Project Cost Management Terms Flashcards
Actual Cost (AC)
The actual amount of monies the project has spent to date
Analogous Estimating
An approach that relies on historical information to predict the cost of the current project.
Also known as top-down estimating and is the least reliable of all the cost-estimating approaches
Bottom-Up Estimating
Estimating approach that starts from zero, accounts for each component of the WBS and arrives at a sum for the project. It is completed with the project team and can be one of the most time-consuming and most reliable methods to predict project costs
Budget Estimate
Somewhat broad estimate and is used early in the planning processes and also in top-down estimates. The range of variance for the estimate can be from -10% to +25 %
Commercial Database
A cost-estimating approach that uses a database, typically software-driven, to create the cost estimate for a project
Contingency Reserve
A contingency allowance to account for overruns in costs. Contingency allowances are used at the project manager’s discretion and with management’s approval to counteract cost overruns for scheduled activities and risk events
Cost Aggregation
Costs are parallel to each WBS work package. The costs of each work package are aggregated to their corresponding control accounts. Each control account is then aggregated to the sum of the project costs
Cost Baseline
A time-lapse exposure of when the project monies are to be spent in relation to cumulative values of the work completed in the project
Cost Budgeting
Cost aggregation is achieved by assigning specific dollar amounts for each of the scheduled activities or, more likely, for each of the work packages in the WBS. Cost Budgeting applies the cost estimates over time
Cost Change Control System
A system that examines any changes associated with scope changes, the cost of materials, and the cost of any other resources, and the associated impact on the overall project cost
Cost Management Plan
Dictates how cost variances will be managed
Cost of Poor Quality
The monies spent to recover from not adhering to the expected level of quality.
Examples may include rework, defect repair, loss of life/limb because of safety precautions, loss of sales and loss of customers.
Also known as the cost of non-conformance to quality
Cost of Quality
The monies spent to attain the expected level of quality within a project.
I.E. - training, testing and safety precautions
Cost Performance Index (CPI)
Measures the project based on its financial performance.
Formula:
CPI = EV/AC
Cost Variance (CV)
The difference of the earned value amount and the cumulative actual costs of the project
CV = EV - AC
Definitive Estimate
Estimate type is one of the most accurate. It’s used late in the planning processes and is associated with bottom-up estimating.
You need the WBS in order to create the definitive estimate.
Range of variance can be from -5% to +10%