Design Economics And Cost Planning Flashcards
What does TPI stand for
Tender price indices
What does CPI stand for
Construction price indicies
What’s the difference between value management and value engineering
Value management is usually done at RIBA stage 0 or 1 and manages the value at a high level of the key elements
Value Engineering is done when the design is more developed and specific aspects are decided to improve value
How many numbered points are there in a cost plan as per NRM1
15
When is CPI taken
At the mid point of the construction programme
When is TPI taken
At the point of tender
Who produces SPONS
AECOM
Why is it important to have regional prices
Because material prices vary across regions (and labour if self employed)
Who produces BCIS
RICS
Are balconies included in the GEA
No
Where would you check to find out what’s included and excluded from GIA GEA and NIA
NRM1
Pros and cons of steel compared to concrete frame
Pros
Fast erection on site
Comparatively Lightweight
Gain more net internal area due to columns and beams being smaller
Cons
Inflation/ market uncertainty
Fire proofing costs
Prone to corrosion
Pros and cons of concrete frame compared to steel
Pros
Naturally Fire and Water resistant
Easy to mould and shape
Energy efficient when producing
Higher compressive strength
CONS
Low tensile strength and so requires reinforcement
Long curing time/ slower installation
Requires form work on site
What are some typical exclusions in a cost plan/ order of cost estimate
VAT
S106/ CIL
Prof fees
Finance Costs
Acquisition Costs
Inflation
What cost of advise would you give to a client at RIBA stage 1-4
Stage 1 - design was restricted to schedule of annotation and high level design aspirations. Using internal and industry data and the GIFA I could provide a high level estimate.
Stage 2-4 - Can provide an elemental costs plan which is updated as design develops based on drawings and specifications