Project schedule management terms Flashcards

1
Q

Activity list

A

The primary output of breaking down the WBS work packages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Alternative analysis

A

The identification of more than one solution. Consider roles, materials, tools, and approaches to the project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Analogous Estimating

A

A somewhat unreliable estimating approach that relies on historical information to predict what current activity durations should be.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Bottom-Up Estimating

A

Most accurate estimating approach a PM can use. This estimating approach starts at the bottom of the project and considers every activity, its predecessor and successor activites and the exact amount of resources each needs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Control Account

A

A WBS entry that considers the time, cost, and scope measurements for that deliverable within the WBS. The estimated performance is compared against the actual performance for the deliverables within that control account.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Control Threshold

A

A predetermined range of acceptable variances, such as +/- 10 percent of schedule. Should the variance exceed the threshold, then project control processes and corrected actions will be enacted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Crashing

A

Schedule compression approach that adds more resources to activities on the critical path to complete the project earlier. Doing this adds cost because of associated labor and sometimes resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Critical Path

A

The path in the project network diagram that cannot be delayed, otherwise the project completion date will be late. Activities on this path have no float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Discretionary Dependencies

A

These dependencies are the preferred order of activities. PM’s should use these relationships at their discretion and should document the logic behind the decision

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Early Finish

A

The earliest a project can finish. Used in the forward pass procedure to discover the critical path and the project float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Early Start

A

The earliest a project activity can begin. Used in the forward pass procedure to discover the critical path and the project float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

External Dependencies

A

Dependencies outside the projects control. Examples include the delivery of equipment from a vendor, the deliverable of another project, or the decision of a committee, lawsuit, or expected new law

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Fast Tracking

A

Schedule compression that changes the relationship of activities. Activities that would normally be done in sequence are allowed to be done in parallel or with some overlap. Adds risk to the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Finish to finish

A

Activity relationship type that requires the current activity to be finished before its successor can finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Finish to start

A

Activity relationship that requires the current activity to be finished before its successor can start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Fragnet/ Subnet

A

A representation of a project network diagram that is often used for outsourced portions of a project, repetitive work within a project, or a subproject.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Free float

A

The total time a single activity can be delayed without affecting the early start of its immediately following successor activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Hard Logic

A

Logic that describes activities that must happen in a particular order.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Internal Dependencies

A

Internal relationships to the project or organization.

20
Q

Lag Time

A

Positive time that moves two or more activities further apart

21
Q

Late finish

A

The latest a project activity can finish. Used in the backward pass procedure to discover the critical path and the project float

22
Q

Late start

A

The latest a project activity can begin

23
Q

Lead time

A

Negative time that allows two or more activities to overlap where ordinarily these activities would be sequential

24
Q

Management Reserve

A

A % of the project duration to combat Parkinson’s law. When project activities become late, their lateness is subtracted from the management reserve

25
Q

Mandatory Dependencies

A

Dependencies that are nature for the order of activities. Can’t build a house before foundation poured for example

26
Q

Monte Carlo Analysis

A

Simulation approach that predicts how scenarios may work out, given any number of variables. Doesn’t churn out a specific answer, but a range of possible answers.

27
Q

Parametric Estimate

A

A quantitatively based duration estimate that uses mathematical formulas to predict how long an activity will take based on the quantities of work to be completed

28
Q

Parkinson’s Law

A

Theory that states work will expand to fill the time available for its completion.

29
Q

Planning Package

A

A WBS entry located below a control account and above the work packages. This signifies that there is more planning that needs to be completed for this specific deliverable

30
Q

Precedence Diagramming Method

A

A network diagram that shows activities in nodes and relationship between each activity. Predecessors come before the current activity, and successors come after the current activity

31
Q

Project Calendars

A

Calendars that identify when the project work will occur

32
Q

Project Float

A

The total time the project can be delayed without passing the customer expected completion date

33
Q

Project network diagram

A

A diagram that visualizes the flow of the project activities and their relationships to other project activities

34
Q

Refinement

A

An update to the WBS

35
Q

Resource Breakdown Structure

A

A hierarchical breakdown of the project resources by category and resource type. For ex : Category of equipment, a category for HR. And within each you have the type of resources you’ll use

36
Q

Resource Calendars

A

Calendars that identify when project resources resources are available for the project work

37
Q

Resource-leveling heuristic

A

A method to flatten the schedule when resources are overallocated. Can be applied using different methords to accomplish different goals. One of the most common methods is to ensure that workers are not overextended on activities

38
Q

Rolling wave planning

A

The imminent work is planned in detail, while the work in the future is planned at a high level. A form of progressive elaboration

39
Q

Schedule Management Plan

A

A subsidiary plan in the PM plan. Defines how the project schedule will be created, estimated, controlled, and managed

40
Q

Soft logic

A

The activities don’t necessarily have to happen in a specific order. Example : you could install the lights before the carpet

41
Q

Start To Finish

A

Activity relationship that requires an activity to start so that its successor can finish. The most unusual of all the activity relationship types

42
Q

Start to Start

A

Activity relationship type that requires the current activity to start before it’s successor can start

43
Q

Subnet / Fragnet

A

Representation of a project network diagram that is often used for outsourced portions of projects, repetitive work within a project, or a subproject.

44
Q

Template

A

A previous project can be adapted for the current project and forms that are pre-populated with organization-specific information.

45
Q

3 point estimating

A

Estimating Technique for each activity that requires optimistic, most likely, and pessimistic estimateds be created. Based on these 3, an average can be created to predict how long the activity should take

46
Q

Total float

A

The total time an activity can be delayed without delaying project completion

47
Q

The smallest item in a WBS

A

Work Package