Quantification And Costing Flashcards

1
Q

How many days between construction application and due date on a standard building contract and can it be amended.

A

7 days (can be amended)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How many days between due date and interim cert/ payment notice on both a D&B and Standard JCT… and can it be amended

A

5 days (can’t amend)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How many days between the due date and the final date for payment on both a standard and D&B JCT

A

14 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How many days before the final date for payment can a pay less notice be issued on a D&B and Standard JCT (can it be amended)?

A

5 days (can be amended)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What’s the definition of Gross internal area (GIA) as per NRM1

A

The area of a building measured to the internal face of the perimeter walls at each floor level

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What’s the definition of Net Internal Area (NIA) as per NRM1

A

The usable area within a building measured to the internal face of the perimeter walls at each floor level

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What areas are excluded from the GIA as per NRM1

A

Perimeter wall thickness

External open sided balconies

Fire escapes

Canopies

Voids over/ under structural, raked or stepped floors

Greenhouses, garden stores etc in resi property

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What’s the definition of gross external area (GEA) as per NRM1

A

The area of a building measured externally (I.e. to the external face of the perimeter walls) at each floor level

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What areas are included in the NIA as per NRM1

A

Atria (from base level only)

Kitchens (incl cabinets)

Areas occupied by skirting and trunking

Partition walls (unless they’re walls enclosing excluded areas)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The GEA excludes the same areas as the GIA with the exception of what

A

Perimeter wall thickness and external projections

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Where can you find what’s included and excluded from the GIA and NIA

A

NRM1

IPMS

RICS Code of measuring practice 6th edition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is NRM1

A

Order of cost estimating and cost planning for capital building works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is NRM2

A

Detailed measurement for building works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is NRM3

A

Order of cost estimating and cost planning for building maintenance works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A) NRM1 provides guidance on the quantification of building works in order to prepare what?

B) it also provides guidance on quantifying what?

A

A)
Order of cost estimates

Cost plans

Approximate estimates.

B)
prelims

OH&P

risk allowance

inflation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A) NRM2 establishes detailed measurement rules for building works in order to prepare what?

B) it also provides guidance on what

A

A)

Bills of quants

Quantified schedules of works

Schedules of rates

B)

The content structure and format of bills of quantities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

A) NRM3 provides guidance on the quantification and description of maintenance works in order to prepare what?

B) it also provides guidance on what?

A

A)
Initial order of cost estimates

Cost plans

B)
Procurement

Cost control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Under which contracts would you issue a bill of quantities as part of the tender docs

A

JCT Standard and Intermediate with quants

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

When would a JCT Standard Building Contract with approximate quants be used

A

When the design is relatively developed but isn’t complete for a full Bill of Quants

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What information is provided as part of the tender information in order to price for a standard building contract without quants

A

Drawings
Description of works
Spec or Schedule of works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What does BIM stand for

A

Building Information Modelling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What do the BIM dimensions provide (2D to 6D)

A

2D - drawings
3D - drawings
4D - time and programme
5D - cost info
6D- facilities management info

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What’s the key difference between the traditional and D&B payment cycle

A

The D&B payment cycle doesn’t start until the contractor submits their application where’s traditional need to be valued in line with the dates even if an application isn’t submitted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What’s the difference between defined and undefined provisional sums

A

The contractor is expected to incorporate defined prov sums into their:

