Project Finance Flashcards

1
Q

What is a provisional sum

A

An allowance for an element of the works that is not defined in enough detail for tenderers to accurately price

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What’s the difference between defined and undefined prov sums

A

The contractor is expected to incorporate defined prov sums into their:

Programme
Prelims
OH&P
Design risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What’s the disadvantage to the client of undefined prov sums

A

The contractor may be entitled to an EoT and/ or additional payments when the works are undertaken

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What’s a prime cost sum as per NRM1

A

A supply only rate for materials or goods

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What costs does a prime cost sum exclude

A

Labour

Materials required for installation

Design fees

Prelims

OH&P

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are fluctuations

A

Financial adjustments made to the original contract to compensate the contractor for inflation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What’s the final account

A

The conclusion of the contract sum and signifies that agreed amount that the employer will pay the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What’s the purpose of a final account meeting

A

To focus on agreeing the outstanding items.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the main headings in a final account statement

A

Contract Sum

Contract instructions

Provisional sum adjustments

Loss and expense

Liquidated damages

Fluctuations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are Daywork allowances

A

Monetary allowances made for the costs of labour, plant and materials for ad-hoc work required throughout the contract where valuing by reference to contract rates isn’t appropriate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Define change control

A

The administrative process that implements the contract mechanisms for instructing change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How are daywork allowances tracked

A

Daywork sheets submitted by the contractor and signed off by the CA and reported on a monthly basis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What’s the definition of a variation

A

Any change to the contract specs or drawings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Define contract instruction

A

The financial adjustment arising from instructions for variations to the contract works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Define loss and expense

A

Additional costs incurred by the contractor arising from delays or the disruption to the performance of the contract caused by the employer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What date in the contract are fluctuations calculated against

A

Base date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

When is the 2nd retention release due

A

After the defects liability period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

How is the 1st retention release dealt with if the final account Isn’t agreed but PC has been issued

A

The Employer is entitled to release only up to the amount they believe is payable under the contract until the final account is agreed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Whats the difference between patent and latent defects

A

Patent defects can be discovered via reasonable inspection

20
Q

What would the preferred scenario be for dealing with a defect prior to issuing a final account

A

Alert the contractor of the defect and give them the opportunity to make good. The final account can then be agreed as if the defect didnt happen

21
Q

What happens if the contractor doesnt make good a defect prior to issuing the final account

A

The Employer can employ a different sub-contractor and then deduct the cost from the final account

22
Q

How is a defect dealt with during the defects liability period

A

The contractor has the chance to make good at their own cost. If the defect isn’t dealt with then a separate contractor can be appointed and the cost deducted from retention

23
Q

How are liquidated damages deducted from the final account

A

Pay less notice

24
Q

Whats set off/ contra charging

A

Where the employer recovers costs from the contractor that he contractor has caused the employer to incur

25
What is the standard amount of time under a JCT that the final account should be issued
No later than 3 months after receipt of information supplied by the Contractor (can be amended)
26
What info should the contractor provide to ascertain the final account
Substantiation of variation figures Subcontractor quotes (if applicable) Daywork sheets Loss and expense claims Build up of fluctuations
27
How long does the contractor have to issue their information from PC in preparation of the final account under a JCT
3 months
28
If a final account cannot be agreed (in dispute) what are the next steps
Ideally mediation if not adjudication then arbitration/ litigation
29
What are the 4 most common reasons for not agreeing a final account
Validity of claimed variations Value of variations Liquidated damages Loss and Expense Claims
30
What should be carried out in order to ensure the final account is fair
An audit of final accounts
31
Why would final accounts need settling in the middle of a project
If the contractor or employer is going into liquidation or administration Contract is being terminated
32
Whats the purpose of a cost report
To inform the client of the forecast cost at a given time
33
What are the typical financial cost report headings on your Leeds D&B scheme
Contract sum Variations (instructed and anticipated) Loss and Expense/ Liquidated Damages Provisional Sums Risk allowance
34
What should the QS review to identify anticipated variations
Instruction requests issued by the contractor Drawing revisions Spec revisions
35
Up to which point should the cost report apply fluctuation amounts
Up to the value of work carried out to date
36
Which 3 courses of action can be taken in the case of cost increases above the brief or approved budget
Omit elements of remaining work that aren't critical for the buildings function Reduce the scale of remaining elements Reduce the spec of the remaining work
37
What should be considered when advising the client of the whole life impact of potential cost savings
Capital costs saving Renewal cost and frequency impact Operating costs Maintenance costs End of life cost
38
What should be considered when advising on the impacts of potential cost saving methods
Programme impact Other cost element impacts Statutory compliance Asset value impact Funding conditions
39
What’s the formula for calculating a prime cost sum
Prime cost = Raw materials + Direct labour
40
Do prime costs include labour for workers who directly contribute to the formation of the product
Yes
41
What are the high level cost report headings on your Leeds project
Title Contents Exec Summary Finance overview Detailed finance review Cashflow Project Risks
42
Name some finance costs (monitoring)
Interest Valuation costs Arrangement fee Exit fee Monitor fees
43
Are liquidated damages a penalty
No
44
When can liquidated damages be levied
Upon issue of a cert of non completion
45
What’s it’s called when the contract completion date has passed without an extension of time
The contract is at large
46
If a contractor says they’re in delay what can you suggest they do to get the programme back on track
Accelerate Re sequence Use float
47
How can you check that the contractor is in delay against their programme when they request an EoT
Review progress against the critical path