71# Which of the following should be done during the Sprint Review? (Multiple answers)
• Demonstration of the Increment
• The Scrum process, and how it was used during the Sprint
• Communication of the project progress
• Technical practices

A
  • Demonstration of the Increment

* Communication of the project progress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

72# The Sprint Review is:
• An opportunity for improving the Scrum processes
• An opportunity for receiving approval for the work done
• An opportunity for inspection and adaptation
• An opportunity for reviewing the viability of the project

A

• An opportunity for inspection and adaptation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
73# Which does a self-organizing Development Team choose?
•	How to best accomplish its work
•	Product Backlog ordering
•	Sprint Length
•	When to release
A

• How to best accomplish its work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

74# When is a Sprint cancelled?
• When the infrastructure and tools are not ready for the whole project
• When the Product Owner determines it makes no sense to finish it
• When the Development Team finds it necessary
• When the Scrum Master decides to

A

• When the Product Owner determines it makes no sense to finish it

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
75# What’s the vertical axis in a typical burn-down chart?
•	The amount of remaining work
•	The progress
•	The technical debt
•	The capacity of the team
A

• The amount of remaining work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

76# Who can replace Sprint Backlog items during the Sprint?
• The Scrum Team
• No one
• The Development Team
• The Product Owner and the Development Team together
• The Product Owner
• The Scrum Master

A

• No one

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
77# Who’s responsible for engaging the stakeholders?
•	The Product Owner
•	The Development Team
•	The Scrum Master
•	The team leader
•	The project manager
A

• The Product Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

78# Items at the bottom of the Product Backlog are usually larger than those on the top.
• False
• True

A

• True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
79# What’s the timebox for a complete Sprint Planning meeting?
•	8 hours for a one month Sprint
•	8 hours for a two week Sprint
•	6 hours for a two week Sprint
•	6 hours for a one month Sprint
A

• 8 hours for a one month Sprint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
80# Who determines how work is performed during the Sprint?
•	The Development Team
•	The business analyst
•	The Scrum Team
•	The solution architect
•	The Product Owner