PT M3 - Lists (Traditional Methodologies) Flashcards

1
Q

When is it recommended to use a traditional management approach?

A
  • Where there is certainty about the project’s scope

- When it is possible to plan the project in the early stages of its lifecycle.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How many processes, process groups, and knowledge areas are there in the PMBOK guide?

A
  • 49 Processes grouped into 5 Process Groups

- 10 Knowledge Areas

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

4 Step Process to the Order of Change Management (When requested by a key stakeholder)

A
  1. Register the change request
  2. Qualify and quantify the impact of the change
  3. Find Alternatives to the Change
  4. Take the Change Request to the Appropriate Business Level for Approval or Rejection
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

4 Types of Planning

A
  • Predictive Planning
  • Agile/Iterative Planning
  • Rolling Wave Planning
  • On Demand Planning
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

2 Questions to answer when you face a new project and are determining to use a traditional vs agile management approach?

A
  • What are you going to do?
  • How are you going to do it?

If you know the answer to these two questions, you are able to have certainty about the project. On the other hand, if you do not know the answer to either of these questions, you can say that you have uncertainty regarding the development of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

3 Practices that are increasingly being used in Project Resource Management

A
  • Emotional Intelligence/Emotional Quotient (EQ)
  • Self-Organizing Teams
  • Virtual/Distributed Teams
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

2 Elements Necessary to Schedule a Project

A
  • Defining Actions

- Establishing a Sequence of Actions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

4 Estimation Techniques to be Familiar w

A
  • Analogous Estimation
  • Parametric Estimation
  • Bottom-Up Estimation
  • Estimation by 3 Points/PERT
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

4 Work Breakdown Structure Levels or Hierarchy

A
  1. Key Deliverables (Top Level: the building, the garden, and the fence)
  2. Project Deliverables (break down each key deliverable into separate deliverables)
  3. Work Packages (break down each deliverable into work packages)
  4. Activities/Tasks (break down each work package into activities or tasks)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

2 Intensification Techniques used to Decrease Project Durations w/out changing the project’s scope

A
  • Crashing
  • Fast-Tracking

Both are used to compress the project timeline without changing the project’s scope while complying with restrictions, new deadlines, or other objectives in the timeline.

Never Reduce the Scope or the Quality of the Project. These requirements are agreed with the client. Reducing them would be entirely contradictory to the project manager’s code of ethics.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

This process consists of using knowledge and creating new knowledge to achieve the project objectives and contribute to organizational learning.

This process is carried out throughout the project, using mainly these two tools…

A

The Knowledge Management Process

  • Knowledge Management Tool
  • Information Management Tool
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

4 Communication Methods to be familiar w

A
  • Push
  • Pull
  • Interactive
  • Osmotic
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

3 Actions that are types of Changes in a Project

A
  • Preventative Actions
  • Defect Repair Actions
  • Corrective Actions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The 4 Stages of the Tuckman’s Scale/Theory

A
  1. Forming
  2. Storming
  3. Norming
  4. Performing
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How many subsidiary plans will you have in the project management plan?

A
  • 11

- 1 plan for each of the knowledge areas and 2 plans for the Scope knowledge area (Scope & Requirements)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

4 Dependency Attributes

A
  • Internal
  • External
  • Mandatory
  • Discretionary

Can only have 2 at a time

17
Q

4 Dependency Links

A
  • Start to Start
  • Start to Finish
  • Finish to Start
  • Finish to Finish