk owners

276
Q

A representation of a project network diagram that is often used for outsourced portions of projects, repetitive work within a project, or a subproject. Also called a fragnet.

A

Subnet

277
Q

Negative time that allows two or more activities to overlap where ordinarily these activities would be sequential

A

Lead Time

278
Q

Project Integration Management - Monitoring and Controlling

A

Monitor and Control Project WorkPerform Integrated Change Control

279
Q

An approach that relies on statistical scenarios to determine what variables within a project will result in the best outcome.

A

Design of experiments

280
Q

This is the total time the project can be delayed without passing the customer-expected completion date.

A

Project float

281
Q

A project management subsidiary plan that defines the stakeholders who need specific information, the person who will supply the information, the schedule for the information to be supplied, and the approved modality to provide the information.

A

Communications management plan

282
Q

The final variance, which is discovered only at the project’s completion. The formula is BAC – AC.

A

Project variance

283
Q

All the business of the project communications is also part of the organizational process assets. This includes e-mails, memos, letters, and faxes.

A

Project records

284
Q

This estimate type is one of the most accurate. It’s used late in the planning processes and is associated with bottom-up estimating. You need the WBS in order to create the definitive estimate. The range of variance for the estimate can be from –5 percent to +10 percent.

A

Definitive estimate

285
Q

This attribute defines what talents, skills, and capabilities are needed to complete the project work.

A

Competency

286
Q

This type of communication happens when the sender pushes the same message to multiple people. Good examples of this are broadcast text messages, faxes, press releases, and group e-mails.

A

Push communications

287
Q

The project manager works to keep the project stakeholders interested, involved, and supportive of the project. Through communication, management skills, and interpersonal skills, the project manager can work to keep the project stakeholders engaged and interested in the project

A

Stakeholder engagement

288
Q

This list details the project milestones and their attributes. It is used for several areas of project planning, but also helps determine how quickly the project may be achieving its objectives.

A

Milestone list

289
Q

This approach pulls the information from a central repository, like a database of information. These are good for large groups of stakeholders who want to access project information at their discretion. Consider a project web site where stakeholders can periodically drop by for a quick update on the project status.

A

Pull communication

290
Q

From seller to buyer. Price is the determining factor in the decision-making process.

A

Bid

291
Q

A project selection method to determine the likelihood of success. These models include linear programming, nonlinear programming, dynamic programming, integer programming, and multiobjective programming.

A

Mathematical model

292
Q

Anyone, whether certified as a project manager or not, who has joined the Project Management Institute.

A

PMI member

293
Q

Project Integration Management - Executing

A

Direct and Manage Project WorkManage Project Knowledge

294
Q

Feedback loops and barriers to communications

A

Sender–receiver models

295
Q

The difference between what was expected and what was experienced.

A

Variance

296
Q

A prepopulated WBS for repetitive projects. Previous projects’ WBSs are often used as templates for current similar projects.

A

WBS template

297
Q

A prompt list used in risk identification to examine the Technical, Environmental, Commercial, Operational, and Political factors of the project.

A

TECOP

298
Q

The project manager has the authority to reward the project team

A

Reward

299
Q

This system communicates the process for controlling changes to the project deliverables. This system works with the configuration management system and seeks to control and document proposals to change the project’s product.

A

Change control system (CCS)

300
Q

An organization that assigns a project team to one project for the duration of the project life cycle. The project manager has high-to-almost-complete project power.

A

Project-oriented structure

301
Q

The project customer may have specific dates when phases of the project should be completed. These milestones are often treated as project constraints.

A

Schedule milestones

302
Q

This approach “qualifies” the risks that have been identified in the project. Specifically, this examines and prioritizes risks based on their probability of occurring and their impact on the project should they occur.

A

Qualitative risk analysis

303
Q

Monies that have already been invested in a project.

A

Sunk costs

304
Q

A contract that requires the buyer to pay for the cost of the goods and services procured plus a fixed fee for the contracted work. The buyer assumes the risk of a cost overrun.

