Project Schedule Management Terms Flashcards

1
Q

Activity List

A

The primary output of breaking down the WBS work packages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Alternative Analysis

A

The identification of more than one solution. Consider roles, materials, tools and approaches to the project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Analogous Estimating

A

A somewhat unreliable estimating approach that relies on historical information to predict what current activity durations should be.

Analogous estimating is more reliable than team member recollections. It is also known as top-down estimating and is a form of expert judgment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Bottom-Up Estimating

A

The most accurate time-and-cost estimating approach a project manager can use. This estimating approach starts at the bottom of the project and considers every activity, its predecessor and successor activities, and the exact amount of resources needed to complete each activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Control Account

A

A WBS entry that considers the time, cost and scope measurements for that deliverable within the WBS. The estimated performance is compared against the actual performance to measure overall performance for the deliverables within that control account. The specifics of a control account are documented in a control account plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Control Threshold

A

A predetermined range of acceptable variances, such as +/- 10 % off schedule.

Should the variance exceed the threshold, then project control processes and corrected actions will be enacted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Crashing

A

A schedule compression approach that adds more resources to activities on the critical path to complete the project earlier. When crashing a project, costs are added because the associated labor and sometimes resources (such as faster equipment) cause costs to increase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Critical Path

A

The path in the project network diagram that cannot be delayed, otherwise the project completion date will be late. There can be more than one critical path. Activities in the critical path have no float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Discretionary Dependencies

A

These are the preferred order of activities. Project managers should use these relationships at their discretion and should document the logic behind the decision. Discretionary dependencies allow activities to happen in a preferred order because of best practices, conditions unique to the project work or external events.

Also known as preferential or soft logic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Early Finish

A

The earliest a project activity can finish. Used in the forward pass procedure to discover the critical path and the project float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Early Start

A

The earliest a project activity can begin. Used in the forward pass procedure to discover the critical path and the project float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

External Dependencies

A

Dependencies outside of the project’s control. I.E. Delivery of equipment from a vendor, the deliverable of another project, or decision of a committee, lawsuit or expected new law

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Fast Tracking

A

A schedule compression method that changes the relationship of activities. Activities that would normally be done in sequence are allowed to be done in parallel or with some overlap.

Can be accomplished by change the Finish-Start, Start-Start, or Finish-Finish by adding lead time to downstream activities.

Adds risk to project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Finish-to-Finish

A

An activity relationship type that requires the current activity to be finished before its successor can finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Finish-to-Start

A

An activity relationship type that requires the current activity to be finished before its successor can start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Fragnet

A

A representation of a project network diagram that is often used for outsources portions of a project, repetitive work within a project or a subproject. Also called a subnet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Free Float

A

This is the total time a single activity can be delayed without affecting the early start of its immediately following successor activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Hard Logic

A

Logic that describes activities that must happen in a particular order. I.E. - the dirt must be excavated before the foundation can be built.

Also known as a Mandatory Dependency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Internal Dependencies

A

Internal relationships to the project or the organization.

I.E. The project team must create the software as part of the project’s deliverable before the software can be tested for QC

20
Q

Lag Time

A

Positive time that moves two or more activities further apart

21
Q

Late Finish

A

The latest a project activity can finish. Used in the backward pass procedure to discover the critical path and the project float

22
Q

Late Start

A

The latest a project activity can begin. Used in the backward pass procedure to discover the critical path and the project float

23
Q

Lead Time

A

Negative time that allows two or more activities to overlap where ordinarily these activities would be sequential

24
Q

Management Reserve

A

A percentage of the project duration to combat Parkinson’s Law. When project activities become late, their lateness is subtracted from the management reserve.

25
Q

Mandatory Dependencies

A

These dependencies are the natural order of activities.

I.E. - You can’t begin building your house until the foundation is in place.

Also known as Hard Logic

26
Q

Monte Carlo Analysis

A

Predicts how scenarios may work out, given any number of variables. The process doesn’t actually churn out a specific answer, but a range of possible answers.

For Example, when it is applied to a schedule it can examine the optimistic completion date, the pessimistic completion date, and the most likely completion date for each activity in the project and then predict a mean for the project schedule

27
Q

Parametric Estimate

A

A quantitatively based duration estimate that uses mathematical formulas to predict how long an activity will take based on the quantities of work to be completed

28
Q

Parkinson’s Law

A

A theory that states Work expands so as to fill the time available for its completion.

It is considered with time estimating because bloated or padded activity estimates will fill the amount of time allotted to the activity

29
Q

Planning Package

A

A WBS entry located below a control account and above the work packages. A planning package signifies that there is more planning that needs to be completed for this specific deliverable

30
Q

Precedence Diagramming Method

A

A network diagram that shows activities in nodes and the relationship between each activity. Predecessors come before the current activity and successors come after

31
Q

Project Calendars

A

Calendars that identify when the project work will occur

32
Q

Project Float

A

This is the total time the project can be delayed without passing the customer expected completion date

33
Q

Project Network Diagram

A

A diagram that visualizes the flow of the project activities and their relationships to other project activities

34
Q

Refinement

A

An update to the Work Breakdown Structure (WBS)

35
Q

Resource Breakdown Structure (RBS)

A

This is a hierarchical breakdown of the project resources by category and resource type.

I.E. - Category of Equipment, HR and Materials. Within each category, you could identify the types of equipment, HR and materials

36
Q

Resource Calendars

A

Calendars that identify when project resources are available for the project work

37
Q

Resource-Leveling Heuristic

A

A method to flatten the schedule when resources are overallocated. Resource leveling can be applied using different methods to accomplish different goals

38
Q

Rolling Wave Planning

A

The imminent work is planned in detail, while the work in the future is planned at a high level. This is a form of progressive elaboration

39
Q

Schedule Management Plan

A

A subsidiary plan to the Project Management Plan. It defines how the project schedule will be created, estimated, controlled and managed

40
Q

Soft Logic

A

The activities don’t necessarily have to happen in a specific order.

I.E. You could install the light fixtures first, then the carpet and then paint.

41
Q

Start-to-Finish

A

An activity relationship that requires an activity to start so that its successor can finish.

This is the most unusual type of activity relationship

42
Q

Start-to-Start

A

An activity relationship type that requires the current activity to start before its successor can start

43
Q

Subnet

A

A representation of a project network diagram that is often used for outsourced portions of projects, repetitive work within a project or a subproject. Also called a Fragnet

44
Q

Template

A

A previous project that can be adapted for the current project and forms that are pre-populated with organizational-specific information

45
Q

Three-Point Estimate

A

An estimating technique for each activity that requires optimistic, most likely and pessimistic estimates to be created. Based on these three estimates, an average can be created to predict how long the activity should take

46
Q

Total Float

A

This is the total time an activity can be delayed without delaying project completion

47
Q

Work package

A

The smallest item in the Work Breakdown Structure (WBS)