Project finance and Cost reporting Flashcards
How is the RICS cost reporting guidance note structured?
- Best practice on cost reporting
- Purpose of cost reporting
- Reporting models – Construction, project, programme
- Reporting frequency – how often to report
- Establishing a budget
- Advising the client on the above
What is cost control?
The process of valuing and managing changes. To ensure the project is delivered at the right price
How have you provided advice to the client on cost control?
• Beckton depot contractor submitted
compensation event for additional ecology mitigation.
- Agreed at tender that survey would be complete but if uncovered then it was an employer’s risk.
- I assessed value of CE
- Filled out change form for approval to spend money
- Accepted CE
- Received quotation
How will you advise on the sufficiency of the remaining budget?
- Review forecast costs for all anticipated changes.
- Ascertain an anticipated final cost,
- Monitor against our remaining risk allowances to ensure I keep within budget.
- If this exercise shows a risk of budget overspend, I will advise when I become aware and we can look at potential mitigation measures.
On Beckton depot how did you advise and implement a change control procedure?
- Being aware of potential changes to price/completion/risks
- Assessing and managing early warnings
- If change is needed on a project getting internal authority for change
- Complete change request form detailing change and cost
- Present to change board
- Once approved accept change on project
What is included on a change control form?
- Name and addresses of the client, EA and contractor
- Description of change
- Dates of when CRF was raised
- Reason for change
- Cost of change
- Source of funding
- Package
On Beckton depot how did you draw down risk?
Once change control form is completed and approved funds from the risk allowance are allocated within the cost plan to the agreed changes.
How do you ensure effective control of costs in a project?
- Reporting on value of work done in cost report
- Reporting on cash flow forecast
- Proactive risk and contingency management
- Implement change control process
On Colindale Project why did you advice the client that an S curve should be used for the construction costs?
- Takes the shape of the letter ‘S’ when shown on a graph .
- This represents the lower level of periodic expenditure at the beginning of a contact (due to site set up and relatively inexpensive enabling works)
- Then an increase in costs due to the main construction work being delivered and most likely costing the highest proportion of the project. More staff, more plant, welfare.
- Costs level off as work decreases and resources decrease to close project out.
You mentioned you are responsible for cost reporting to the client. Please talk me through how you would produce a cost report and how this would be presented to the client?
On Beckton depot I advised the client on construction costs under a lump sum contract:
I advised the cost report should include
- Contract sum
- Agreed changes
- Unagreed changes
- Lease agreement
- Internal staff cost
- Adjustment of risk allowances.
This would reported in an in house templated excel format so it could feed into the project cost report which feeds into programme cost report.
I advised reporting on costs each period – 1-13 – 4 weekly.
How can a cost report help to monitor & control the project budget?
- It tracks all the issues relating to cost on a project
- Budget, forecast, expenditure to date
- Shows remaining expenditure
- Helps final account
What are the contents of a monthly project cost report?
- construction costs
- professional fees
- statutory fees and charges
- third-party costs
- direct works costs
- land costs
- agency costs
- finance cost; and
- legal fees
Are there any costs you would exclude from a cost report?
If it is a construction cost report i would exclude professional fees, 3rd party costs, land costs, agency costs, finance cost and legal fees
What is the purpose of cost reporting?
To inform the client of the likely outturn costs.
- To record all known costs which can be accurately valued
- To report all costs which are known and can be estimated at the date of the report
- To forecast costs as can reasonably be foreseen at the date of the report
- risk allowances necessary as can be reasonably foreseen at the date of the report.
What are benefits of cost reporting?
Cost reporting regularly and frequently will afford the client and project team the ability to control the outturn construction cost.
How is outturn cost controlled by cost reporting?
Outturn cost is controlled by the recognition of cost changes incurred and planned implementation of future cost changes.