A

Cost plus fixed fee contract

305
Q

This approach encourages participants to generate as many ideas as possible about the project requirements. No idea is judged or dismissed during this session.

A

Brainstorming

306
Q

This is a hierarchical breakdown of the project resources by category and resource type. For example, you could have a category of equipment, a category of human resources, and a category of materials. Within each category, you could identify the types of equipment your project will use, the types of human resources, and the types of materials.

A

Resource breakdown structure (RBS)

307
Q

The PMI publication that defines widely accepted project management practices. The CAPM and the PMP exam are based on this book.

A

A Guide to the Project Management Body of Knowledge (PMBOK Guide)

308
Q

A collection of related projects working in unison toward a common deliverable.

A

Program

309
Q

An estimate to predict how long it will take a project to pay back an organization for the project’s investment of capital.

A

Payback period

310
Q

From buyer to seller. Requests the seller to provide a price for the procured product or service.

A

Invitation for Bid (IFB)

311
Q

A logbook of the issues the project team has identified and dates as to when the issues must be resolved by. This may also include team members or stakeholders who are responsible for finding a solution to the identified issues.

A

Issue log

312
Q

An update to the work breakdown structure.

A

Refinement

313
Q

A quantifiable return on investment. The return can be tangible, such as equipment, money, or market share. The return can also be intangible, such as brand recognition, trademarks, and reputation.

A

Business value

314
Q

Describes the rules, policies, and procedures that people within an organization abide by. Addresses the organization, but also address portfolios, programs, and projects. Regarding portfolios, programs, and projects, this addresses alignment with organizational vision, risk management, performance factors, and communication.

A

Governance framework

315
Q

An uncertain event or condition that can have a positive or negative impact on the project.

A

Risk

316
Q

The most accurate time-and-cost estimating approach a project manager can use. This estimating approach starts at “the bottom” of the project and considers every activity, its predecessor and successor activities, and the exact amount of resources needed to complete each activity.

A

Bottom-up estimating

317
Q

This is a software program to store and analyze project data for reporting. A common _______ will take project data, allow the project manager to pass the data through earned value management, for example, and then create forecasting reports about the project costs and schedule.

A

Reporting system

318
Q

A system to quickly and effectively store, archive, and access project information.

A

Information retrieval system

319
Q

An earned value management formula that predicts how much funding the project will require to be completed. Three variations of this formula are based on conditions the project may be experiencing.

A

Estimate to complete (ETC)

320
Q

A system to record the actual time to complete project activities.

A

Time reporting system

321
Q

The project manager’s authority comes both from experience with the technology the project focuses on and from expertise in managing projects

A

Expert power

322
Q

Costs that change based on the conditions applied in the project (the number of meeting participants, the supply of and demand for materials, and so on).

A

Variable costs

323
Q

The cost associated with not satisfying quality expectations. This is also known as the cost of poor quality.

A

Cost of nonconformance to quality

324
Q

Project team members go about getting the project work, begin to rely on one another, and generally complete their project assignments.

A

Norming

325
Q

The person who is sending the message.

A

Sender

326
Q

Organizational knowledge repositories are the databases, files, and historical information that you can use to help better plan and manage your projects. This is an organizational process asset that is created internally to your organization through the ongoing work of operations and other projects.

A

Organizational Knowledge Repositories

327
Q

A type of risk based on the variations that may occur in the project, such as production, number of quality errors, or even the weather.

A

Variability risks

328
Q

The consideration of the local and international laws, languages, communication challenges, time zone differences, and other non-collocated issues that affect a project’s ability to progress.

A

International and political environment

329
Q

The agreed-upon approach to the management of the project risk processes.

A

Risk management planning

330
Q

Stakeholders—such as management, the project manager, program manager, or customers—that have the authority to make decisions in the project

A

Key stakeholder

331
Q

This system defines how stakeholders are allowed to submit change requests, the conditions for approving a change request, and how approved change requests are validated in the project scope. It also documents the characteristics and functions of the project’s products and any changes to a product’s characteristics.

