Question 61 to 70 Flashcards

1
Q

61# It’s better to have longer Sprints when the project is riskier.
• True
• False

A

• False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

62# Items in the Product Backlog are usually larger than items in the Sprint Backlogs.
• False
• True

A

• True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
63# Who must do all the work required for Product Backlog items, to make sure they are potentially releasable?
•	The Development Team
•	The Product Owner
•	The Scrum Master
•	The Scrum Team
A

• The Development Team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

64# What does it mean for a Development Team to be cross-functional?
• The team should collaborate with all functional units
• The team includes not only programmers, but also testers, architects, UI designers, etc.
• All the Development Team members should be cross-functional individuals.
• The developers should work closely with business analysts, architects, and testers external to the team.

A

• The team includes not only programmers, but also testers, architects, UI designers, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
65# When should Increments be shipped?
•	After each Sprint
•	When it makes sense
•	When the Increment is shippable
•	When the Increment is free of defects
A

• When it makes sense

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

66# When multiple teams are working on the same project, how many Definitions of Done should they use?
• There can be multiple definitions, as long as they are well communicated and understood among teams and with the customer
• There can be multiple definitions, as long as they are capable of creating a potentially releasable Increment
• Each team defines its own Definition of Done independently of others
• There should be only one Definition of Done for all teams

A

• There can be multiple definitions, as long as they are capable of creating a potentially releasable Increment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

67# Which is NOT a Development Team responsibility?
• Measuring the performance of the Sprint
• Resolving internal team conflicts
• Selecting the Product Owner
• Optimizing the work required for Sprint Backlog items

A

• Selecting the Product Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
68# Which of the following is the subject of Sprint Retrospective?
•	Scrum process
•	Product Backlog order
•	Technical approach
•	Increment
A

• Scrum process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

69# All Increments should be potentially releasable.
• True
• False

A

• True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
70# When should the Sprint Retrospective be held?
•	Each Sprint
•	When needed, based on lessons learned
•	When asked by the Scrum Master
•	When asked by the Product Owner
A

• Each Sprint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly