Quantification And Costing Flashcards
How many days between construction application and due date on a standard building contract and can it be amended.
7 days (can be amended)
How many days between due date and interim cert/ payment notice on both a D&B and Standard JCT… and can it be amended
5 days (can’t amend)
How many days between the due date and the final date for payment on both a standard and D&B JCT
14 days
How many days before the final date for payment can a pay less notice be issued on a D&B and Standard JCT (can it be amended)?
5 days (can be amended)
What’s the definition of Gross internal area (GIA) as per NRM1
The area of a building measured to the internal face of the perimeter walls at each floor level
What’s the definition of Net Internal Area (NIA) as per NRM1
The usable area within a building measured to the internal face of the perimeter walls at each floor level
What areas are excluded from the GIA as per NRM1
Perimeter wall thickness
External open sided balconies
Fire escapes
Canopies
Voids over/ under structural, raked or stepped floors
Greenhouses, garden stores etc in resi property
What’s the definition of gross external area (GEA) as per NRM1
The area of a building measured externally (I.e. to the external face of the perimeter walls) at each floor level
What areas are included in the NIA as per NRM1
Atria (from base level only)
Kitchens (incl cabinets)
Areas occupied by skirting and trunking
Partition walls (unless they’re walls enclosing excluded areas)
The GEA excludes the same areas as the GIA with the exception of what
Perimeter wall thickness and external projections
Where can you find what’s included and excluded from the GIA and NIA
NRM1
IPMS
RICS Code of measuring practice 6th edition
What is NRM1
Order of cost estimating and cost planning for capital building works
What is NRM2
Detailed measurement for building works
What is NRM3
Order of cost estimating and cost planning for building maintenance works
A) NRM1 provides guidance on the quantification of building works in order to prepare what?
B) it also provides guidance on quantifying what?
A)
Order of cost estimates
Cost plans
Approximate estimates.
B)
prelims
OH&P
risk allowance
inflation
A) NRM2 establishes detailed measurement rules for building works in order to prepare what?
B) it also provides guidance on what
A)
Bills of quants
Quantified schedules of works
Schedules of rates
B)
The content structure and format of bills of quantities
A) NRM3 provides guidance on the quantification and description of maintenance works in order to prepare what?
B) it also provides guidance on what?
A)
Initial order of cost estimates
Cost plans
B)
Procurement
Cost control
Under which contracts would you issue a bill of quantities as part of the tender docs
JCT Standard and Intermediate with quants
When would a JCT Standard Building Contract with approximate quants be used
When the design is relatively developed but isn’t complete for a full Bill of Quants
What information is provided as part of the tender information in order to price for a standard building contract without quants
Drawings
Description of works
Spec or Schedule of works
What does BIM stand for
Building Information Modelling
What do the BIM dimensions provide (2D to 6D)
2D - drawings
3D - drawings
4D - time and programme
5D - cost info
6D- facilities management info
What’s the key difference between the traditional and D&B payment cycle
The D&B payment cycle doesn’t start until the contractor submits their application where’s traditional need to be valued in line with the dates even if an application isn’t submitted
What’s the difference between defined and undefined provisional sums
The contractor is expected to incorporate defined prov sums into their:
Programme
Prelims
OH&P
Design risk
How do you value prelims if an EoT has been granted but no loss and expense
Divide the prelims budget within the contract sum by the extended programme duration
What does IPMS stand for
International property measurement standards
What does NRM stand for
New rules of measurement
Whats the document which quantities are to be re measured against in a re-measurable contract
Bill of quants