A

Configuration management system

332
Q

A contract type that requires the buyer to pay a cost for the procured work, plus an incentive fee, or a bonus, for the work if terms and conditions are met.

A

Cost plus incentive fee

333
Q

A scope definition technique that breaks down a product into a hierarchical structure, much like a WBS breaks down a project scope.

A

Product breakdown

334
Q

The project manager aims to gain favor with the project team and stakeholders through flattery.

A

ingratiating power

335
Q

An activity relationship type that requires the current activity to start before its successor can start.

A

Start-to-start

336
Q

The project team meets and learns about their roles and responsibilities on the project. Little interaction among the project team happens in this stage as the team is learning about the project and project manager.

A

Forming

337
Q

This denotes what a person is specifically responsible for in a project. These are usually tied to job titles, such as network engineer, mechanical engineer, and electrician.

A

Role

338
Q

A planning heuristic for creating the WBS. This rule states that the work package in a WBS must take no more than 80 hours of labor to create and no fewer than 8 hours of labor to create.

A

8/80 Rule

339
Q

System or process flowcharts show the relationship between components and how the overall process works. These are useful for identifying risks between system components.

A

Flowcharts

340
Q

Traditional chart that depicts how the organization is broken down by department and disciplines. This chart is sometimes called the organizational breakdown structure (OBS) and is arranged by departments, units, or teams.

A

Organization chart

341
Q

______ believed that we have five needs; we’re on a quest to satisfy these needs. The needs are,from the bottom up:1. Physiological. We need air, food, clothing, and shelter.2. Safety. We need safety and security.3. Social. We need friends, approval, and love.4. Esteem. We need respect, appreciation, and approval.5. Self-actualization. We need personal growth, knowledge, and fulfillment

A

Maslow’s Hierarchy of Needs

342
Q

A process in which the project management team determines the cost-effectiveness, benefits, and feasibility of making a product or buying it from a vendor.

A

Make-or-buy decision

343
Q

The activities don’t necessarily have to happen in a specific order. For example, you could install the light fixtures first, then the carpet, and then paint the room. The project manager could use soft logic to change the order of the activities if so desired.

A

Soft logic

344
Q

4.1 Develop Project Charter - Inputs

A

Business DocumentsAgreementsEnterprise Environmental FactorsOrganizations Process Assets

345
Q

An activity relationship type that requires the current activity to be finished before its successor can start.

A

Finish-to-start

346
Q

All changes that enter into a project are recorded in this. The characteristics of the change, such as the time, cost, risk, and scope details, are also recorded.

A

Change log

347
Q

The operational definitions that specify the measurements within a project and the expected targets for quality and performance

A

Quality metrics

348
Q

Describes a loosely organized business or organization. There likely aren’t big formal departments and people work alongside one another regardless of roles and titles. The project manager likely has little control over the project resources and may not be called a project manager.

A

Organic or simple

349
Q

An approach that assumes the cost per unit decreases the more units workers complete, because workers learn as they complete the required work.

A

Learning curve

350
Q

The formatted communication of work performance information. Communicate what’s happening in the project through status reports, memos, dashboards, or other modalities.

A

Work performance reports

351
Q

From buyer to seller. Requests the seller to provide a price for the procured product or service.

A

Request for Quote (RFQ)

352
Q

A predetermined range of acceptable variances, such as +/–10 percent off schedule. Should the variance exceed the threshold, then project control processes and corrected actions will be enacted.

A

Control threshold

353
Q

The receiver signals that the message has been received. This shows receipt of the message, but not necessarily agreement with the message

A

Acknowledgment

354
Q

These dependencies are the natural order of activities. For example, you can’t begin building your house until your foundation is in place. These relationships are called hard logic

A

Mandatory dependencies

355
Q

Project Integration Management - Planning

A

Develop Project Management Plan

356
Q

Measures the project based on its schedule performance. The formula is EV/PV.

A

Schedule performance index (SPI)

357
Q

Describe the culture and the styles of an organization. Work ethics, hours, view of authority, and shared values, can affect how the project is managed.

