During which time are team members’ commitments to the project strengthened?
A. Controlling
B. Execution
C. Planning
D. Monitoring
Planning
Which of the following is a tailoring consideration for Project Resource Management?
A. Physical location
B. Salary of resources
C. Resource calendar
D. Number of team members
Physical location
Which of the following project resource management process is best defines the process of tracking team member performance, providing feedback, resolving issues, and managing team changes to optimize project performance?
A. Control Resources
B. Acquire Resources
C. Develop Team
D. Manage Team
Manage Team
The major processes of Project Resource Management are:
A. Leadership management, team building, and negotiation
B. Plan resource management estimate activity, resources, acquire resources, develop team, manage team, and control resources
C. Plan Organizational structure, build project team, develop communications plan, and manage team conflicts.
D. Develop project staffing plan, recruit project team, administer personnel actions, and manage labor relations.
Plan resource management estimate activity, resources, acquire resources, develop team, manage team, and control resources
When tailoring processes for Project Resource Management, you should consider all of these EXCEPT:
A. Number of team members
B. Physical location
C. Life cycle approach
D. Diversity
Number of team members
The responsibility assignment matrix (RAM) is:
A. Developed at the activity level and used to closely link project roles and responsibility to project network activities
B. Used for development of the project Budget and network diagrams
C. Used to identify accountabilities and responsibilities in individual performance appraisals of project team members.
D. Illustrates the connections between work packages or activities and project team members. It ensures that there is only one person accountable for each
Illustrates the connections between work packages or activities and project team members. It ensures that there is only one person accountable for each
Which of the following contains information on threats and opportunities that may impact resource planning?
A. Staff release plan
B. Project organization chart
C. Risk register
D. Resource calendar
Risk register
Which is the following definition of a RACI chart?
A. An organizational chart that shows functional relationships between resources
B. A common type of responsibility assignment matrix to define the involvement of stakeholders in project activities
C. A bar chart showing the amount of time that a resource is scheduled to work. Over a series of time periods
D. A calendar that identifies the working days and shifts upon which each specific resource is available
A common type of responsibility assignment matrix to define the involvement of stakeholders in project activities
Which of the following describes why a Responsible, Accountable Consult and Inform (RACI) chart is a useful tool?
A. Shows the sponsor the amount of time that a resource is scheduled to work over a series of time periods
B. Ensures a clear assignment of roles and responsibilities when the team consists of internal and external resources
C. Provides all team members with a hierarchical representation of resource by category and type
D. Identifies the working days and shifts upon which each specific resource is available
Ensures a clear assignment of roles and responsibilities when the team consists of internal and external resources
What type of chart is well suited for displaying detailed descriptions of team member responsibilities?
A. Text-oriented
B. Hierarchical-type
C. Organizational chart
D. Graphic-display
Text-oriented
What is the definition of Plan Resource Management?
A. The process of mapping project resources to deliverables and project budget
B. The process of defining how to estimate, acquire, manage, and use physical and team resources
C. The process of creating a formal document defining resource budgets
D. The process of identifying resources and associated costs.
The process of defining how to estimate, acquire, manage, and use physical and team resources
Which output of Plan Resource management provides guidance on how team resources should be defined, staffed, managed, and eventually released?
A. Resource management plan
B. Resource assignment matrix (RAM)
C. Team Charter
D. Resource Breakdown Structure (RBS)
Resource management plan
Which of the following is an output of the Estimate Activity Resources process?
A. Scope baseline
B. Analogous estimating
C. Project management information system
D. Resource breakdown structure (RBS)
Resource breakdown structure (RBS)
The types and quantities of resources required for each activity in a work package are included in which of the following?
A. Resource package
B. Organizational chart
C. Resource breakdown structure
D. Resource requirements
Resource requirements
Which of the following is an input to the Estimate Activity Resources process?
A. Risk register
B. Basis of estimates
C. Project management information system
D. Bottom-up estimating
Risk register
All of the following are inputs to the Estimate Activity Resources process EXPECT:
A. Resource management plan
B. Resource breakdown structure (RBS)
C. Enterprise environmental factors
D. Activity list
Resource breakdown structure (RBS)