Quantification & Costing Flashcards
What would be on your take-off list for a concrete slab?
- Floor slab area, incl the depth
*Reinforcement allowance - Formwork
- Joints
- Surface treatments
What is NRM 1?
Order of cost estimating and cost planning for capital building works
What is NRM 2?
Detailed measurement for building projects
What is NRM 3?
Order of cost estimating and cost planning for capital maintenance works
What is standard methods of measurements?
Standard methods are rules to ensure that all pricing of construction projects are of the same standard.
These consist of guidance and a set of rules for the basis of measurement, to ensure that the same items are included (or excluded) in each rate, so that costs for that element can be accurately applied.
Name a number of sources of cost data
Spons + Legacy Projects
What is prime cost?
The Unit rate
What is dayworks?
When works cant be measured in a normal way and so have to be priced based on labour, plant and OHP.
How would you price an estimate at RIBA Stage 1?
m2 based on the GIFA or on functional units
How would you price an estimate at RIBA Stage 2-4?
More concise measures using dimension etc
What is a GIFA?
Internal part of the building to the internal perimeter wall
What is a GEA?
All areas outside the building
What is the difference between NRM1 & NRM2?
- NRM 1 utilises unit rates - should include the cost of all materials, labour and plant that are specifically required to construct the item. Costs are also to include any subcontractors’ on costs
- NRM2 - more detailed, costed and broken down in detail. E.g. finishing, formwork, reinforcement types all split out
Outline valuation process
-Pre val - Checking due dates
-Pre Val - Review programme, cash flow, take offs
-On site assessment - walkround with contractor do not need to agree val
-Valuation - review documents one last time and issue documents
-Post val - reporting
Outline Valuation timeline
-Contractor submits interim valuation on or before the due date
- 1 week after the due date, assessment take places
-2 weeks after is last day for pay less
-3 weeks Is payment