A

Cultural norms

358
Q

A documentation of each stakeholder’s contact information, position, concerns, interests, and attitude toward the project. The project manager updates this as new stakeholders are identified and when stakeholders leave the project.

A

Stakeholder register

359
Q

Assurance provided to management and the project team.

A

Internal QA

360
Q

Part of stakeholder analysis classification. A ______ stakeholder is aware of your project, but they do support the changes your project will create

A

Resistant stakeholder status

361
Q

Project management team members may have authority over other project team members, may have the ability to make decisions, and perhaps even sign approvals for project work and purchases

A

Authority power

362
Q

This plan defines how the project team will implement and fulfill the quality policy of the performing organization.

A

Quality management plan

363
Q

Treating others with conduct that may result in harm, fear, humiliation, manipulation, or exploitation. For example, berating a project team member because they’ve taken longer than expected to complete a project assignment may be considered humiliation.

A

Abusive manner

364
Q

This is the study of the functions within a system, project, or, what’s more likely in the project scope statement, the product the project will be creating. This studies the goals of the product, how the product will be used, and the expectations the customer has of the product once it leaves the project and moves into operations. This may also consider the cost of the product in operations, which is known as life-cycle costing.

A

Functional analysis

365
Q

The abbreviation for the International Organization for Standardization. This is Greek for “equal,” while “International Organization for Standardization” in a different language would be abbreviated differently. The organization elected to use “ISO” for all languages.

A

ISO

366
Q

A quick and cost-effective risk identification approach.

A

Checklists

367
Q

These are disagreements between the buyer and the seller, usually centering on a change, who did the change, and even whether a change has occurred. These are also called disputes and appeals, and are monitored and controlled through the project in accordance with the contract terms.

A

Claims

368
Q

The smallest item in the WBS.

A

Work package

369
Q

The project manager works with the project team and subject matter experts to create a strategy to manage the project stakeholders.

A

Stakeholder engagement planning

370
Q

The observer records information about the work being completed without interrupting the process; sometimes called the invisible observer.

A

Passive observation

371
Q

A software package that allows the project management team to present the project’s health through graphics, spreadsheets, and text. (Think of Microsoft Project.)

A

Information presentation tools

372
Q

This plan defines who will get what information, how they will receive it, and in what modality the communication will take place.

A

Communications management plan

373
Q

A prompt list used in risk identification that examines the Volatility, Uncertainty, Complexity, and Ambiguity of risk factors within the project

A

VUCA

374
Q

This is documentation of what did and did not work in the project implementation. This documentation is created throughout the project by the entire project team. When these sessions are completed, they’re available to be used and applied by the entire organization. They are now part of the organizational process assets.

A

Lessons learned

375
Q

The process of gathering project details. This process uses deductive reasoning, logic, and a series of information-gathering techniques to identify details about a project, product, or solution.

A

Progressive elaboration

376
Q

A benefit comparison model to determine the present value of a future amount of money. The formula to calculate present value is PV = FV ÷ (1 + I)n, where FV is future value, I is the given interest rate, and n is the number of periods.

A

Present value

377
Q

A process to consider and control the impact of a proposed change on the project’s knowledge areas.

A

Integrated change control

378
Q

This plan defines staff acquisition, the timetable for staff acquisition, the staff release plan, training needs for the project team, any organizational compliance issues, rewards and recognition, and safety concerns for the project team doing the project work.

A

Resource management plan

379
Q

This takes out the personal preferences of the decision maker in the organization to ensure that the best seller is awarded the contract. These are assigned to the values of the proposals, and each proposal is scored

A

Weighting system

380
Q

This plan details how the project costs will be planned for, estimated, budgeted, and then monitored and controlled.

A

Cost management plan

381
Q

These forecasting formulas predict the likely completed costs of the project based on current scenarios within the project.

