Ramdayal - PMP Documents/Process Created Flashcards

1
Q

Document = Activity attributes

Detailed information about each individual activity

A

Process = Define Activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Document = Activity list

List of all the activities on the project

A

Process = Define activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Document = Assumption log

List of all project assumptions and constraints

A

Process = Develop project charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Document = Basis of estimates

Describes how schedule, cost, and resource
estimates were developed. Also includes their
confidence level and ranges

A

Process = Estimate activity duration, estimate costs, estimate activity resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Document = Change log

Lists and describes the status of the change requests
that is being processed or have been processed
through the perform integrated change control
process

A

Process = Perform integrated change control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Document = Cost estimates

Cost of each individual activity

A

Process = Estimate costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Document = Cost forecasts

A prediction of how much the project will cost when
it completes based on the current work

A

Process = Control costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Document = Duration estimates

Amount of time needed to complete each activity on
the project

A

Process = Estimate activity durations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Document = Issue log

List of all issues on the project. Could include
history type, description, priority, status, and
resolution

A

Process = Direct and manage project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Document = Lessons learned register

List of all lessons learned throughout the project

A

Process = Manage project knowledge

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Document = Milestone list

Description of milestones on a project

A

Process = Define activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Document = Physical resource assignments

Assignments of the physical resources to the
activities or work packages

A

Process = Acquire resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Document = Project calendars

A calendar view of what takes place on a day-to-day
basis on the project

A

Process = Develop schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Document = Project communications

Communicate on the project by following the
communications management plan

A

Process = Manage communications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Document = Project schedule

A detailed breakdown of the work that needs to be
done in order to complete the project. Will include a
bar chart, milestone chart, and the project schedule
network diagram

A

Process = Develop schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Document = Project schedule network diagram

A sequencing diagram that shows the relationships
amongst the activities and the sequence they will be
performed. But also show the critical path

A

Process = Sequence activities

17
Q

Document = Project scope statement

A detailed description of the project or phase
deliverables

A

Process = Define scope

18
Q

Document = Project team assignments

Assignment of the project team members to the work
packages or activities

A

Process = Acquire resources

19
Q

Document = Quality control measurements

Results of the activities done in the “control quality”
processes to determine if the quality standards or
policies were met

A

Process = Control quality

20
Q

Document = Quality metrics

An attribute that will be used to measure the project
or to deliverable to verify that it has met the quality
requirements and/or standards

A

Process = Plan quality management

21
Q

Document = Quality report

A report which generally includes information about
quality issues on the project and recommendations
on how to improve the processes on the project

A

Process = Manage quality

22
Q

Document = Requirements documentation

Description of all requirements from project
stakeholders

A

Process = Collect requirements

23
Q

Document = Requirements traceability matrix

A table that traces the origin of the requirements

A

Process = Collect requirements

24
Q

Document = Resource breakdown structure

Categorization and type of the project resources

A

Process = Estimate activity resources

25
Document = Resource calendars Shows the availability of resources on the project both physical and HR
Process = Acquire resources
26
Document = Resource requirements Description of the number and type of resources needed to complete each work package or activity
Process = Estimate activity resources
27
Document = Risk register A list of all positive and negative risks on a project, along with responses
Process = Identify risks
28
Document = Risk report A description of the overall project risks
Process = Identify risks
29
Document = Schedule data The information that is used to create the schedule such as who made it, assumptions, and constraints
Process = Develop schedule
30
Document = Schedule forecasts A prediction of when the project may be completed based on the current progress of the work
Process = Control schedule
31
Document = Stakeholder register A list of all stakeholders, which can include categorization, impact, and communication requirements
Process = Identify stakeholders
32
Document = Team charter Guidelines team should follow on a project. Includes values, decision-making process, acceptable behavior, code of conduct, and etiquette
Process = Plan resource management
33
Document = Test and evaluation documents Used to help evaluate the project deliverables when completed
Process = Manage quality