Project Finance Flashcards
What is a provisional sum
An allowance for an element of the works that is not defined in enough detail for tenderers to accurately price
What’s the difference between defined and undefined prov sums
The contractor is expected to incorporate defined prov sums into their:
Programme
Prelims
OH&P
Design risk
What’s the disadvantage to the client of undefined prov sums
The contractor may be entitled to an EoT and/ or additional payments when the works are undertaken
What’s a prime cost sum as per NRM1
A supply only rate for materials or goods
What costs does a prime cost sum exclude
Labour
Materials required for installation
Design fees
Prelims
OH&P
What are fluctuations
Financial adjustments made to the original contract to compensate the contractor for inflation
What’s the final account
The conclusion of the contract sum and signifies that agreed amount that the employer will pay the contractor
What’s the purpose of a final account meeting
To focus on agreeing the outstanding items.
What are the main headings in a final account statement
Contract Sum
Contract instructions
Provisional sum adjustments
Loss and expense
Liquidated damages
Fluctuations
What are Daywork allowances
Monetary allowances made for the costs of labour, plant and materials for ad-hoc work required throughout the contract where valuing by reference to contract rates isn’t appropriate.
Define change control
The administrative process that implements the contract mechanisms for instructing change
How are daywork allowances tracked
Daywork sheets submitted by the contractor and signed off by the CA and reported on a monthly basis
What’s the definition of a variation
Any change to the contract specs or drawings
Define contract instruction
The financial adjustment arising from instructions for variations to the contract works
Define loss and expense
Additional costs incurred by the contractor arising from delays or the disruption to the performance of the contract caused by the employer
What date in the contract are fluctuations calculated against
Base date
When is the 2nd retention release due
After the defects liability period
How is the 1st retention release dealt with if the final account Isn’t agreed but PC has been issued
The Employer is entitled to release only up to the amount they believe is payable under the contract until the final account is agreed