Programme
Prelims
OH&P
Design risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
How do you value prelims if an EoT has been granted but no loss and expense
Divide the prelims budget within the contract sum by the extended programme duration
26
What does IPMS stand for
International property measurement standards
27
What does NRM stand for
New rules of measurement
28
Whats the document which quantities are to be re measured against in a re-measurable contract
Bill of quants
29
What are the 4 types of valuation method
Stage payment Milestone payment Payment against an activity schedule Valuation of the works done to date on site
30
What are the pros and cons of stage payments
High predictability of cashflow but low accuracy of works done to date
31
Pros and cons of milestone payments
High predictability of an amount due upon each milestone but a low predictability of when they become due
32
Pros and cons of an activity schedule
Provides reasonable predictability of cashflow but only reasonable accuracy of the value of works done to date
33
Pros and cons of valuation of works done to date
Lowest predictability for cashflow but most accurate for value of works done to date
34
Describe stage payments
Pre agreed amounts paid at pre set times regardless of progress
35
Describe milestone payments
Pre agreed amounts are paid upon completion of pre agreed elements
36
Describe payments against an activity schedule
At pre agreed timescales progress against an activity schedule is monitored and pre-agreed payments are made for activities which have been completed
37
Who holds the risk of having quantified the scope of work correctly from the contract docs on a standard building contract WITHOUT quants
The contractor
38
Who holds the risk that a bill of quants are accurate under a standard building contract WITH quants
The Employer
39
How are errors in the bill of quants dealt with
They are corrected and treated as variations
40
When will the bill of approx quants be re-measured
Once the design is complete
41
Who holds responsibility that the approximate bill of quants is accurate
The employer
42
In terms of valuing change, whats the benefit of having a bill of quants opposed to a priced document (e.g. a CSA)
There is more info for the QS to use for the valuation of variations
43
How would I get comfortable with the price of a variation
Benchmark the rate against comparable data
44
What does RFI stand for
Request for information
45
What does COR stand for
Change order request
46
Who submits an RFI or COR and what’s the process
Contractor submits I review by measuring against drawings and benchmarking If I agree we tell the client the request is acceptable and ask if they want it instructed If I disagree I query it with the contractor
47
Who generally controls contingency (excl contingency built into D&B contract sum)
Client
48
What contract would you expect contingency to be built into the contract sum
D&B
49
How do you manage and quantify risk
Prepare a risk register
50
How does a risk register work
Outline the initial risk and score it based on impact and likeliness Outline a mitigation method Re-score based on the mitigation method Comment if the risk is acceptable or not
51
Give an example of value engineering
Introduce a lesser spec
52
What does RCA stand for
Reinstatement cost analysis
53
What does an RCA do
Provides an assessment of the construction costs of building the scheme from the ground up for insurance purposes
54
What three elements form the build up of a variation cost
Plant, labour and material Additional OH&P Additional Prelims
55
How would you value a variation if the spec is the same but the quantity is different
Use the rates in the CSA, and re-measure quantity against drawings
56
How would you value a variation of spec changes but quantity is the same
Use the measurements from the CSA then use rate/ benchmarked rate
57
What elements have you included in a valuation
Prelims Measured works Variations Materials on/ off site Loss and expense claims Retention
58
Who physically issues the payment notices on your Leeds scheme
My Director
59
What documents do you received ahead of issuing your payment notice on Leeds
Contractors application QS valuation (myself) Compliance statements from the design team
60
Where would you check for the valuation rules
The Valuing Change black book The JCT contract clause 5.6-5.10
61
How would you value a variation if varied work is not of similar character to work in the CSA (I.e different spec and quantity)
Fair rates and prices shall be used and measurement will be taken from the latest drawings
62
How would you omit element of the contract sum
Omission will be in accordance with the values in the CSA for such work. If the item of work can’t be clearly identified in the CSA then the employer and contractor need to act fairly in agreeing the value of omission.
63
What method of valuation is used if work cannot be properly valued by measurement.
Daywork
64
What schedule of the JCT D&B and Standard Building contract deals with Contractors Quotations for valuing change
Schedule 2
65
What does schedule 2 of the D&B and standard building contracts contain
Mechanisms that enable the contractor to provide a variation quotation.
66
What should the Contractors variation quotation include
Value of the adjustment alongside relevant calculations The length of any EoT required The amount of any direct loss and expense A method statement for undertaking the variation.
67
Is the inclusion of Contractors Quotations for valuations optional?
Yes
68
Are columns included in the NIA as per IPMS
Yes
69
How do you deal with valuing prelims in case of delay
Unless it’s a relevant matter, the prelims budget in the CSA is spread across the revised duration.
70
What would you do if you received a quote from a European supplier
Convert to euros Notify client of potential import tariffs Notify client of potential exchange rates Notify client of potential delivery delays
71
Give some examples of maintenance work carried out under NRM3
Legionella testing PAT testing
72
Why was IPMS introduced
It was introduced as a global standard for consistent measurement