Project finance and Cost reporting Flashcards

1
Q

How is the RICS cost reporting guidance note structured?

A
  • Best practice on cost reporting
  • Purpose of cost reporting
  • Reporting models – Construction, project, programme
  • Reporting frequency – how often to report
  • Establishing a budget
  • Advising the client on the above
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is cost control?

A

The process of valuing and managing changes. To ensure the project is delivered at the right price

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How have you provided advice to the client on cost control?

A

• Beckton depot contractor submitted
compensation event for additional ecology mitigation.

  • Agreed at tender that survey would be complete but if uncovered then it was an employer’s risk.
  • I assessed value of CE
  • Filled out change form for approval to spend money
  • Accepted CE
  • Received quotation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How will you advise on the sufficiency of the remaining budget?

A
  • Review forecast costs for all anticipated changes.
  • Ascertain an anticipated final cost,
  • Monitor against our remaining risk allowances to ensure I keep within budget.
  • If this exercise shows a risk of budget overspend, I will advise when I become aware and we can look at potential mitigation measures.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

On Beckton depot how did you advise and implement a change control procedure?

A
  • Being aware of potential changes to price/completion/risks
  • Assessing and managing early warnings
  • If change is needed on a project getting internal authority for change
  • Complete change request form detailing change and cost
  • Present to change board
  • Once approved accept change on project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is included on a change control form?

A
  • Name and addresses of the client, EA and contractor
  • Description of change
  • Dates of when CRF was raised
  • Reason for change
  • Cost of change
  • Source of funding
  • Package
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

On Beckton depot how did you draw down risk?

A

Once change control form is completed and approved funds from the risk allowance are allocated within the cost plan to the agreed changes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How do you ensure effective control of costs in a project?

A
  • Reporting on value of work done in cost report
  • Reporting on cash flow forecast
  • Proactive risk and contingency management
  • Implement change control process
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

On Colindale Project why did you advice the client that an S curve should be used for the construction costs?

A
  • Takes the shape of the letter ‘S’ when shown on a graph .
  • This represents the lower level of periodic expenditure at the beginning of a contact (due to site set up and relatively inexpensive enabling works)
  • Then an increase in costs due to the main construction work being delivered and most likely costing the highest proportion of the project. More staff, more plant, welfare.
  • Costs level off as work decreases and resources decrease to close project out.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

You mentioned you are responsible for cost reporting to the client. Please talk me through how you would produce a cost report and how this would be presented to the client?

A

On Beckton depot I advised the client on construction costs under a lump sum contract:

I advised the cost report should include

  • Contract sum
  • Agreed changes
  • Unagreed changes
  • Lease agreement
  • Internal staff cost
  • Adjustment of risk allowances.

This would reported in an in house templated excel format so it could feed into the project cost report which feeds into programme cost report.

I advised reporting on costs each period – 1-13 – 4 weekly.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How can a cost report help to monitor & control the project budget?

A
  • It tracks all the issues relating to cost on a project
  • Budget, forecast, expenditure to date
  • Shows remaining expenditure
  • Helps final account
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the contents of a monthly project cost report?

A
  • construction costs
  • professional fees
  • statutory fees and charges
  • third-party costs
  • direct works costs
  • land costs
  • agency costs
  • finance cost; and
  • legal fees
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Are there any costs you would exclude from a cost report?

A

If it is a construction cost report i would exclude professional fees, 3rd party costs, land costs, agency costs, finance cost and legal fees

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the purpose of cost reporting?

A

To inform the client of the likely outturn costs.

  • To record all known costs which can be accurately valued
  • To report all costs which are known and can be estimated at the date of the report
  • To forecast costs as can reasonably be foreseen at the date of the report
  • risk allowances necessary as can be reasonably foreseen at the date of the report.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are benefits of cost reporting?

A

Cost reporting regularly and frequently will afford the client and project team the ability to control the outturn construction cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How is outturn cost controlled by cost reporting?

A

Outturn cost is controlled by the recognition of cost changes incurred and planned implementation of future cost changes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is good cost reporting?

A
  • Always accurately track cost and changes
  • Communicate changes effectively as and when required
  • Keep a rolling final account
  • Good cost report document to keep client informed
  • Good relationship with contractor
18
Q

How often are costs reported?

A

On TfL projects (rail) the periods are split over 13 periods a year and each period a report is produced.

19
Q

What is a final account?