A

Estimate at completion (EAC)

382
Q

The project team struggles for project positions, leadership, and project direction. The project team can become hostile toward the project leader, challenge ideas, and try to establish and claim positions about the project work. The amount of debate and fury can vary depending on if the project team is willing to work together, the nature of the project, and the control of the project manager

A

Storming

383
Q

Defines how a project affects people and how those people may affect the project. Includes the economic, educational, ethical, religious, demographic, and ethnic composition of the people affected by the project.

A

Cultural and social environment

384
Q

A triangle with the characteristics of time, cost, and scope. Time, cost, and scope each constitute one side of the triangle; if any side of the Iron Triangle is not in balance with the other sides, the project will suffer. The Iron Triangle of Project Management is also known as the Triple Constraints of Project Management, as all projects are constrained by time, cost, and scope.

A

Iron Triangle of Project Management

385
Q

The calculated score based on each risk’s probability and impact. The approach can be used in both qualitative and quantitative risk analysis.

A

Risk score

386
Q

When the project management team decides to use transference to respond to a risk, this is created between the buyer and the seller.

A

Risk-related contractual agreements

387
Q

An estimating approach that starts from zero, accounts for each component of the WBS, and arrives at a sum for the project. It is completed with the project team and can be one of the most time-consuming and most reliable methods to predict project costs.

A

Bottom-up estimating

388
Q

The message receiver restates what’s been said to fully understand and confirm the message and it provides an opportunity for the sender to clarify the message if needed.

A

active listening

389
Q

Diagrams that show the relationship between variables within a process and how those relationships may contribute to inadequate quality. The diagrams can help organize both the process and team opinions, as well as generate discussion on finding a solution to ensure quality.

A

Cause-and-effect diagrams

390
Q

A group-decision method where the largest part of the group makes the decision when it’s less than 50 percent of the total. (Consider three or four factions within the stakeholders.)

A

Plurality

391
Q

A deliverables-oriented breakdown of the project scope

A

Work breakdown structure (WBS)

392
Q

There are hygiene agents and motivating agents. Hygiene agents are expectations for employment:paycheck, insurance, safe working environment. Motivating agents are motivators for employeessuch as bonuses, career advancement, opportunity to grow. Hygiene agents will not motivate, buttheir absence will de-motivate.

A

Herzberg’s Theory of Motivation

393
Q

Defines the product or service that will come about as a result of completing the project. It defines the features and functions that characterize the product.

A

Product Scope

394
Q

The physical structure and surroundings that affect a project’s work.

A

Physical environment

395
Q

Uses a network structure to communicate and interact with other groups and departments. A point of contact exists for each department and these department point of contact receive and send all messages for the department.

A

Virtual organization

396
Q

These are charts and diagrams that help the project manager determine the influence of stakeholders in relation to their interest in the project. Common __________ include the power/interest grid, the power/influence grid, the influence/impact grid, and the salience model.

A

Stakeholder classification models

397
Q

Only one vendor can provide what your project needs to purchase. Examples include a specific consultant, specialized service, or unique type of material.

A

Sole source

398
Q

A formula to forecast the likelihood of a project to achieve its goals based on what’s happening in the project right now. There are two different flavors for the TCPI, depending on what you want to accomplish. If you want to see if your project can meet the budget at completion, you’ll use this formula: TCPI = (BAC – EV)/(BAC – AC). If you want to see if your project can meet the newly created estimate at completion, you’ll use this version of the formula: TCPI = (BAC – EV)/(EAC – AC).

A

To-Complete Performance Index

399
Q

Anything that interferes with or disrupts a message.

A

Noise

400
Q

Utilizes positional power to maintain, administrate, control, and focus on getting things done without challenging the status quo of the project and organization.

A

management

401
Q

Costs that remain constant throughout the life of the project (the cost of a piece of rented equipment for the project, the cost of a consultant brought on to the project, and so on).

A

Fixed costs

402
Q

This approach pushes the information from the sender to the receiver without any real acknowledgment that the information was really received or understood. Consider letters, faxes, voicemail messages, e-mails, and other communications modalities that the sender packages and sends to receivers through some intermediary network

A

Push communication

403
Q

The project manager has power because of certain situations in the organization

A

situational power

404
Q

This defines the procedures for how the contract may be changed. The process for changing the contract includes the forms; documented communications; tracking; conditions within the project, business, or marketplace that justify the needed change; dispute resolution procedures; and the procedures for getting the changes approved within the performing organization.

