Project schedule management terms Flashcards
Activity list
The primary output of breaking down the WBS work packages
Alternative analysis
The identification of more than one solution. Consider roles, materials, tools, and approaches to the project work
Analogous Estimating
A somewhat unreliable estimating approach that relies on historical information to predict what current activity durations should be.
Bottom-Up Estimating
Most accurate estimating approach a PM can use. This estimating approach starts at the bottom of the project and considers every activity, its predecessor and successor activites and the exact amount of resources each needs
Control Account
A WBS entry that considers the time, cost, and scope measurements for that deliverable within the WBS. The estimated performance is compared against the actual performance for the deliverables within that control account.
Control Threshold
A predetermined range of acceptable variances, such as +/- 10 percent of schedule. Should the variance exceed the threshold, then project control processes and corrected actions will be enacted
Crashing
Schedule compression approach that adds more resources to activities on the critical path to complete the project earlier. Doing this adds cost because of associated labor and sometimes resources
Critical Path
The path in the project network diagram that cannot be delayed, otherwise the project completion date will be late. Activities on this path have no float
Discretionary Dependencies
These dependencies are the preferred order of activities. PM’s should use these relationships at their discretion and should document the logic behind the decision
Early Finish
The earliest a project can finish. Used in the forward pass procedure to discover the critical path and the project float
Early Start
The earliest a project activity can begin. Used in the forward pass procedure to discover the critical path and the project float
External Dependencies
Dependencies outside the projects control. Examples include the delivery of equipment from a vendor, the deliverable of another project, or the decision of a committee, lawsuit, or expected new law
Fast Tracking
Schedule compression that changes the relationship of activities. Activities that would normally be done in sequence are allowed to be done in parallel or with some overlap. Adds risk to the project
Finish to finish
Activity relationship type that requires the current activity to be finished before its successor can finish
Finish to start
Activity relationship that requires the current activity to be finished before its successor can start
Fragnet/ Subnet
A representation of a project network diagram that is often used for outsourced portions of a project, repetitive work within a project, or a subproject.
Free float
The total time a single activity can be delayed without affecting the early start of its immediately following successor activities
Hard Logic
Logic that describes activities that must happen in a particular order.