CONTRACT PRACTICE Rev2 Flashcards
What is a contract?
A Legally binding agreement between two parties whereby one party is to fulfill an obligation for another in return for consideration.
What needs to be in place for a contract to be valid?
Offer
Acceptance
Consideration
Intent
Legality
Capacity
Why do we use contracts in construction?
Construction projects are often bespoke and require risk management and allocation which contracts support.
What are the NEC options?
NEC – Option A Priced contract with activity schedule
NEC – Option B Priced contract with Bill of quantities
NEC – Option C Target cost with activity schedule
NEC – Option D Target cost with BOQ
NEC – Option E Cost reimbursable
NEC – Option F Management contract
NEC – ECC Short Contract
What other suites of contract are available?
JCT & FIDIC
What Does JCT Stand for?
Joint Contracts Tribunal
What is the payment mechanism under the NEC Option A?
Paid for full completed activity schedule activities.
Price for the works done plus any additional amounts due to the contract i.e CEs minus retention.
You mention the construction act 1996, what is the purpose of it and what did it introduce
To ensure that contractors and sub-contractors could enforce payment of amounts due without having to take expensive court proceedings
Interim payments
Suspension
Adjudication
Pay when paid
Applies to verbal contracts
What are the standard timescales for payment in the NEC?
The first assessment date is decided by the PM
Contractor must submit application on or before the assessment date
PM certifies payment 7days later
Final date for payless to be issued 14day after assessment date
Final date for payment 21 days after assessment date
What is the risk to a client if the doesn’t pay by the final date for payment?
If the failure continues for 7days after notice to the employer of intention to suspend has been issued they can suspend performance
It also entitled the contractor to Relevant Event
And will be reimbursed for reasonable costs for suspension
If the default continues for 14 days following notice the contractor can on or within 21 days from expiry of the 14 days terminate the contract
What impact can the non submittal of the first programme have on the payment to the contractor?
25% can be withheld from the contractor until the first programme is submitted
What are the steps you take through the valuation process?
Planning - Understand the contract and the requirements of dates and co-ordinate with all parties
Pre-Valuation - Desk top review of the valuation submitted
Valuation - Review the works on site discuss and agree wit the contractor the position of the valuation (DOSENT HAVE TO HAVE AGREEMENT)
Validation docs - Carry out final review of val and correct all items within the val that are erroneous
Issue Val - Complete payment certificates and issue to all parties
Post Val - Record the val and payments and manage discrepancies
What is a compensation event?
An event that doesn’t arise from the fault of the contractor but they are due the additional cost and or time in which the event has caused.
How many CEs are there?
19
What are the two ways a CE can be notified?
By the contractor by CE or PM via PMI
What is the CE process?
Notification
Quote
Assessment
Implementation