A
  • Financial statement of all the adjustments to the contract sum and therefore the total amount the employer is liable to pay.
  • End financial position
20
Q

How did you prepare the final account on Silvertown Tunnel project?

A

Check the contract procedures for final account including the timescales.

  • Produced final account statement with components detailed
  • Summary
  • Periodic payments
  • Variations
  • Claims
  • Adjustments
  • End figure
  • Provide evidence to other party
  • Presented to designer
  • Discussed any discrepancies
  • Once in agreement both parties sign and keep a record

Send all documentation to other party for agreement

Any issues not agreeing on arrange a meeting to discuss and try to find resolution

21
Q

What is a purchase order?

A

A purchase order is a legally binding document between a supplier and a buyer. It details the items the buyer agrees to purchase at a certain price point. It also outlines the delivery date and terms of payment for the buyer.

22
Q

What are variable costs?

A
  • Provisional sums
  • Risk
  • Loss and expense
  • Liquidated damages
  • Variations
  • Prime cost sums
  • Re-measurable contracts
  • Anticipated instructions
  • Fluctuations
23
Q

What are the processes for evaluating change?

A
  • Schedule of rates
  • Contractors quotes
  • Dayworks
  • First principles
24
Q

What is Daywork?

A

The monetary allowances made for the costs of labour, plant and materials, against which percentage uplifts are priced against the base rates of labour and prime cost of materials and plant.

I. E adhoc work that maybe not be covered in the contract.

25
Q

How did you reconcile invoices on the Surface transport project?

A

Forecast costs on predicted processions.

After possessions I would receive invoices from network rail and adjust the actual cost accordingly.

26
Q

Why is it important that the contingency pot is only used for risks which there was no provision for?

A

This is because these risks already have a provision in the contract and using the contingency would not be necessary. All costs which can be foreseen should have a provision within the contract.

27
Q

What factors affect the outturn construction costs?

A
  • Fixed costs
  • Variable costs
  • Daywork allowances
  • Provisional Costs
  • Planned and unplanned variations
  • Compensation events
  • Risk Allowances
28
Q

If a client suggests there is an error in the Cost Report – how would you go about resolving the problem?

A

I would clarify what the error is with the client and then do an inspection of the error. If i find that the client is correct, I will apologize and rectify the error. I will also let the client know of my complaints handling procedure.

29
Q

How did you deal with contractor’s claims in the cost report?

A

These should be treated as unapproved changes until they have been assessed for scope and cost.

30
Q

From your own experience what costs often escalate on a project? What did you do to mitigate this? Why did you do this?

A

Changes by the client, try to ensure the scope and design is as detailed as possible before tender.

31
Q

How do you produce the cashflows on your project and why is this helpful to the client?

A

Once the project has been tendered or a contract has been entered into with the contractor then the cash flow forecasting can become more accurate. If the contract is for stage payments of milestone payments then it becomes relatively simple to plot this information and create an accurate cash flow forecast.

I planned the cash flow of the project based on the forecast completion of the activities in line with the programme for the works. Then I could plot out how much money would be required each period.

32
Q

What are defined v undefined provisional sums? How do you report on these?

A

• Defined provisional sums are those which have been described in sufficient detail

• Undefined provisional sums are less well
described and so the contractor cannot be expected to make allowance for them

• Put in a figure and adjust as costs become apparent

33
Q

What is the purpose of a cashflow for the client?

A
  • To monitor progress against agreed programme

* To manage resources

34
Q

What is the purpose of a cashflow for the contractor?

A
  • To monitor subcontractor’s progress against subcontractors

* To manage resources

35
Q

What is cost value reconciliation?

A

It gives you an ongoing account of a contract’s profitability by measuring cost against value at different points in a contract’s lifecycle, right through to completion

36
Q

If monthly valuations are not in line with the projected cashflow what could this imply.

A

This could mean the project is not in line with the programme

37
Q

What are the causes of valuations not in line with cash flow?

A

The contract is behind schedule or the works were front loaded by the contractor

38
Q

How do you deal with provisional sums in a cost report?

A

NEC3 does not use provisional sums, display the figure as accurate as possible given the information available. If it cannot be described then don’t include and be valued as a compensation event.

39
Q

What quality assurance can be used for cost reports?

A

ISO 9001 standards

40
Q

Why is important for the contractor to be paid on time?

A

To ensure they can pay their debts and keep a positive cash flow to avoid borrowing money.