Quantification & Costing Flashcards

1
Q

Why were the new Rules of Measurement introduced.

A

To standardise and improve the accuracy of measuring works.

NRM aimed to enhance cost management, reduce disputes, and provide cost compatibility with international standards

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is NRM 1

A

Order of cost estimating and elemental cost planning for capital building works

provides a structured basis for measuring building works and for the production of cost estimates and cost plans.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the key sections of NRM 1

A

Part 1 - general introduction explaining the purpose of the documents and how it should be used.

Part 2 - Measurement rules for the production of cost estimates

Part 3 - Measurement rules for the production of elemental cost plans

Part 4 - Tabulated rules of measurement for elemental cost planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why should you use the New Rules of measurement

A

The NRM provides a common and consistent basis for the production of cost estimates and cost plans

NRM is seen as best practice, therefore in the event QS had a claim against them for negligence, if they could prove they used NRM it could provide a good defence against the claim.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does GEA stand for

A

Gross External Area

this is the area of the building measured externally at each floor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What does GIA stand for

A

Gross Internal area

area of the building measured to the internal face of the external walls.
Excludes external open sided balconies, canopies, external walls and fuel stores

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What does NIA stand for

A

Net internal area

this is the area of useable space measured to the internal face of the perimeter wall at each floor level.

The NIA excludes internal structural walls, columns, spaces with headroom less than 1.5m, lift lobbies, toilets, plant rooms

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Where are all the abbreviations found

A

The Code of Measuring Practice, issued by the RICS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the purpose of the code of measuring practice

A

Provides precise definitions to allow for accurate and consistent measurement of buildings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What would you expect the percentage of NIA to GIA to be

A

The percentage would depend on the type of project you are undertaking

For example in an office building, the NIA to GIA would be roughly 70%-85%

Where 70% is considered as relatively inefficient, a percentage of 85% is considered very efficient.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What do you measure in accordance with

A

The method of measurement would depend on the region, project and client i am working for

For example in the united kingdom, in the building sector, i would use the New Rules of Measurement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the purpose of a BOQ

A

To provide the estimator with an accurate picture of the scope of works and common consistent basis for pricing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How would you prepare a BOQ

A

Compile all necessary information - drawings specifications, schedules, document registers.

If the Information provided was sufficient to allow for the BOQ to be compiled, i would discuss with the project team the best method of measurement to be adopted.

i would then commence the take-off and work from the sub-structure upwards.

following the BOQ production i would carry out regular meetings and review any updated drawings to ensure that no that no works items have been missed between packages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How would you structure a BOQ

A

In accordance with an elemental breakdown structure under NRM 2, I would include the following sections:-

o Preliminaries (Main Contract).
o Facilitating Works.
o Substructure.
o Superstructure.
o Internal Finishes.
o Fittings, Furnishings and Equipment.
o Services.
o External Works.
o Provisional Sums.
o Dayworks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How would you describe the preliminaries section in a BOQ

A
  • The preliminaries detail out items of works that are required but are not associated in the main measured works.

For example, site set up, management & supervision, or insurances

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How do you evaluate a variation which is based on a BQ item which contains an error

A

Assuming the same nature and conditions are applicable, the variation would be based on the BOQ rate in the contract

unless both parties agree to amend the rate to a fair and reasonable alternative

17
Q

What is a Provisional Sum

A

It is an allowance for item of works that cannot be defined or accurately priced.