PMP - Keeping the Team on Track (L4) Flashcards
How often should we be doing Team Building?
At Every Meeting!!
Key Performance Indicators - matches team performance with project vision and objectives.
-We always have KPIs and they are always SMART!
Specific - goal is focused, not overly general or vague
Measurable - change can be quantified and assessed
Achievable - plausible and realistic
Relevant - KPI is meaningfully related to its critical
success factors
Time-bound - goal is not open-ended but can be
assigned a specific target duration
- Isomorphic
- Matrix Team
- Surgical Team
(Same Shape)
- (Specialty Team)
- (Einstein)
** Tuckerman’s Stages of Group Development **
- 3.
4.
5.
- Forming - Wondering if decision to join team was wise. Making initial judgements about the skills and personal qualities of their teammates as well as worrying about how they will be personally be viewed. Team member conversations are polite and noncommittal as they do not want to reveal yet their personal views, team tries to figure out who is in charge
- Storming - team members begin to assert themselves and control issues as they arise, personality differences begin to arise. Conflicts result as members differ on the way they want to do project work, or the way they want to make decisions.
- Norming - team begins to work productively without worrying about personal acceptance or control issues. There are still conflicts, but they tend to be focused on process issues rather than personality differences. Team begins to operate off mutual dependence and trust.
- Performing - Team is working at optimum productivity. Team feels safe in reporting problems, trusting their fellow team members to help them create the best solution for the team as a whole.
- Adjourning - Team members complete their assigned work and shift to the next project or assigned work. Also known as “Mourning”
** When a project is done & past the scheduled completion date, what is the SPI? What is the SV?
SPI = 1
SV = 0
** Planned Value (PV) is… **
the authorized budget assigned to scheduled work and is specified in the project cost baseline.
-PV indicates the value of work scheduled to be done during a particular time period.
** Earned Value (EV) is… **
** EV = ?
the measure of work performed expressed in terms of the budget authorized for that work.
-EV indicates the value of work actually performed during a particular time period.
EV = % completed x Planned Value (PV)
** Actual Cost (AC) is **
the realized cost incurred for the work performed on an activity during a specific time period.
-AC indicates the actual money that has been spent for work that has been completed
** Schedule Variance (SV) is **
** SV = ?
measure of schedule performance
SV = EV - PV
A positive SV indicates that the project is…?
Ahead of Schedule
A zero SV indicates that the project is…?
On Schedule
A negative SV indicates that a project is…?
Behind Schedule
**Schedule Performance Index (SPI) is… **
SPI = ?
a measure of schedule efficiency
SPI = EV / PV
An SPI number greater than 1.0 indicates…?
Project is Ahead of Schedule
An SPI number of 1.0 indicates…?
Project is On Schedule