A

Contract change control system

405
Q

A network diagram that shows activities in nodes and the relationship between each activity. Predecessors come before the current activity, and successors come after the current activity

A

Precedence diagramming method

406
Q

Also known as the Iron Triangle. This theory posits that time, cost, and scope are three constraints that every project has.

A

Triple Constraints of Project Management

407
Q

These are costs incurred by the project in order for the project to exist. Examples include the equipment needed to complete the project work, salaries of the project team, and other expenses tied directly to the project’s existence.

A

Direct costs

408
Q

A group decision method where more than 50 percent of the group must be in agreement.

A

Majority

409
Q

These risks may have negative or positive outcomes. Examples include using a less experienced worker to complete a task, allowing phases or activities to overlap, or forgoing the expense of formal training for on-the-job education.

A

Business risks

410
Q

This is the physical work completed to date and the authorized budget for that work. It is the percentage of the BAC that represents the actual work completed in the project.

A

Earned value (EV)

411
Q

Calendars that identify when the project work will occur.

A

Project calendars

412
Q

The smallest item in the work breakdown structure.

A

Work package

413
Q

These seven tools are used in quality planning and in quality control: cause-and-effect diagrams, flowcharts, check sheets, Pareto diagrams, histograms, control charts, and scatter diagrams.

A

Seven basic quality tools

414
Q

Project Integration Management - Initiating

A

Develop Project Charter

415
Q

A quantitative risk analysis tool that examines each risk to determine which one has the largest impact on the project’s success.

A

Sensitivity analysis

416
Q

The project manager has the authority to discipline the project team members. This is also known as penalty power.

A

Coercive power

417
Q

A project simulation approach named after the world-famous gambling district in Monaco. This predicts how scenarios may work out, given any number of variables. The process doesn’t actually churn out a specific answer, but a range of possible answers. When this analysis is applied to a schedule, it can examine, for example, the optimistic completion date, the pessimistic completion date, and the most likely completion date for each activity in the project and then predict a mean for the project schedule.

A

Monte Carlo analysis

418
Q

A stakeholder who sees the benefits of the project and is in favor of the change the project is to bring about.

A

Positive stakeholder

419
Q

Defines three areas of PDUs for PMI certified professionals to maintain their certification. Includes technical project management, leadership, and strategic and business management.

A

PMI Talent Triangle

420
Q

A risk response effort to reduce the probability and/or impact of an identified risk in the project.

A

Mitigation

421
Q

Project Integration Management - Closing

A

Close Project or Phase

422
Q

Knowledge that can be quickly and easily expressed through conversations, documentation, figures, or numbers, is easily communicated.

A

Explicit knowledge

423
Q

This subsidiary plan defines how changes to the project requirements will be permitted, how requirements will be tracked, and how changes to the requirements will be approved.

A

Requirements management plan

424
Q

A theory that states: “Work expands so as to fill the time available for its completion.” It is considered with time estimating, because bloated or padded activity estimates will fill the amount of time allotted to the activity.

A

Parkinson’s Law

425
Q

These models use a common set of values for all of the projects up for selection. For example, values can be profitability, complexity, customer demand, and so on.

A

Scoring models

426
Q

A group decision method where everyone must be in agreement

A

Unanimity

427
Q

This is a factor in the planning process that is held to be true but not proven to be true.

A

Project Assumptions

428
Q

A quality control tool that shows the results of inspection in the order in which they’ve occurred. The goal of a thisis first to demonstrate the results of a process over time and then to use trend analysis to predict when certain trends may reemerge

A

Run chart

429
Q

A WBS entry located below a control account and above the work packages. This signifies that there is more planning that needs to be completed for this specific deliverable.

A

Planning package

430
Q

The project manager can restrict choices to get the project team to perform and do the project work.

