Which of the following best describes the first part of Project Communications Management?
A. Assessing the effectiveness of completed communication activities
B. Delivering the project communications plan to team members
C. Carrying out activities necessary to implement the communication strategy
D. Developing a strategy to ensure communication is effective for stakeholders

A

Developing a strategy to ensure communication is effective for stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which of the following is the process of ensuring the information needs of the project and its stakeholders are met?
A. Plan communications management
B. Monitor communications
C. Manage communications
D. Execute communications

A

Monitor communications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Project Communications Management includes all of the following EXCEPT:
A. Communications activities include internal and external, formal and informal, written and oral.
B. Affected communication creates a bridge between diverse stakeholders whose differences will generally have an impact or influence upon the project execution or outcome.
C. Communication can be directed upward to senior management stakeholders, downward to team members, or horizontally to peers.
D. Resource management is concentrated on allocating realizing the physical resources needed for successful completion of the project and the efficient and effective way.

A

Resource management is concentrated on allocating realizing the physical resources needed for successful completion of the project and the efficient and effective way.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The major processes of Project Communications Management are:
A. Distribute information, Report Changes, Update Project Documents, and Accept Project
B. Plan Communications, Distribute Information, and Schedule Reporting
C. Plan Communications Management, Manage Communications, and Monitor Communications
D. Plan Communications Management, Develop Responses, Report Progress, and Distribute Information

A

Plan Communications Management, Manage Communications, and Monitor Communications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which of the following best describes the process of developing an appropriate approach and planning for project communications activities based on the information needs of each stakeholder or group, available organizational assets, and the needs of the project?
A. Communication requirements analysis
B. Knowledge management
C. Plan Communications Management
D. Manage Communications

A

Plan Communications Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which of the following are dimensions of communication activities?
A. Formal and informal
B. Positive and negative
C. Conceptual and definitive
D. Printed and posted

A

Formal and informal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Communication activities have many potential dimensions that generally include all of the following EXCEPT:
A. Written, oral, and nonverbal
B. Formal and informal
C. Internal and external
D. Conceptual and definitive

A

Conceptual and definitive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which of the following are some of the factors that can affect the choice of communication technology?
A. Ease of use, executive requirements, and project environment
B. Resource budget, executive requirements, and project environment
C. Ease of use, project environment, and urgency of the need of information
D. Urgency of the need for information, resource budget, and ease of use

A

Ease of use, project environment, and urgency of the need of information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The communications management plan usually contains all of the following EXCEPT:
A. Information to be communicated, including language, format, content, and level of detail
B. E-mail archives, correspondence, reports, and documents related to the project from all stakeholders
C. Time frame and frequency for the distribution of required information and receipt of acknowledgement or management, if applicable.
D. Methods or technologies used to convey the information, such as memos, e-mail, and/or press releases.

A

E-mail archives, correspondence, reports, and documents related to the project from all stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which of the following is a technique of the Plan Communications Management process that determines the information needs of the project stakeholders?
A. Communication Requirements Technology
B. Information Management System (IMS)
C. Project Management Information System (PMIS)
D. Communication Requirements Analysis

A

Communication Requirements Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which of the following is an output of the plan communication management process and the component of the project management plan that describes how project communications will be planned and structured, implemented, and monitored for effectiveness?
A. Benefits Management Plan
B. Scope Management Plan
C. Stakeholder Engagement Plan
D. Communications Management Plan

A

Communications Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Which of the following are sources of information typically used to identify and define project communication requirements?
A. Number of deliverables
B. Availability of the project sponsor
C. Budget and schedule for each product deliverable
D. Disciplines, departments, and specialties involved in the project

A

Disciplines, departments, and specialties involved in the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which of the following is an input to the Plan Communications Management process?
A. Project Charter
B. Project Reporting
C. Work Performance Reports
D. Work Performance Data

A

Project Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

As part of the communications model, the sender is responsible for:
A. Presenting the information in the most favorable manner
B. Confirming that the communication is correctly understood
C. Ensuring that the receiver agrees with the message
D. Decoding the medium correctly

A

Confirming that the communication is correctly understood

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Memos and emails are examples of what communication method?
A. Push
B. Interactive
C. Pull
D. Transmit message

A

Push

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Which of the following is a tool or technique used in the Manage Communications process?
A. Stakeholder engagement plan
B. Risk report
C. Project Management Information System
D. Communications Management Plan

A

Project Management Information System

17
Q

Which of the following best describes the system that provides access to information technology software tools, such as scheduling software and work authorization systems?
A. Configuration Management System
B. Internal Communications Systems
C. Internal Management Systems
D. Project Management Information System

A

Project Management Information System

18
Q

Which of the following are communication techniques that can be used for the Manage Communication process?
A. Nonverbal, web conferencing, and social media
B. Feedback, nonverbal, and presentations
C. Social media, feedback, and email
D. Email, fax, and web conferencing

A

Feedback, nonverbal, and presentations

19
Q

Which of the following is a PMIS tool that can be used to execute this process?
A. Networking
B. Social media management
C. Active listening
D. Conflict management

A

Social media management

20
Q

Which of the following describes a comprehensive list of changes submitted during the project and their current status?
A. Change log
B. Activity changes
C. Revision list
D. Change treatment

A

Change log

21
Q

What tools and techniques are used in the Monitor Communications process?
A. Communication technology, expert judgement, and meetings
B. Project management information system, communication technology, and performance reporting
C. Project management information system, expert judgement, and meetings
D. Communication technology, communication methods, and performance reporting

A

Project management information system, expert judgement, and meetings

22
Q

What is a formal proposal to modify a document, deliverable, or baseline?
A. Modification bid
B. Change proposal
C. Revision request
D. Change request

A

Change request

23
Q

Which of the following is an output of the monitor communications process?
A. Project charter updates
B. Project communications
C. Work performance information
D. Enterprise environmental factors updates

A

Work performance information

24
Q

Monitor Communications is the process of:
A. And sharing that information is provided on a need to know basis only to avoid unnecessary confusion and possible conflicts
B. Ensuring that the information needs of the project stakeholders are met throughout the entire project lifecycle
C. Providing all project information to all project stakeholders to enhance full buy in regarding project requirements
D. Securing and guarding any negative information related to project performance throughout the entire project lifecycle to ensure that the project team can continue working on the project with minimal disruption.

A

Ensuring that the information needs of the project stakeholders are met throughout the entire project lifecycle

25
Q

Which of the following is a tool or technique used in the monitor communications process?
A. Interpersonal and team skills
B. Work performance information
C. Change requests
D. Issue log

A

Interpersonal and team skills