Quantification & Costing Flashcards

1
Q

What would be on your take-off list for a concrete slab?

A
  • Floor slab area, incl the depth
    *Reinforcement allowance
  • Formwork
  • Joints
  • Surface treatments
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is NRM 1?

A

Order of cost estimating and cost planning for capital building works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is NRM 2?

A

Detailed measurement for building projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is NRM 3?

A

Order of cost estimating and cost planning for capital maintenance works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is standard methods of measurements?

A

Standard methods are rules to ensure that all pricing of construction projects are of the same standard.

These consist of guidance and a set of rules for the basis of measurement, to ensure that the same items are included (or excluded) in each rate, so that costs for that element can be accurately applied.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Name a number of sources of cost data

A

Spons + Legacy Projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is prime cost?

A

The Unit rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is dayworks?

A

When works cant be measured in a normal way and so have to be priced based on labour, plant and OHP.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How would you price an estimate at RIBA Stage 1?

A

m2 based on the GIFA or on functional units

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How would you price an estimate at RIBA Stage 2-4?

A

More concise measures using dimension etc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a GIFA?

A

Internal part of the building to the internal perimeter wall

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a GEA?

A

All areas outside the building

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the difference between NRM1 & NRM2?

A
  • NRM 1 utilises unit rates - should include the cost of all materials, labour and plant that are specifically required to construct the item. Costs are also to include any subcontractors’ on costs
  • NRM2 - more detailed, costed and broken down in detail. E.g. finishing, formwork, reinforcement types all split out
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Outline valuation process

A

-Pre val - Checking due dates
-Pre Val - Review programme, cash flow, take offs
-On site assessment - walkround with contractor do not need to agree val
-Valuation - review documents one last time and issue documents
-Post val - reporting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Outline Valuation timeline

A

-Contractor submits interim valuation on or before the due date
- 1 week after the due date, assessment take places
-2 weeks after is last day for pay less
-3 weeks Is payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How is a valuation calculated under Option A

A

PWDD for fully complete activities + CEs - retention

17
Q

How do you benchmark?

A
18
Q

Why is it important to measure the works according to industry standards and best practice?

A

-To provide consistency and greater accuracy of pricing.
-To ensure that all parties price on the same basis and therefore reduce the risk of dispute

19
Q

What is IPMS and what is its Purpose?

A

International Property Measurement Standards - IPMS All Buildings supersedes all previously published IPMS standards for individual asset classes by utilising the concepts and objectives contained in those specific versions of IPMS into one harmonised standard

20
Q

What is a defined Prov Sum

A

A Provisional sums which have been described in sufficient detail that the contractor is expected to have made allowance for them in their programming, planning and pricing preliminaries.

21
Q

What is an undefined prov sum

A

A Provisional sum which has not been described in enough detail so the contractor is not expected to allow for programming and prelims.