A

pressure-based power

431
Q

A project manager’s responsibility to be loyal to another person, organization, or vendor. For example, a project manager has a duty of loyalty to promote the best interests of an employer rather than the best interests of a vendor

A

Duty of loyalty

432
Q

A scope definition process where the project management team interviews the stakeholders and categorizes, prioritizes, and documents what the project customer wants and needs. The analysis is to determine, quantify, and prioritize the interests of the stakeholders. This demands quantification of stakeholder objectives; goals such as “good,” “satisfaction,” and “speedy” aren’t quantifiable.

A

Stakeholder analysis

433
Q

The imminent work is planned in detail, while the work in the future is planned at a high level. This is a form of progressive elaboration.

A

Rolling wave planning

434
Q

The earliest a project activity can finish. Used in the forward pass procedure to discover the critical path and the project float.

A

Early finish

435
Q

These risks have only a negative outcome. Examples include loss of life or limb, fire, theft, natural disasters, and the like.

A

Pure risks

436
Q

The receiver is involved in the listening experience by paying attention to visual cues from the speaker and paralingual characteristics, and by asking relevant questions.

A

Effective listening

437
Q

Begins with problem definition. Problem definition is the ability to discern between the cause and effect of the problem. Root-cause analysis looks beyond the immediate symptoms to the cause of the symptoms—which then affords opportunities for solutions.

A

active problem solving

438
Q

These are the measurable goals that determine a project’s acceptability to the project customer and the overall success of the project. These often include the cost, schedule, technical requirements, and quality demands.

A

Project objectives

439
Q

Anything that limits the project management team’s options. When it comes to this, geographical locales, incompatible communications software, and even limited communications technology can constrain the project team.

A

Communication constraints

440
Q

Contracts and agreements with unions or other employee groups may serve as constraints on the project.

A

Collective bargaining agreement constraints

441
Q

This clearly states what is included with the project and what’s excluded from the project. This helps to eliminate assumptions between the project management team and the project customer.

A

Project boundaries

442
Q

The project manager’s power is because of the position she has as the project manager. This is also known as formal, authoritative, and legitimate power.

A

positional power

443
Q

4.1 Develop Project Charter - Tools and Techniques

A

Expert JudgementData GatheringInterpersonal and Team SkillsMeetings

444
Q

The project management knowledge area that focuses on the management and engagement of the project stakeholders. There are four processes in this knowledge area: identify stakeholders, plan stakeholder management, manage stakeholder engagement, and Monitor Stakeholder Engagement.

A

Stakeholder management

445
Q

From seller to buyer. Price is the determining factor in the decision-making process.

A

Quotation

446
Q

This is an example of a benefits comparison model. It examines the benefit-to-cost ratio.

A

Benefit/cost ratio (BCR) models

447
Q

This allows the vendor to begin working on the project immediately. It is often used as a stopgap solution.

A

Letter contract

448
Q

A data analysis table that shows the strength between variables and relationships within it.

A

Matrix diagram

449
Q

A smaller project managed within a larger, parent project. Often contracted work whose deliverable allows the larger project to progress.

A

Subprojects

450
Q

These risks are outside of the project, but directly affect it—for example, legal issues, labor issues, a shift in project priorities, or weather. “Force majeure” risks call for disaster recovery rather than project management. These are risks caused by earthquakes, tornadoes, floods, civil unrest, and other disasters.

A

External risks

451
Q

A project management subsidiary plan that defines how risks will be identified, analyzed, responded to, and monitored within the project. The plan also defines the iterative risk management process that the project is expected to adhere to.

A

Risk management plan

452
Q

A committee that evaluates the worthiness of a proposed change and either approves or rejects the proposed change.

A

Change control board (CCB)

453
Q

Issues are points of contention where some question of the project’s direction needs to be resolved. All identified issues are documented in the issue log, along with an issue owner and a deadline to resolve the issue. The outcome of the issue is also recorded.

A

Issue log

454
Q

Positive time that moves two or more activities further apart.

