Design Economics & Cost Planning Flashcards
What are the RIBA Stages?
0 - Strategic Definition 1 - Preparation & Brief 2 - Concept Design 3 - Spatial Co-ordination 4 - Technical Design 5 - Manufacturing + Construction 6 - Handover 7 - Use
What is NRM 1?
- Rules for Order of Cost estimating + Cost planning for Capital Building Works
- Best Practice Guidance Note
How is the NRM1 set out?
NRM1 comprises four parts:
• Part 1 sets out the context and definitions.
• Part 2 explains how to prepare an order of cost estimate.
• Part 3 explains how to prepare an elemental cost plan.
• Part 4 provides tabulated rules of measurement for the preparation of cost plans.
What areas does the NRM1 provide guidance for?
- Facilitating works
- Building works
- Main contractor prelims
- Main contractor OHP
- Project/ design team fees
- Other development costs
- Risk (4 types)
- Cost limit
- Inflation
What is benchmarking?
Benchmarking is a tool for assessing and comparing performance in order to achieve continuous improvement. It is part of a total quality management process
How did you benchmark costs within your estimate?
I used in house indices that allow costs to be analysed.
This establishes a data base of similar projects cost data that can be used to assist in price future prices.
Give me an example of where you have given advice about the predicted costs of a construction project?
I joined the Silvertown project mid way through the tendering period and assisted in the commercial management of suppliers that were undertaking site surveys as part of the information that would be given to the tenderers. The staff resource was for internal staff. I worked with the programme manager to establish the ongoing project requirements and how these will change going forward.
- Firstly I identified the key positions that were needed throughout the life of the project.
- Then I calculated the number of hours that were likely to be needed per role
- I inserted this into a spreadsheet that fed into the cost plan and the hours were fluctuated against stage of the project.
- I linked this to the hourly rate for the position to determine the costs.
On Beckton Depot value engineering exercise how did you conclude the site accommodation should be moved from one project to the other?
I reviewed the main programme of works for DLR project and realised there was an opportunity to utilise time in between the enabling works and awarding the main contract to procure the site accommodation concurrently to have it established for the main contractor to start works straight away. I suggested to the Project Manager that as the site accommodation was intended beyond the duration of the main contractor for additional contract works that exploring this option could save time and reduce costs through no fees. This was the planned approach but due to Covid-19 the time gains were lost and the accommodation was moved back in to the Main Contract.
I spoke to multiple suppliers to understand the cost of rental, including all the services that were needed, including generator, sceptic tank and water bowser until more permanent solutions could be installed. I enquired about purchasing the welfare for the project but the disposal or buy back options at the end did not make it viable. If it could be used on more projects then it may have made better financial sense.
What is the BCIS?
BCIS is the Building Cost Information Service of the Royal Institution of Chartered Surveyors (RICS).
What is the purpose of a cost plan?
- It is used by the cost consultant to control the development of the design - It identifies the client’s agreed cost limit and how the money is to be allocated to the different parts of the building.
On cycle Quietway project how did you produce the cost plan?
To produce the cost plan I only had feasibility information and the brief from the client. They were able to tell me the likely route of the Quietway and what sort of path they intended for the route.
- Establish the employers requirements
- Understand the design – in this case route and basic requirements
- Location
- Timeframe
- Site conditions
- Procurement route
- Prelims
- OH and P
- Assumptions
- Exclusions
For me to then offer a cost appraisal I used previous projects costings per metre value for different cycleway layouts and applied it to the proposed route to. I also advised on the number of junctions and trees that the cycleway might intersect as this adds additional costs.
How have you advised on buildability?
Looking at the defined route to see what obstacles and restrictions are likely to increase costs ie trees
What are prelims?
They are the costs that are directly related to the running of the project that are not accounted for under labour or material. • Staff costs • Welfare • Staff provisions • Security • Safety • insurances
What Exclusions I have made on the cost estimate?
- Inflation as project was not long enough
- Contaminated land – Programme risk
- Leasing the land fees – Programme budget
What assumptions have you made in a cost estimate?
- Weekday working normal working hours
- Security in the day only
- Existing perimeter fencing provides adequate security
What are the purposes of a cost plan, other than cost control?
- Develop employer and designer awareness of cost proposals and desires
- Ensure employers get value for money
- Advise designers on practical and balanced design within budget
What is the importance of a cost plan?
To understand in an elemental form the costs of the project and how to control the costs. To inform the design team in changes to reflect the cost.
What is an order of cost estimate report?
This where you present the order of cost estimate to the client.
This will show the forecast output costs including project/design fees, project costs, risk allowances, inflation
Give me an example where you have given advice about the development options /sensitivity analysis/risk analysis/VE options in relation to a development design.
Whilst working for the Surface transport team in producing a cost estimate as part of the Quietway cycle scheme in south east London I advised the route and cycle path could be varied to accommodate the client’s budget. On busier road sections using a physically separated road cycle path would be more a more expensive option in terms of construction and space requirements but increase safety. On quieter sections the use of a shared in roadway bikeway could be utilised to extend the cycle path along the intended route and remain within the client’s budget.
What is an order of cost estimate?
The determination of possible cost of a building(s) early in design stage in relation to the employer’s fundamental requirements.
What is typically included in an order of cost estimate?
- Facilitating Works
- Building Works
- Main Contractor Overhead
- Profit Project/Design Team Fees
- Risk Allowance
- Inflation
What exclusions might you make in an order of cost estimate?
- VAT
- Inflation
- Legal costs
- Planning costs
- Unexpected ground conditions
- Land acquisition costs
What is the purpose of an order of cost estimate?
The purpose of an order of cost estimate is to establish if the proposed building project is affordable and, if affordable, to establish a realistic cost limit for the building project
When would you prepare an order of Cost Estimate?
RIBA Stage 0 - Strategic Definition + RIBA Stage 1 - Preparation and Briefing
What information do you need to be able to carry out an order of cost estimate?
- Location
- Purpose
- Floor Area
- Indicative Programme
- Site Conditions
- Any exclusion of inclusion requirements (EG design team fees)
What types of estimate are there?
- Order of Cost Estimate
- Cost Estimate
- Base Cost estimate
What is a cost estimate?
A forecast of the possible cost of a building based on historical data
What is a Base cost estimate?
The base cost estimate is the sum of the works cost estimate, the project/design team fees estimate and the other development/project costs estimate. Not including risk or inflation.
What are the principal components of a cost estimate?
- Construction cost
- Preliminaries
- Contractor’s OH&P
- Contingency/risk allowance
- Inflation
- Assumptions
- programme
- Exclusions
- Area Schedule
- Basis of Estimate
- Drawings / specifications list