Questions from Paris exam Flashcards

1
Q

Creating a Benefit plan you have field “Offset types” (field to indicate when the benefits start realizing) with 3 choices, what are those?

A

Milestones
Start Date
End Date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What role can assign time sheet (or card) policy to a user?

A

Time Card Administrator (can assign a time sheet policy to a user)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Where can you make changes in RAIDAC…?

A

Flow Designer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What field (and tab?) is Capex/Opex chosen in?

A

Project Form->Cost Plan->Field: Cost Type (Capex & Opex / 5 choices each)

  • External Labor
  • Labor
  • Software
  • Hardware
  • Other
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Something about “derrive from assignee…” where do you set this option?

A

Project form->Preference tab-> Derive assignee list from resource plan (limits the possibility to only derive resources from allocated resource plans for the project).
Also: Derrive Time component from planned dates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What role is needed to see details tab in project(not sure)?

A

it_project_user: Can see details tab

it_project_manager (?)- configuration access right to all Project Management application features and functionality.
it_project_portfolio_user: User who can view IT Portfolio Project records (can see details…)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What values are project score based on?

A

Risk - value - size

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What cannot be part of several programs (or portfolio, not sure)? (several examples)

A

*Project & demand can NOT be part of multiple
Programs, only 1
*Program can be part of 1 portfolio or no portfolio
*You can have projects and demands that can directly be part of a portfolio and not part of a program

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is WBS?

A

Work Breakdown Structure (WBS) is a hierarchical representation of all the tasks in your project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What plugin is needed to activate investment funding?

A

Investment Funding for PPM plugin (com.snc.investment_planning_pmo)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Something about: What can PM or Time Card Admin create to specify activities….? Timecard/timesheet, what is the difference?

A
  • Time cards are used to record the time worked on a task by a task assignee
  • A time sheet groups all the time cards for a user for the given week
  • The time card retrieves time accrued on a project or spent working on any record in the Task table from the Time worked field (user must be Timecard User & Assigned to task)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Customer need to be able to connect time entries to specific activities, how do you do that(?)???

A

Track the activities of a time card, such as who submitted or approved a time card, in the Activities section on the Time Card form. To track the activities, enable the State field of the Time Card [time_card] table for auditing the time card activities, if it is not already enabled
**Project time category - used to specify

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Whats the default schedule for project?

A

Mon-fri, 8-12 & 1-5 (8h)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When is assessments sent for a demand?

A

Screening state

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Something about stakeholderlist??? 5 diffrent types, what are they?

A

Assessment Stakeholders- asmt_m2m_stakeholder
Demand Stakeholder- dmn_m2m_demand_stakeholder
Stakeholder Register- dmn_stakeholder_register
Project Stakeholder- pm_m2m_project_stakeholder
TeamSpace1…- tsp1_stakeholder_register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How long is the default sprint period?

A

14 days

17
Q

What colors (statuses) are there for projects(?)

A

Green-Yellow-Red

18
Q

What diffrent types of roadmaps are there in PPM (3)?

A

CIO
Project
Demand

19
Q

What dates are populated from a demand when project is created?

A

Planned end-start

Approved start-end

20
Q

What role can access a MPP project imported to a Teamspace???

A

Project user (it_project_user) - Can only view Project form fields. Can modify additional fields on the Project Task form, such as Time constraint and State.

Project manager - Has configuration access right to all Project Management application features and functionality
MPP imported into a teamspace is only available to users who can access the teamspace.. tsp_project_user?

21
Q

Where does the “status” for a project come from?

Or what color/status is picked up by overall status?

A

overall health field in the most recent project status report of the project.

22
Q

The Project Task form includes a Time Constraint field, which can be either of these values(4)?

A

Start ASAP
Start on specific date.
Start no earlier than
Start no later than

23
Q

What execution types are there for projects?

A

Waterfall
Agile
Hybrid

24
Q

In allocation workbench you can filter on 2 “time types”?

A

In Allocation Workbench you choose week or month,

25
Q

What box/field needs to be checked for surveys to be sent to a specific stakeholder?

A

Assessment Recipient (set to yes)

26
Q

To create several tasks at once, what feature do you use?

A

Project Task Creator

27
Q

What needs to be done to have a task outside a schedule?

A

In Planning Console, set task to “Allow dates outside schedule”

28
Q

Time sheet policy, on what levels can you set it (?)

A

As a time card administrator, you can assign a time sheet policy to a user.

29
Q

What zoom levels are there in (project) Planning Console?

A
Day
Week
Month
Quarter
Year
Auto Fit