Project Schedule Management Terms Flashcards
Activity List
The primary output of breaking down the WBS work packages
Alternative Analysis
The identification of more than one solution. Consider roles, materials, tools and approaches to the project work
Analogous Estimating
A somewhat unreliable estimating approach that relies on historical information to predict what current activity durations should be.
Analogous estimating is more reliable than team member recollections. It is also known as top-down estimating and is a form of expert judgment
Bottom-Up Estimating
The most accurate time-and-cost estimating approach a project manager can use. This estimating approach starts at the bottom of the project and considers every activity, its predecessor and successor activities, and the exact amount of resources needed to complete each activity
Control Account
A WBS entry that considers the time, cost and scope measurements for that deliverable within the WBS. The estimated performance is compared against the actual performance to measure overall performance for the deliverables within that control account. The specifics of a control account are documented in a control account plan
Control Threshold
A predetermined range of acceptable variances, such as +/- 10 % off schedule.
Should the variance exceed the threshold, then project control processes and corrected actions will be enacted
Crashing
A schedule compression approach that adds more resources to activities on the critical path to complete the project earlier. When crashing a project, costs are added because the associated labor and sometimes resources (such as faster equipment) cause costs to increase
Critical Path
The path in the project network diagram that cannot be delayed, otherwise the project completion date will be late. There can be more than one critical path. Activities in the critical path have no float
Discretionary Dependencies
These are the preferred order of activities. Project managers should use these relationships at their discretion and should document the logic behind the decision. Discretionary dependencies allow activities to happen in a preferred order because of best practices, conditions unique to the project work or external events.
Also known as preferential or soft logic
Early Finish
The earliest a project activity can finish. Used in the forward pass procedure to discover the critical path and the project float
Early Start
The earliest a project activity can begin. Used in the forward pass procedure to discover the critical path and the project float
External Dependencies
Dependencies outside of the project’s control. I.E. Delivery of equipment from a vendor, the deliverable of another project, or decision of a committee, lawsuit or expected new law
Fast Tracking
A schedule compression method that changes the relationship of activities. Activities that would normally be done in sequence are allowed to be done in parallel or with some overlap.
Can be accomplished by change the Finish-Start, Start-Start, or Finish-Finish by adding lead time to downstream activities.
Adds risk to project
Finish-to-Finish
An activity relationship type that requires the current activity to be finished before its successor can finish
Finish-to-Start
An activity relationship type that requires the current activity to be finished before its successor can start
Fragnet
A representation of a project network diagram that is often used for outsources portions of a project, repetitive work within a project or a subproject. Also called a subnet
Free Float
This is the total time a single activity can be delayed without affecting the early start of its immediately following successor activities
Hard Logic
Logic that describes activities that must happen in a particular order. I.E. - the dirt must be excavated before the foundation can be built.
Also known as a Mandatory Dependency