Project Finance Flashcards

1
Q

How would you create a Cashflow forecast

A

I would gather the CSA and the programme duration and insert the data into an S-curve Formula

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

If your construction budget was £2.5m and proposed construction period was 25 weeks, would a forecast cashflow expenditure of £100,000 per week be realistic?

A
  • This is not a realistic cashflow forecast as this would be based on a flat rate expenditure for the duration of the project.
  • Typically at the beginning of the project during the enabling works stage and you only have one or two sub-contractors onsite expenditure is relatively low and as progress increases more trades are onsite therefore once the superstructure shell is compete internal M&E and internal finishes will be underway where the bulk of the cost is so expenditure will be much higher.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the benefit of a cashflow forecast

A

A cashflow forecast allows the client to forecast budget expenditure throughout the project. Time to secure future funds.

It can also be guide on contractor valuations which can be used as a guidance on progress.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a financial report and what is its purpose

A

A financial report is a structured document based on client requirements and issued periodically.

it tracks any adjustments to the Contract Sum Analysis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What would you include within a financial report

A
  • Executive summary (Anticipated Final Account)
  • Contract instructions
  • Anticipated variations
  • Provisional Sum tracker
  • EOT adjustments
  • Other
  • Cashflow forecast
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are Variations

A

Variations are adjustments to the contract scope such as design, quality or quantity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Why might variations arise

A

Variations might arise, because a client wants to make a change to their project that will increase value.

  • Discrepancies between contract documents
  • change in specification
  • Deficiencies in Employers requirements
  • Errors and Omissions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What form must instructions take

A

Contract administrators instruction. Under most contracts it is best practice for instructions to be made in writing.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Does contracts allow for verbal instructions

A

It is best practice to always provide a written instruction.

Yes the JCT has provisions for verbal instructions. The contractor must follow up with a written notice within 7 days. then the CA should notify the contractors notice within 7 days.

The new 2024 suite of contract states contract instructions should be given in writing when practically possible.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Can the contractor object to a variation

A

Some contracts allow the contractor to object to an instruction in special circumstances for example, in the JCT standard Building Contract certain exceptions are:
- Where the instruction might affect the contractors compliance with the CDM Regulations

  • Where the instruction may infringe patent rights
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

what can the CA/EA do if the contractor does not comply with an instruction

A
  • Depends on the form of contract being used. Under JCT suites if the contractor does not follow an instruction, the CA/EA will be required to issue a ‘notice to comply’ to the contractor
  • If the Contractor still fails to comply after 7 days, another party can be instructed to carry out the work and the contractor will be liable for any additional costs incurred.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What 3 methods are there of obtaining a cost for variations under JCT forms of contract

A

Under JCT SBC can be made by:

  1. Agreement between employer and contractor
  2. A schedule 2 quotation
  3. Valuation Rules
    - Contract Rates
    - Market rates
    - Dayworks
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

what are the variations valuation rules under JCT forms of contract

A

Valuation Rules
- Contract Rates if works are similar character, quantity, conditions
- Market rates/ fair and reasonable allowance, if similar character, but different quantity and conditions
- Daywork

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are fair and reasonable rates and prices

A
  • A market rate
  • A rate based on actual costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

what are dayworks

A
  • The prime cost for all the materials, labour and plant used to carry out the works
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a star rate

A
  • a new rate, for example a change of specification of concrete to rapid set, fast setting concrete
17
Q

What document should the prime cost be calculated in accordance with

A

‘Definition of the prime cost of day work carried out under building contracts’ published by the RICS

18
Q

What Information is necessary to be able to assess dayworks

A
  • Time sheets
  • Names if the workmen
  • plant and materials used
19
Q

Can the QS alter hours which he considers to be excessive on a dayworks sheet that is authorised by the architect

A
  • No the hours recorded and signed off should be maintained within the variation
20
Q

What would you do id the contractor submitted 10 dayworks sheets to you for payment

A
  • I would verify that a relevant variation has occurred and is recorded on an Instruction
  • I would check to ensure there is no other contractual method of valuing the variation
  • providing the Instruction is in place and no other mechanism for valuation is available i would seek verification of the hours and materials
21
Q

What is an example of dayworks under the valuation rules

A

unforeseen circumstances in ground conditions i.e unaccounted for rock layers or utilities

22
Q

If you and the contractors QS could not agree on something how would you resolve it

A
  • i would discuss with the client to try and seek a resolution with the contractor
  • the contractor could take the dispute to adjudication if necessary but all parties should try and resolve the matter by negotiation in the first instance
23
Q

What is quantum meruit

A
  • This translates to ‘what he deserves’ for example, fair and reasonable costs that have been incurred.
24
Q

What is quantum merit and give an example of where it might be used

A
  • If the employer and contractor reach a separate agreement on acceleration, the costs of this may be based on a ‘fair and reasonable’ basis
25
what is loss and expense under JCT forms of Contract
- A breakdown provided by the contractor that should include losses incurred in carrying out additional work from an employers breach of contract
26
What are the procedures for claiming loss and expense under a JCT form of contract
As soon as the regular progress of work is affected, or the contractor becomes aware of any other matter that would cause them to incur loss and expense, they would notify the architect of QS in writing
27
What are relevant matters under JCT forms of Contract
Events listed in the contract that entitle the contractor to loss and expense
28
What are the relevant matters
There are 4 relevant matters - Variations - instructions - suspension by the contractor for non-payment - any impediment or default by the employer (Example, the employer preventing the contractor access to the site)
29
What is the key thing to remember when assessing loss and expense claims
It should be the actual loss incurred by the contractor
30
What are the common heads of claim in loss and expense claims
Direct costs: - Cost for materials - labour costs - costs for specialist equipment Indirect costs (Overheads and Prelims) - Rent, utilities - salaries - insurance - temporary site facilities
31
What is a change control procedure
A process which clearly defines how changes are requested and approved
32
What are the common types of discrepancies between contractors cash flow and yours
- Front loading - Contractor trying to claim more funds at the beginning of a project - re-sequencing of works - variation and allowances for change control - Delays and loss and expense - Project progressing slower than anticipated Cashflow must be regular updated and reviewed.