Project Cost Management Terms Flashcards

1
Q

Actual Cost (AC)

A

The actual amount of monies the project has spent to date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Analogous Estimating

A

An approach that relies on historical information to predict the cost of the current project.

Also known as top-down estimating and is the least reliable of all the cost-estimating approaches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Bottom-Up Estimating

A

Estimating approach that starts from zero, accounts for each component of the WBS and arrives at a sum for the project. It is completed with the project team and can be one of the most time-consuming and most reliable methods to predict project costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Budget Estimate

A

Somewhat broad estimate and is used early in the planning processes and also in top-down estimates. The range of variance for the estimate can be from -10% to +25 %

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Commercial Database

A

A cost-estimating approach that uses a database, typically software-driven, to create the cost estimate for a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Contingency Reserve

A

A contingency allowance to account for overruns in costs. Contingency allowances are used at the project manager’s discretion and with management’s approval to counteract cost overruns for scheduled activities and risk events

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Cost Aggregation

A

Costs are parallel to each WBS work package. The costs of each work package are aggregated to their corresponding control accounts. Each control account is then aggregated to the sum of the project costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost Baseline

A

A time-lapse exposure of when the project monies are to be spent in relation to cumulative values of the work completed in the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Cost Budgeting

A

Cost aggregation is achieved by assigning specific dollar amounts for each of the scheduled activities or, more likely, for each of the work packages in the WBS. Cost Budgeting applies the cost estimates over time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Cost Change Control System

A

A system that examines any changes associated with scope changes, the cost of materials, and the cost of any other resources, and the associated impact on the overall project cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Cost Management Plan

A

Dictates how cost variances will be managed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Cost of Poor Quality

A

The monies spent to recover from not adhering to the expected level of quality.

Examples may include rework, defect repair, loss of life/limb because of safety precautions, loss of sales and loss of customers.

Also known as the cost of non-conformance to quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Cost of Quality

A

The monies spent to attain the expected level of quality within a project.

I.E. - training, testing and safety precautions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Cost Performance Index (CPI)

A

Measures the project based on its financial performance.

Formula:
CPI = EV/AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Cost Variance (CV)

A

The difference of the earned value amount and the cumulative actual costs of the project

CV = EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Definitive Estimate

A

Estimate type is one of the most accurate. It’s used late in the planning processes and is associated with bottom-up estimating.

You need the WBS in order to create the definitive estimate.

Range of variance can be from -5% to +10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Direct Costs

A

Costs attributed directly to the project work and cannot be shared among projects (i.e. - airfare, hotels, etc.)

18
Q

Earned Value (EV)

A

Earned value is the physical work completed to date and the authorized budget for that work. It is the percentage of the BAC that represents the actual work completed in the project

19
Q

Estimate at Completion (EAC)

A

These forecasting formulas predict the likely completed costs of the project based on current scenarios within the project

20
Q

Estimate to Complete (ETC)

A

An Earned Value Management formula that predicts how much funding the project will require to be completed.

3 variations of this formula are based on conditions the project may be experiencing

21
Q

Fixed Costs

A

Costs that remain constant throughout the life of the project

22
Q

Funding Limit Reconciliation

A

An organization’s approach to managing cash flow against the project deliverables based on a schedule, milestone accomplishment or data constraints

23
Q

Indirect Costs

A

Costs that are representative of more than one project (i.e. utilities for the organization, access to a training room, PM Software license, etc.)

24
Q

Known Unknown

A

An event that will likely happen within the project, but when it will happen and to what degree is unknown.

These events, such as delays, are usually risk-related

25
Q

Learning Curve

A

An approach that assumes the cost per unit decreases the more units workers complete, because workers learn as they complete the required work

26
Q

Oligopoly

A

A market condition where the market is so tight that the actions of one vendor affect the actions of all the others

27
Q

Opportunity Cost

A

The total cost of the opportunity that is refused to realize an opposing opportunity

28
Q

Parametric Estimating

A

An approach using a parametric model to extrapolate what costs will be needed for a project (i.e. cost per hour or cost per unit).

It can include variables and points based on conditions

29
Q

Planned Value (PV)

A

Planned value is the work scheduled and the budget authorized to accomplish that work.

It is the percentage of the BAC that reflects where the project should be at this point in time

30
Q

Project Variance

A

The final variance, which is discovered only at the project’s completion.

Formula: VAR = BAC - AC

31
Q

Regression Analysis

A

This is a statistical approach to predicting what future values may be, based on historical values. Regression analysis creates quantitative predictions based on variables within one value to predict variables in another.

This form of estimating relies solely on pure statistical math to reveal relationships between variables and to predict future values

32
Q

Reserve Analysis

A

Cost reserves are for unknown unknowns within a project.

The management reserve is not part of the project cost baseline, but is included as part of the project budget

33
Q

Rough Order of Magnitude

A

This rough estimate is used during the initiating processes and in top-down estimates. The range of variance for the estimate can be form -25% to +75%

34
Q

Schedule Performance Index (SPI)

A

Measures the project based on its schedule performance

Formual: SPI = EV/PV

35
Q

Schedule Variance (SV)

A

The difference between the earned value and the planned value.

Formula: SV = EV-PV

36
Q

Single Source

A

Many vendors can provide what your project needs to purchase, but you prefer to work with a specific vendor

37
Q

Sole Source

A

Only one vendor can provide what your project needs to purchase.

38
Q

Sunk Costs

A

Monies that have already been invested in a project

39
Q

To-Complete Performance Index

A

A formula to forecast the likelihood of a project to achieve its goals based on what’s happening in the project right now.

There are 2 different flavors of the TCPI, depending on what you want to accomplish.

  1. If you want to see if your project can meet the budget at completion, Formula is: TCPI = (BAC-EV)/(BAC-AC)
  2. If you want to see if your project can meet the newly created estimate at completion, Formula is: TCPI = (BAC-EV)/(EAC-AC)
40
Q

Variable Costs

A

Costs that change based on the project conditions applied in the project (the number of meeting participants, the supply of and demand for materials, etc.)

41
Q

Variance

A

The difference between what was expected and what was experienced

42
Q

Variance at Completion (VAC)

A

A forecasting formula that predicts how much of a variance the project will likely have based on current conditions within the project.

Formula: VAC = BAC-EAC