Ramdayal - PMP Documents/Process Created Flashcards
Document = Activity attributes
Detailed information about each individual activity
Process = Define Activities
Document = Activity list
List of all the activities on the project
Process = Define activities
Document = Assumption log
List of all project assumptions and constraints
Process = Develop project charter
Document = Basis of estimates
Describes how schedule, cost, and resource
estimates were developed. Also includes their
confidence level and ranges
Process = Estimate activity duration, estimate costs, estimate activity resources
Document = Change log
Lists and describes the status of the change requests
that is being processed or have been processed
through the perform integrated change control
process
Process = Perform integrated change control
Document = Cost estimates
Cost of each individual activity
Process = Estimate costs
Document = Cost forecasts
A prediction of how much the project will cost when
it completes based on the current work
Process = Control costs
Document = Duration estimates
Amount of time needed to complete each activity on
the project
Process = Estimate activity durations
Document = Issue log
List of all issues on the project. Could include
history type, description, priority, status, and
resolution
Process = Direct and manage project work
Document = Lessons learned register
List of all lessons learned throughout the project
Process = Manage project knowledge
Document = Milestone list
Description of milestones on a project
Process = Define activities
Document = Physical resource assignments
Assignments of the physical resources to the
activities or work packages
Process = Acquire resources
Document = Project calendars
A calendar view of what takes place on a day-to-day
basis on the project
Process = Develop schedule
Document = Project communications
Communicate on the project by following the
communications management plan
Process = Manage communications
Document = Project schedule
A detailed breakdown of the work that needs to be
done in order to complete the project. Will include a
bar chart, milestone chart, and the project schedule
network diagram
Process = Develop schedule