Quantification and Estimating New Flashcards
How did you normalize bids on Beckton depot enabling works?
- Bidders did not all offer the same solution
- Requested 2 bidders to submit a mains foul connection solution.
- Only one bidder submitted a price so had 2 bidders with mains connection price and one with sceptic tank.
- I decided that the highest figure would be applied to the missing tenderer
- That then enabled each bidder to have comparative solutions to the mains connection.
How did you create the tender documentation for the bidders to value?
- I created an activity schedule for the bidders to price.
- This detailed out the preliminaries so they would all be priced in the same way.
- As well as the main works descriptions
- The bidders could then apply assumptions
How have you negotiated and agreed the valuation of construction works at various stages of a project such as contract sum, construction and final account?
On Beckton depot enabling works it was decided by the client that the mains foul water connection was no longer needed.
The contractor priced the work in the activity schedule at £110k as part of the tender.
The PM assumed they would receive back the value from the activity schedule price.
I advised the PM it would not be a case of removing the activity and returning the cost.
Under NEC3 ECC option A the cost would should be calculated on I built up a price from forecasted defined cost and the costs already incurred.
I advised that we Issue a PMI for the contractor to provide a quotation for the descope based on:
(i) the Defined Cost of the work already done
(ii) the forecast Defined Cost of the work not yet
done
(iii) the resulting fee (fee percentage applied to
the amount of Actual Cost covering specific
costs, mainly head office overheads and
profit).
How have you advised on appropriate methods of measurement and costing?
…
Describe advice given to a client in the valuation of variations, what was your advice? How did you arrive at this decision? why was it better than alternatives?
…
What is the Civil Engineering Standard Method of Measurement?
CESMM – has been well established for over 20 years as the standard for the preparation of bills of quantities in civil engineering work
When was the latest edition of the CESMM?
Volume 4 revised in 2019 published by ICE
How is the CESMM categorised?
26 classes - A-Z – Ground investigation, site clearance, earthworks, pipework, roads..etc
How would you advise your client on dealing with an error that was contained within a bid?
On identification of the error I would advise the client that…
- If identified prior to the contract being signed then this could be discussed with the contractor & amended in accordance with the option notified in the Instruction to Tenderers.
- Once the contract has been signed both parties must stand by the rate within the contract, even if it were wrong. Only through agreement would the parties be able to amend the rate.
What is the purpose of the RICS Code of Measuring Practice?
Provides precise definitions to permit the accurate and consistent measurement of buildings
What methods can be used to form an order of cost estimate?
- Floor area method
- Functional unit method (per bed per house)
- Elemental method (individual elements)
What is an elemental cost analysis?
Is a full appraisal of cost involved in previously constructed buildings and is aimed mainly at providing reliable information that will assist in accurately estimating the cost of future buildings. It provides a product-based cost model providing data which initial elemental estimates and elemental cost plans can be based on.
What are preliminaries?
Are items which cannot be allocated to a specific element, sub-element or component. Main contractor’s preliminaries include the main contractor’s costs associated with management and staff, site establishment, temporary services, security, safety and environmental protection, control and protection, bonds, guarantees and warranties.
What are enabling works?
Enabling works are the preparation of a site in readiness for the first stage of development. Examples include installing perimeter fencing, carrying out ground clearance, building access routes and putting up safety signage. Enabling works may also include preliminary construction work, such as groundworks.
What are facilitating works?
Facilitating works is a term used to describe specialist works which, normally, need to be completed before any building works can commence (e.g. demolition works, works involving the removal of hazardous and deleterious materials, and soil stabilization