A

Lag Time

455
Q

A collection of related processes in project management. There are five process groups and 49 project management processes. The five are Initiating, Planning, Executing, Monitoring and Controlling, and Closing.

A

Process groups

456
Q

The observer interacts with the worker to ask questions and understand each step of the work being completed. In some instances, the observer could serve as an assistant in doing the work.

A

Active observation

457
Q

A requirements collection method used to elicit requirements from stakeholders in a one-on-one conversation.

A

Interviews

458
Q

The systematic process of combing through the project, the project plan, the work breakdown structure, and all supporting documentation to identify as many risks that may affect the project as possible.

A

Risk identification

459
Q

The total cost of the opportunity that is refused to realize an opposing opportunity

A

Opportunity cost

460
Q

The scope verification and completeness auditing of project or phase deliverables to ensure that they are in alignment with the project plan.

A

Configuration verification and auditing

461
Q

The leader emphasizes the goals of the project and rewards and disincentives for the project team. This is sometimes called management by exception as it’s the exception that is reward or punished.

A

transactional leadership

462
Q

An organization where organizational resources are pooled into one project team, but the functional managers have less project power than the project manager.

A

Strong matrix structure

463
Q

The device that decodes a message as it is being received

A

Decoder

464
Q

These diagrams, such as the project network diagram, show the flow of the project work.

A

Activity network diagram

465
Q

Anyone who is affected by the existence of the project or who can affect the project’s existence. These can enter and exit the project as conditions change within the project.

A

Stakeholder

466
Q

Involves aligning, motivating, and inspiring the project team members to do the right thing, build trust, think creatively, and to challenge the status quo.

A

leadership

467
Q

Defines the obligations for the seller, what the seller will provide, and all of the particulars of the contracted work. This is similar to the statement of work.

A

Terms of Reference

468
Q

This project management subsidiary plan controls how the scope will be defined, how the project scope statement will be created, how the WBS will be created, how scope validation will proceed, and how the project scope will be controlled throughout the project.

A

Project scope management plan

469
Q

An activity that ranks stakeholders based on their influence, interests, and expectations of the project. Stakeholders are identified and ranked, and then their needs and expectations are documented and addressed.

A

Stakeholder analysis

470
Q

This is a formal agreement between the buyer and the seller. These can be oral or written—though written is preferred.

A

Contract

471
Q

The project team personally knows the project manager. This can also mean that the project manager refers to the person who assigned him the position.

A

Referent power

472
Q

An organization where organizational resources are pooled into one project team, but the functional managers and the project managers share the project power.

A

Balanced matrix structure

473
Q

A stakeholder who has neither a positive nor negative attitude about the project’s existence.

A

Neutral stakeholder

474
Q

The best modality to use when communicating that is relevant to the information being communicated.

A

Choice of media

475
Q

Once the project is done, either the team moves onto other assignments as a unit, or the project team is disbanded and individual team members go on to other work.

A

Adjourning

476
Q

Knowledge that’s more difficult to express because it’s personal beliefs, values, knowledge gain from experience, and “know-how” when doing a task.

A

tacit knowledge

477
Q

A risk response that transfers the ownership of the risk to another party. Insurance, licensed contractors, or other project teams are good examples of this. A fee and contractual relationships are typically involved with the transference of a risk.

A

Transference

478
Q

This estimate is also somewhat broad and is used early in the planning processes and also in top-down estimates. The range of variance for the estimate can be from –10 percent to +25 percent.

A

Budget estimate

479
Q

These are committees that ask every conceivable negative question about the proposed project. Their goals are to expose the project’s strengths and weaknesses, and to kill the project if it’s deemed unworthy for the organization to commit to. Also known as project steering committees or project selection committees.

A

Murder boards

480
Q

The most common approach to risk identification; usually completed by a project team with subject matter experts to identify the risks within the project.

A

Brainstorming

481
Q

A quantitatively based duration estimate that uses mathematical formulas to predict how long an activity will take based on the quantities of work to be completed.

A

Parametric estimate