Project Finance Flashcards
At what stage do you produce a feasibility estimate?
RIBA Stage 1
At what stage do you produce a Cost plan?
RIBA stage 2, 3 & 4
What’s the difference between estimate and cost plan?
Cost Estimate
- RIBA stage 1
-Limited info based on area rates
- Budget setting purposes
Cost Plan
- RIBA stage 2, 3 & 4
-Concept to full design info
-Assesses design development
Why is an estimate beneficial to a client?
It allows the client to make financial decisions on budget setting purposes and may also affect design changes.
Why is a cost plan beneficial to a client?
Allows the client to see design development and allows them to make financial designs based on the impact of design against budget.
What is a cost report?
A Cost report is a monthly report which demonstrates the known and anticipated cost changes against the client budget.
What elements should be included within a cost report?
-CSA
-Agreed change
-Anticipated change
-Fixed costs such as professional fees and direct work costs
-Cash Flow Forecast
-Final account forecast
Why is a cost report important to a client?
The purpose of cost reporting is to inform the client in a construction project of the likely outturn cost of the construction project. The forecast of outturn costs may
be expressed as a variance against a budget amount, or expressed in absolute terms.
What shape is a cashflow and why is this the case?
- S Shape
-The least amount of works take place at the start and end of the project. - The majority of work packages take place in the middle.
- Less works at the start and end mean less payment compared to the middle.
If a contractors application was more than the cash flow forecast what could this mean?
-Ahead of Programme
-Overclaiming
If a contractors application was less than the cash flow forecast what could this mean?
-Behind on Programme
How did you show value for money when assessing CEs?
-Benchmark rates against legacy schemes
-Check if it is a valid CE in the contract
-Request supplier quotes
- Check if it is Arithmetical correct
-Query contract on any rates or discrepancies
CE TIMELINE
Contractor notifies within 8 weeks of knowing about the issue and submits a CE.
1 Week period for PM to submit a PMI or the contractor to submit a quote.
PM accepts or in 2 weeks the CE is automatically accepted.
Do you know any recent legislation changes?
Building safety act 2022
What did the Building safety act 2022 introduce and what is the affect on building projects?
Fire safety legislation
- increase cost for certain compliant materials
-Increased planning within design stages
- Harder to obtain insurances and greater risk premium
- Changes to design regulations particularly with high rise residential dwellings